5- Exhibit B- Statement of Work_REDLINE.docx
DOCX document 2 MB Posted
- Attached to
- Groundwater Sampling and Geochemical Testing Federal contract opportunity
- Solicitation number
- 0000313-CC-25
- Issued by
- Department of Energy
About this file
This document is a Statement of Work (SOW) for groundwater sampling and geochemical testing services at the Nevada National Security Site (NNSS) for the Defense Nuclear Nonproliferation Program's Rock Valley Direct Comparison (RV/DC) project. The subcontractor will collect groundwater samples from a core boring drilled to approximately 7,000 feet below ground surface, specifically at a depth of 6,398 +/- 164 feet. Required geochemical testing includes pH, salinity, total dissolved solids, and cation/anion analysis for sulfate and hydrogen sulfide.
Key technical requirements mandate that sampling equipment must operate at temperatures up to 185°F, pressures up to 2,600 psi, and collect samples in a 3.77-inch diameter borehole. The work will be performed in Area 27 of the NNSS, approximately 14 miles northwest of Mercury, Nevada. The subcontractor must provide all necessary equipment, submit a detailed sampling plan, provide field logs within 24 hours of collection, and be able to mobilize within 730 days' notice, with field operations to be completed between 30-45 days from notice. On-site personnel cannot be foreign nationals, and all sampling and testing must be coordinated with the Subcontract Technical Representative.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MISSION SUPPORT AND TEST SERVICES, LLC
FIRM-FIXED-PRICE SERVICE SUBCONTRACT
EXHIBIT B
STATEMENT OF WORK, SPECIFICATIONS AND DRAWINGS
TABLE OF CONTENTS
NO. TITLE PAGE
| B-1 | Scope/Background | 2 |
| B-2 | Requirements | 2 |
| B-3 | Technical Specifications | 4 |
| B-4 | Drawings | 4 |
| B-5 | Delivery & Work Location | 7 |
| B-6 | Clearance Requirements | 8 |
| B-7 | Specialized Experience/Specific Training/Specific Certifications | 8 |
| B-8 | Environmentally Preferable Products | 9 |
| B-9 | Attachments | 9 |
| B-10 | Submittals | 10 |
B-1 Scope/Background
1. Scope: This Statement of Work (SOW) defines the requirements to conduct groundwater sampling services and geochemical testing for the core boring to be drilled at the Rock Valley Direct Comparison (RV/DC) Testbed site. The core boring will be drilled by others under a separate subcontract. The core boring is hereinafter referred to as the Corehole (CH) in this document.
2. Project Background: The work consists of collecting groundwater samples and performing geochemical analysis to support the Defense Nuclear Nonproliferation Program’s RV/DC project at the Nevada National Security Site (NNSS). A small diameter CH will be drilled to a total depth (TD) of approximately 7,000 ft (2,134 m) below ground surface (bgs). The CH will be cased from the surface to 4,000 ft (1,219 m) bgs with an inner diameter (ID) no smaller than 3.9 inch (99 mm). The CH will be open hole, with a diameter greater than or equal to 3.7 in (93.98 mm), between 4,000 ft (1,219 m) bgs and TD. Groundwater samples will be collected at a depth of 6,398 +164 ft/-656.2 ft (1,950 +50 m/-200 m) bgs. Chemical analysis will be performed on the collected groundwater samples. Groundwater sampling will occur at the end of CH drilling, and the drilling subcontractor will pump at least three well volumes of water to purge drilling fluids. The well will sit for a short period prior to groundwater sample collection. The drillers will be on site during sample collection.
3. General Site Information:
3.1. The Nevada National Security Site (NNSS) is a U.S. Department of Energy, National Nuclear Security Administration (NNSA) installation, operated by Mission Support and Test Services, LLC (CONTRACTOR), comprising approximately 3,561 square kilometers (1,375 square miles) of federally owned land located in southeastern Nye County, Nevada. Located approximately 105 kilometers (65 miles) northwest of Las Vegas, Nevada, the NNSS is accessed from U.S. Highway 95 toward Mercury (see Figure 1) The RV/DC project site is located in Area 27, approximately 14 miles northwest of Mercury (see Figure 2). The CH will be installed on the center of 3 drill pads that will be constructed on site (see Figure 3).
