Text version
Exhibit I Attachment B for EP (Rev. 0.1, 2-17-15) Subcontractor Submittal Requirements Summary Dated 10/22/2018
Subcontract No. PR# RFP-0000186 Page 1 of 3
Subcontractor Submittal Requirements Summary
NOTICE
Failure to submit required submittals as delineated on this form may result in withholding of payment in accordance with subcontract terms and conditions.
Submit To: Overnight Delivery Address: Regular Mailing Address:
SUBMITTAL SCHEDULE
A Per Subcontract Schedule S Prior to Shipment Z When Required SANN Semi Annual B Prior to Balance of Payment U Prior to Use ANN Annually WKLY Weekly F Prior to Fabrication W Prior to Commencing Work DAY Daily WRR Implemented at work release level on Blanket Agreements
M Prior to Mobilization X Prior to Purchase MON Monthly BI-
WKLY
Every 2 weeks
N Prior to Notice to Proceed Y Prior to Progress Payment for Each Specific Task
QRTLY Quarterly
SUBMITTAL TYPE REQUIRED
D Drawings ED Electrical Diagrams P Prints /photocopies SD Shop Drawings
EM Electronic media II Installation Instructions PD Performance Data - Curves SP Spare Parts and Maintenance Materials
CA Calculations ML Materials/Parts List/Design Mixes
PH Photographs TR Test Reports
CD Catalog Data OM Operations & Maintenance Data
RD Project Record Documents WA Warranties
CT Certifications OT Other S Sample (2) (*) indicates quantity R Report O Original SC Samples/Colors SPEC
REVIEWER DESIGNATION (For LANS Use Only)
CA Contract Administrator IT Information Technology RM Regulatory Manager
CFO Chief Financial Office LR Labor Relations SA Safety
CON Construction LTS Long Term Stewardship SBM Small Business Office Manager
DC Derivative Classifier NFS Nuclear/Facility Safety SCM STR Manager
EC Environmental Compliance NMC Nuclear Materials & Accountability SEC Security
ES&H Environmental Safety & Health OCI Office of Counterintelligence SST Secondary SCC
ERM Emergency Management PCE Project Controls STR Subcontract Technical Representative
FM Facility Manager PHS Physical Security TA Transportation
FP Fire Protection PM Project Manager TL Technical Lead
HR Human Resources PS Personnel Security TRN Training
HRE HR Employee Concern QA Quality Assurance VC Visitor Control
HRS HR Secondary RAD RADCON WGS Waste Generator Services
IH Industrial Hygiene RM/L Risk Manager/Legal (*) Denotes Lead Reviewer
Submittal No./ Submittal Description
Reference
Submittal Schedule
Submittal Type
LANS
Response Needed?
LANS’ Reviewer (For LANS Use Only)
Commercial Document Requirements (CDR)
3.0 Exhibit D Scope of Work and Technical Requirements
3.8 Field Data
3.8.1 Summary of IH Sampling Results 1.1.1 Z RD N STR/TL(*)/PM
3.8.2 Utility Cold Air Gap Cold and Dark
Verification Documents
1.1.1 Z RD Y STR
3.8.3 NMED Notifications 2.4.24 10 working
days prior to beginning work requiring notification
RD Y STR
3.8.4 Sample Collection Logs
1.1.11 Within 24
hours of sample collection
P N STR/TL(*)/PM
Subcontract No. PR# RFP-0000186 Page 2 of 3
Submittal Type
LANS
Response Needed?
LANS’ Reviewer (For LANS Use Only)
3.8.5 Field Chain of Custody records
1.1.11 Within 24
hours of final chain of custody signature
P N STR/TL(*)/PM
3.8.6 Field log and note books (PIC logbooks, Health & Safety logbooks, field photographic logbooks, Field Data logs, Field Waste Technician logbook)
1.1.11 Z RD N STR/TL(*)/PM
3.8.7 Digital photography and associated
electronic files
1.1.11 Z R,EM N STR/TL(*)/PM
3.8.8 Field Data tables/Samples Taken Tables 1.1.11 Z RD N STR/TL(*)/PM
3.8.9 Field Container Summary and Transmittal
Forms
1.1.11 Within 5 days
of obtaining final signature from SMO.
