This is a Notice of Intent to Award issued by the Oregon Department of Transportation (ODOT) Procurement Office for Specifications for National Bridge Inventory (SNBI) Services (RFP S-73000-00013359). The document notifies Fickett Structural Solutions, Inc. of its selection as one of seven top-ranked firms for contract negotiations to provide bridge inspection and data collection services across Oregon. The RFP solicitation was originally issued with an October 15, 2025 proposal submission deadline, with contract services expected to commence in October 2025 and continue for approximately four years. The procurement encompasses seven geographic regions (Areas 1-7) in Oregon, with Area 2 awarded to Fickett Structural Solutions, Inc. The services include comprehensive bridge inspections, traffic control, project management, and seasonal inspections designed to optimize efficiency during low stream or canal flows. ODOT's Project Manager, Joel Boothe, will serve as the primary contact for negotiations regarding the statement of work (SOW), schedule of performance, and costs. The negotiation phase is expected to be completed within a specified timeline: SOW discussion and revision within 10 business days, Breakdown of Costs (BOC) submission within 10 business days of final scope agreement, legal sufficiency review within 15-20 business days, and contract execution within 6-8 days thereafter, with Notice to Proceed issued within one day of execution.
The contract will be structured as a fixed-price agreement with costs to be negotiated through submission of a Breakdown of Costs that must demonstrate Disadvantaged Business Enterprise (DBE) subcontractor utilization meeting ODOT's 15.37% participation goal for federally funded contracts. Funding for the contract derives from the Federal Highway Administration (FHWA). Competing proposers have until 2:00 p.m. on December 19, 2025 to submit written selection protests. Award submittal requirements include billing rate information, cost disclosure questionnaires, certificates of insurance, lists of subconsultants, responsibility inquiry forms, and business registry numbers. ODOT offers optional ACH direct deposit payment authorization to expedite consultant payments and encourages consultants to extend ACH payment options to their subcontractors. No work is authorized until the contract is executed and the consultant receives written Notice to Proceed from the ODOT Project Manager.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00013359_Attachment A _Sample Contract final.docx | DOCX document | |
| 00013359_Attachment C_Proposal Cover Sheet.docx | DOCX document | |
| 00013359_ITA_Area 7.pdf | ||
| 00013359_RFP final.docx | DOCX document | |
| 00013359_ITA_Area 1.pdf | ||
| 00013359_ITA_Area 5.pdf | ||
| 00013359_Attachment D_Area Map.pdf | ||
| 00013359_Attachment E_Location List.xlsx | XLSX spreadsheet | |
| 00013359_ITA_Area 3.pdf | ||
| 00013359_EvaluationScoreMatrixSummary.pdf | ||
| 00013359_ITA_Area 6.pdf | ||
| 00013359_ITA_Area 4.pdf | ||
| RFP 5890-0 Summer EBT -Notice of Intent to Award.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Transportation Procurement Office
355 Capitol St NE, MS#3-3 Salem, OR, 97301
Phone: (503) 986-2710 Fax: (503) 986-5790
OREGON DEPARTMENT OF TRANSPORTATION
Notice of Intent to Award
DATE: December 12, 2025
TO: Fickett Structural Solutions, Inc.
SUBJECT: Intent to Award for RFP Specifications for National Bridge Inventory (“SNBI”) Services (S-73000-00013359)
AREA AWARDED: Area 2
Fickett Structural Solutions, Inc. is one of the seven top-ranked firms selected for negotiations of a contract to provide Personal Services as specified in the above referenced RFP. The scores and rankings of all Proposers are shown in the score matrix accompanying this notice. The award submittal requirements stated in the RFP are summarized in Attachment 1 of this notice.