3.2. The CONTRACTOR also operates the North Las Vegas Facility (NLV); the Remote Sensing Lab at Nellis AFB, North Las Vegas, NV (RSLN); the Remote Sensing Lab at Andrews AFB, Maryland (RSLA); Special Technologies Lab at Santa Barbara, CA (STL); Livermore Operations at Livermore, CA (LO); and Los Alamos Operations at Los Alamos, NM (LAO).
B-2 Requirements
1. General: The SUBCONTRACTOR shall provide experienced groundwater sample technicians, equipment operators, and all related equipment to successfully collect groundwater samples as describe herein. The SUBCONTRACTOR shall perform geochemical analysis on the collected samples for the constituents/properties described in section 2.2.
2. Detailed Requirements: SUBCONTRACTOR shall complete the following:
2.1. Sample Collection:
2.1.1. Groundwater samples shall represent the natural geochemical state of the aquifer
2.1.2. Groundwater samples shall be acquired at a depth of 6,398 +164 ft /-656.2 ft (1,950 +50 m/-200 m) bgs
2.1.3. In the case that samples cannot be acquired at the depth requested in 2.1.2 due to adverse hole conditions, the collection depth may be adjusted with approval of the CONTRACTOR’s Subcontract Technical Representative (STR)
2.1.4. The number and volume of samples shall be acquired to at least meet the testing requirements specified in 2.2
2.1.5. Sampling equipment shall be clean and decontaminated before samples are acquired
2.2. Groundwater samples shall be geochemically tested for, at a minimum, the following:
2.2.1. pH
2.2.2. Salinity
2.2.3. Total Dissolved Solids
2.2.4. Cation/Anion Analysis including
2.2.4.1. Sulfate (SO42-)
2.2.4.2. Hydrogen Sulfide (H2S)
2.3. Tests listed in 2.2 may be offered individually or as part of a standard General Fluid Chemistry suite as provided by the SUBCONTRACTOR
2.4. Additional requirements to be performed by the SUBCONTRACTOR shall include:
2.4.1. On-site personnel shall not be foreign nationals
2.4.2. Work with the STR to coordinate sampling collection activities, dates, and logistics
2.4.3. Additional sample collects/analysis must be approved by the STR
2.4.4. Provide all necessary equipment to successfully collect the samples as described in section B-2 above, as spare parts and additional support equipment will be locally unavailable.
2.4.5. Provide or subcontract hoisting and/or wireline equipment if needed, as no rigging or hoisting equipment will be on location
2.4.6. Provide field logs to the STR within 24 hours of collection that show the samples meet the minimal requirements in 2.1.2 through 2.1.5
2.4.6.1. Provide all logs as an electronic deliverable (email) PDF format for review and approval
2.4.6.2. Logs will be deemed “Final” after review and approval of the STR
2.4.7. Complete geochemical testing as described in 2.2 and provide a report detailing the methodology, equipment, results, and uncertainty
2.4.8. Submit a sampling plan that provides site-specific scope and describes Standard Operating Procedures for the sampling and testing requirements specified in B-2 3.3, including:
2.4.8.1. Sampling tool specifications and tool diagrams
2.4.8.2. Anticipated sampling duration and number of samples
2.4.8.3. Specify the ability to mobilize with 730 days’ notice. Field operations must be completed between 30 and 45 days from notice.
2.4.8.4. Order of operations once equipment & personnel have arrived on location
2.4.8.5. Specify how hoisting/cabling will be provided
2.4.8.6. Include methodology for depth control and cable stretch correction of the hoist cable
2.4.8.7. Include anticipated uncertainty (i.e., error) in sample depth measurements
2.4.8.8. Contingency plans for tight/adverse hole conditions
2.4.8.9. Details on sample handling (i.e., maintaining sample provenance), transport, testing location, testing methodology and equipment, quality assurance, and approximate turnaround time of the results
3. Additional Information:
3.1. Lost or Damaged equipment:
3.1.1. The CONTRACTOR is not responsible for lost or damaged equipment. The CONTRATOR will not be responsible for schedule delays or increased time on site due to lost, stuck, or damaged equipment.
3.2. Anticipated Conditions: The first 2,900 ft (884 m) are anticipated to be composed of alluvium, tertiary clastic and volcanic rock. Paleozoic rock (primarily dolomite and limestone) is anticipated below that depth to TD (Table 1). The water table is expected at approximately 1,400 ft (426 m) bgs. Subsurface temperatures are anticipated to reach over 185 °F (85 °C) by TD. Pressure gradients are anticipated to be approximately 0.465 psi/ft (10.52 kPa/m), reaching approximately 2,600 psi (17,926 kPa) by TD.
