This document is a Technical Specifications Exhibit for the Oregon Department of Transportation's Conference Room Expansion project located at 3313 Bret Clodfelter Way in The Dalles, Oregon. The scope of work involves expanding an existing conference room by removing a room divider partition and performing associated renovation tasks, including demolition of an existing wall, in-wall electrical work, wall patching, flooring patch, rough framing, painting, and ceiling grid framing. Specific work includes removal of the existing wall, installation of new flooring, rough framing, drywall installation with tape and texture, and wall painting.

The technical specifications provide detailed requirements for construction materials and processes across multiple divisions, including Rough Carpentry (specifying Douglas Fir lumber and plywood standards), Finish Carpentry (requiring AWI "Custom" grade with Douglas Fir materials), Gypsum Drywall (detailing panel thickness and moisture resistance), and Painting (outlining paint systems from manufacturers like Rodda, Fuller-O'Brien, and Sherwin-Williams). The painting specifications include both interior and exterior coating requirements, with specifications for different surfaces such as gypsum wallboard, concrete masonry units, and galvanized metal, and emphasize low VOC compliance with Green Seal Standard GS-11.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 1

TECHNICAL SPECIFICATIONS

Oregon Department of Transportation

The Dalles Conference Room Expansion

Address: 3313 Bret Clodfelter Way # D, The Dalles, OR 97058

SCOPE OF WORK / SUMMARY OF WORK

Expansion of existing conference room by removing room divider partition and associated work including demolition of existing wall and in wall electrical, wall patching, flooring patch, rough framing, painting, ceiling grid framing, and work as shown on Exhibit 2 - Plans.

Work includes:

• Removal of existing wall.

• Installation of new flooring.

• Rough framing, drywall and tape and texture

• Painting of walls

Specifications

Division 6 Rough Carpentry

• Framing Lumber: KD Douglas Fir, sanded four sides #2.

• Plywood:

o US Product Standard I-83.

o APA Grades: Exposed Surfaces C.

o Display APA Grade Mark on each piece.

o Thickness per drawings.

o Oriented Strand Board is not allowed.

Division 6 Finish Carpentry

• Conform to AWI “Custom” grade.

• Species: Douglas Fir

• Grain: Vertical

• Surface texture: Smooth

Division 9 Gypsum Drywall

• Panels:

o Thickness: 5/8”, Type X.

o Tapered edges conforming to ASTM C-36.

o Mold and moisture resistant conforming to ASTM C1396.

o Joint system: ASTM C745 as recommended by panel manufacturer.

Division 9 Painting

• Paint systems based on Rodda, Fuller-Obrien and Sherwin-Williams or approved equal.

o Interior Coatings.

GWB: Primer: 1 coat wall primer sealer. Finish: 2 coats acrylic latex semi-gloss enamel.

CMU: Primer: CMU block filler. Finish: 2 coats acrylic latex semi-gloss enamel.

Galvanized Metal: 1 coat galvanized iron primer. Finish 2 coats semi-gloss alkyd enamel.

Low VOC meeting Green Seal Standard GS-11.

o Exterior Coatings.

Cement Fiber Siding and trim: Prime: Face and edges prior to installation. Finish: 2 coats acrylic latex eggshell sheen exterior house paint.

Galvanized Metal: Prime: 1 coat galvanized iron primer. Finish 2 coats semi-gloss alkyd enamel.

Color as selected by Construction Project Manager.