Joel Boothe will be the ODOT Project Manager (PM) for this Project. ODOT’s PM will initiate contact with Consultant and will be the primary contact for negotiation of the statement of work (SOW), schedule of performance and costs under the contract. Following discussion and agreement on the SOW, a Breakdown of Costs (BOC) must be completed (using the BOC, BOC-CPFF or BOC- NBR as applicable) and submitted to ODOT’s PM. A BOC must demonstrate subcontractor utilization to meet the Disadvantaged Business Enterprise (DBE) goal set forth in the RFP. To set expectations for the contracting phase, listed below is a schedule for completing the SOW, preparing a BOC, completing negotiations, and securing approvals for both the Consultant and ODOT to follow:
Activity Responsible Party Business Days
N eg ot ia tio ns
Establish work session to discuss the SOW with Consultant
ODOT PM Within 5-10 days of this notice (days depend on size and complexity of the project) Respond to work session with comments/edits to SOW Consultant Within 5 days of work session Respond to SOW comments/edits ODOT PM Within 3 days of receipt of Consultant comments/edits
Submission of BOC / Billing Rates Consultant Within 5-10 days of final ODOT scope (days depend on size and complexity of the project)
Activity Responsible Party Business Days Respond to BOC, billing rates, negotiate, and
Submit for legal sufficiency
ODOT PM / OPO
OPO
Within 5-10 days of Consultant submission of the BOC (days depend on the size and complexity of the project) Legal Sufficiency OPO, ODOT PM, and DOJ Within 15 (Mini- Solicitation) & 20 (Formal) days of submission by ODOT PM Signature routing and execution OPO, Consultant, and ODOT Expenditure Authority (if required)
Within 6-8 days from initial routing
Issue Notice to Proceed (NTP) ODOT PM 1 day after execution
Negotiations are anticipated to be completed (ready to submit to for legal sufficiency) within the schedule set forth in this notice.
If the schedule for negotiations cannot be met and the Consultant and ODOT are negotiating in good faith, additional time may be mutually agreed upon.
If agreement on costs, tasks, or other WOC requirements cannot be reached within this time frame, ODOT may terminate the negotiations and begin negotiations with the next highest ranked firm as provided in the solicitation and governing Oregon Administrative Rules (OARs).
Note that no work is authorized until the contract is executed and Consultant has received a written NTP from the ODOT PM.
Because this notice is being emailed, the date of this notice will start the protest period for competing proposers to submit a written selection protest (REF Section 1.3.2 of the RFP). Any proposer who claims to have been adversely affected or aggrieved by the selection of a higher ranked proposer must deliver a written selection protest to my attention and received at the email address below no later than 2:00 p.m. on December 19, 2025. ODOT shall not consider a selection protest submitted after the deadline established herein. To be adversely affected or aggrieved, a protestor must demonstrate that the protester was ranked higher than other selected proposers and that higher ranked proposers are ineligible for selection.
ODOT would like to thank each Proposer for your time and efforts in preparing a response to this solicitation.
Sincerely, Sarika Herigstad Phone: 503.779.7094| Sarika.Herigstad@odot.oregon.gov mailto:Sarika.Herigstad@odot.oregon.gov
Attachment 1 – Award Submittal Requirements
Please email to me, the Contract Coordinator, the following items if marked as “REQUIRED” in the RFP (see detailed requirements and due date for each item in Section 3 of the RFP).
• Billing Rate Information
• Cost Disclosure Questionnaire
• Breakdown of Costs
• Certificates of Insurance
• COI Disclosure
• List of Subconsultants
• Responsibility Inquiry form
• Business Registry Number
Direct Deposit via Automated Clearing House (ACH). For Consultants that receive ongoing monthly payments from Agency on one or more contracts or work orders, Agency prefers making Consultant payments via ACH direct deposit. While not required, if Consultant has not previously authorized ACH direct deposit and would prefer ACH to expedite transfer of payments after invoices are approved, Consultant must complete a Vendor ACH Authorization form and submit to Agency per the instructions on the form. To expedite Consultant’s payments to its subcontractors, if applicable, Consultant should make reasonable efforts to offer ACH direct deposit payments.
https://www.oregon.gov/ODOT/Forms/2ODOT/7310781.pdf https://www.oregon.gov/ODOT/Forms/2ODOT/7310781.pdf
File details come from the government source that posted it. Updated .