3.3. The sampling equipment must meet the following technical specifications:
3.3.1. The ability to obtain unaltered and uncontaminated (representative) single-phase groundwater samples. Two-phase samples are acceptable, given justification of the use is provided.
3.3.2. The ability to collect samples in a 3.77 in (95.8 mm) diameter borehole
3.3.3. Have a maximum operational temperature rating above 185 °F (85 °C)
3.3.4. Have a maximum operational pressure rating above 2,600 psi (17,926 kPa)
3.3.5. The ability to collect the volume and number of samples required to perform geochemical tests for:
3.3.5.1. pH
3.3.5.2. Salinity
3.3.5.3. Total Dissolved Solids
3.3.5.4. Cation/Anion Analysis including
3.3.5.4.1. Sulfate (SO42-)
3.3.5.4.2. Hydrogen Sulfide (H2S)
3.3.5.5. Additional analytes if part of a standard suite of tests
B-3 Technical Specifications
| SPEC NUMBER |
| TITLE |
| REV |
| PAGES |
N/A
B-4 Drawings
| DRAWING NUMBER |
| TITLE |
| REV |
| PAGES |
| Table 1 |
| Predicted Geology |
| Figure 1 |
| Location of NNSS and Las Vegas, NV |
| Figure 2 |
| Location of RV/DC Site, NNSS Area 27, Mercury |
| Figure 3 |
| RV/DC Testbed Access Road, Drill Pads, and CH Location |
Table 1. Predicted Geology
| Depth interval, ft bgs |
| Geologic Unit |
| 0–50 |
| ALLUVIUM (QA): Poorly sorted sand and gravel, unconsolidated to loosely consolidated. |
| 50–2,000 |
| PAVITS SPRINGS FORMATION (Tpa): Interbedded sandstone, tuff, conglomerate, mudstone, and limestone. May be thin or absent. |
| 2,000–2,900* |
| ROCKS OF THE WINAPI WASH (Tgw): Formerly Horse Springs Formation (Ths). Interbedded siltstone (30%), limestone (30%), claystone (20%), sandstone (10%), tuff (5%), conglomerates (5%); fairly to moderately indurated, tuffaceous beds tend to be zeolitized; thin claystone beds may contain swelling clay. May be thin or absent. |
| 2,900–3,700 |
| GOODWIN LIMESTONE (Og): Thick-bedded limestone. May be thin or absent. |
| 3,700–4,700 |
| SMOKY MEMBER OF THE NOPAH FORMATION (Cns): Thick-bedded, blocky limestone and silty limestone. |
| 4,700–4,900 |
| HALFPINT MEMBER OF THE NOPAH FORMATION (Cnh): Thin-bedded limestone and silty limestone; irregular dark-colored chert common throughout. |
| 4,900–5,000 |
| DUNDERBERG SHALE MEMBER OF THE NOPAH FORMATION (Cnd): Thinly laminated shale and calcareous shale. May be thin or absent. |
| 5,000–7,400 |
| BONANZA KING FORMATION (Cb): Interbedded limestone and dolomite. |
| 7,400– |
| UNKNOWN: Paleozoic carbonates or quartzite. Could be a granitic intrusion present. |
*Paleozoic contact estimated between 2,700–2,940 ft. Faults in the rock are anticipated in the RV/DC area.
Figure 1. Location of NNSS (brown outline with Mercury near the SE corner) and Las Vegas, NV.
Figure 2. Location of RV/DC Site, NNSS Area 27, Mercury
Figure 3. RV/DC Testbed Access Road, Drill Pads, and CH location
B-5 Delivery & Work Location Delivery Location:
N/A Work Location:
Nevada National Security Site - Area __27___ Building __N/A__ Mercury, NV 89023 Additional Delivery/Work Locations: Work location is RV/DC testbed in Area 27.
B-6 Clearance Requirements
1. Check all that apply:
| ☒ | No security clearance; unclassified work |
| ☐ | DOE L |
| ☐ | DOE Q |
| ☐ | HSPD-12 PIV Credential |
2. If applicable, add any or all parts of the following statement security qualifications:
| ☐ | The SUBCONTRACTOR shall have the ability to obtain a U.S. Department of Energy (DOE) facility security clearance and have personnel capable of obtaining a Q-type or L-type security clearance. |
| ☐ | Q- or L-type security clearance is required for all SUBCONTRACTOR personnel having access to classified information or special nuclear material when performing such work. |
| ☐ | A corresponding level of security clearance from another federal agency may be applicable if approved by the CONTRACTOR and DOE. |
| ☒ | N/A |
3. Security Misc.:
3.1. N/A
B-7 Specialized Experience/Specific Training/Specific Certifications
1. Licenses – SUBCONTRACTOR shall have the following job-specific licenses:
1.1. N/A
2. Training – SUBCONTRACTOR shall have the following job-specific training:
2.1. N/A
3. Certifications – SUBCONTRACTOR shall have the following job-specific certifications:
3.1. N/A
B-8 Environmentally Preferable Products NOTE TO SUBCONTRACTORS: Federal Contractors such as MSTS are required by the U.S. Department of Energy to purchase Environmentally Preferable Products (EPP) (also known as green or sustainable purchasing) and are also required to flow those procurement requirements to their Subcontractors. When designing materials and/or supplying materials to be used onsite as part of a subcontract scope-of-work, those materials must meet these same requirements.
The following is a list of EPP types that must be used if they are available:
· Products with Recycled Content. U.S. Environmental Protection Agency (EPA) list
· Water Efficient Plumbing Products. EPA WaterSense® list
· Non-Toxic or Less Toxic Alternatives
· Green Certified Products. (e.g., Design for Environment, Green Seal)
· Bio-Based Products. U.S. Department of Agriculture list
· Energy Efficient Products. EPA Energy Star® or Federal Energy Management Program designated products
· Energy Efficient Electronics. EPEAT®-silver-rated or higher rated desktop computers, laptops and monitors, televisions, multifunction devices and printers
· Non-Ozone Depleting Alternative Products B-9 Attachments
| Attachment Number |
| TITLE |
| REV |
| PAGES |
N/A
B-10 Submittals (ADM = Subcontract Administrator; STR = Subcontract Technical Representative; NLT = No Later Than;
NTP = Notice to Proceed; TLO = Transmittal Letter Only)
| Description |
| Reference |
| Copies |
| Received By |
| Due Date |
| Comments |
PROCUREMENT RELATED SUBMITTALS
| Environmental, Safety, and Health Plan |
| Exhibit E |
| 1 |
| STR |
ADM (TLO)
| NLT 10 calendar days from award/Prior to start of work |
| Site-Specific Plan |
| Safety Data Sheet(s) |
| Exhibit E |
| 1 |
| STR |
ADM (TLO)
NLT 10 calendar days from award/Prior to start of work
| Safety and Personnel Report |
| Exhibit E |
| 1 |
| STR |
(TLO)
| Monthly, NLT 28th day of the new month |
| Provided using CONTRACTOR Form FRM-1253, “SUBCONTRACTOR Hours” |
| Quality Control/Assurance Program |
| Exhibit A |
Exhibit D
| 1 |
| STR |
ADM (TLO)
NLT 10 calendar days from NTP/Prior to start of work
| Insurance Certificates |
| Exhibit D |
| 1 |
| ADM |
| NLT 10 calendar days from award/Prior to start of work |
| Hazard Communication Program |
| Exhibit E |
| 1 |
| STR |
ADM
TLO
| No later than 10 calendar days from Notice to Proceed prior to start of Work |
| Prior to start of Work |
| Service Contract Reporting Requirements |
| Exhibit D |
| 1 |
| ADM |
| Annually by October 15 |
| As specified in special condition titled, “Service Contract Reporting Requirements” |
| SUBCONTRACTOR’s Authorized Representative |
| Exhibit C |
| 1 |
| ADM |
| Prior to the start of work |
| Also, when changes occur |
PROJECT SPECIFIC AND TECHNICAL SUBMITTALS/DELIVERABLES (documentation only)
| Description |
| Reference |
| Copies |
| Received By |
| Due Date |
| Comments |
| Field Logs in, PDF format |
| B-2 |
| 1, Digital |
| STR |
| Within 24 hours of sample collection. |
| To be emailed and approved the by STR |
| Laboratory Results |
| B-2 |
| 1, Digital |
| STR |
| TBD on anticipated turnaround time of results |
| To be emailed and confirmed received by STR. |
| Exhibit B (Ver May 2023) | Solicitation Number: 0000313 |
| Date: 02/25/2025 | Subcontract Number: TBD |