RD N STR/TL(*)/PM
3.8.10 Analytical data summaries 1.1.11 Z RD N STR/TL(*)/PM
3.8.11 Turnover Punch List 2.6 Z R Y STR
3.9 Mapping
3.9.1 Maps 1.2.2 A OT,EM,RD Y STR/TL(*)/PM
3.14 Readiness
3.14.1 Schedules 2.4.30, 3.7, 3.9 MON,Z OT Y STR/PM(*)
3.14.2 Readiness Assessments, including
training audit verification sheets
2.4.4 A EM Y STR/PM(*)
3.14.3 Project Execution Plan 2.4.5.1 M, 15 working
days after mobilization
R Y STR/PM(*)
3.15 Reports
3.15.1 95% Draft Investigation Report 1.2.4 ZA EM,R,CT Y STR/PM(*)
3.15.2 Final Draft Investigative Report 1.2.6 ZA EM,R,CT Y STR/PM(*)
3.15.3 Approved NMED Investigation Report 1.2.6 ZA EM,R,CT Y STR/PM(*)
3.15.4 Daily Progress report 2.4.26 WKLY RD N STR
3.15.5 Weekly Progress report 2.4.26 WKLY RD N STR
3.15.6 Monthly Progress Report 2.4.32 MON RD N STR
3.15.7 Meeting Materials 1.2.6.3 Z EM Y STR/PM(*)
3.15.8 Final Project Closeout Report 3.12 B EM,R Y STR/PM(*)
3.15.9 Schedules 2.4.30 MON,Z OT Y STR/PM(*)
4.0 Exhibit F Environmental Safety & Health
4.1 ES&H Plan (Corporate) F2 N RD Y STR/ES&H(*)
4.2 SSESHP F2 N RD Y STR/ES&H(*)
4.3 Subcontractor & Lower-Tier Subs
Minimum Performance Eligibility Factors F3.1 and F3.2 Attachment F3-2
M, 15 days prior to new lower- tier start
RD Y STR/ES&H(*)
4.4 Qualifications ES&H Specialists F4.2 M RD Y STR/ES&H(*)
4.5 Qualifications Environmental Professional F4.10 M RD Y STR/ES&H(*)
4.6 Incident Reporting Written F5.2 Within 24
hours of the incident
RD Y STR/ES&H(*)
4.7 Complete Accident/Incident F5.4 Within 2
working days of the incident
RD Y STR/ES&H(*)
4.8 Weekly Productive Man-hour report F6.4 Attachment F6-
WKLY-
Mondays
RD N STR/ES&H(*)
4.9 Emergency procedures F11.3 M ES&H plan RD Y STR/ES&H(*)
4.10 Hearing Conservation Program F14.1 M ES&H plan RD Y STR/ES&H(*)
4.11 Motor Vehicle Safety Program F16.1 M ES&H plan RD Y STR/ES&H(*)
4.12 Major Equipment Declaration and
documentation of removal of uncontaminated equipment
F16.10 Attachment F16-1
Prior to placing in service
RD Y STR/ES&H(*)
4.13 Hazard Communication Plan F19.1 M ES&H plan RD Y STR/ES&H(*)
4.14 Material Safety Data Sheets (MSDS) F19.2 M, Z RD Y STR/ES&H(*)
4.15 Integrated Work Documents (IWDs) F20.3 Prior to start
of work
RD Y STR/ES&H(*)
4.16 Fire Protection and Prevention Plan F21.3 M ES&H plan RD Y STR/ES&H(*)
4.17 Spark and Flame Permit F22.4 Attachment
F22-1 2 working days prior to activity
RD Y STR/ES&H(*)
Subcontract No. PR# RFP-0000186 Page 3 of 3
Submittal Type
LANS
Response Needed?
LANS’ Reviewer (For LANS Use Only)
4.18 Excavation and Trenching F28.3 10 working
days prior to activity submit Excavation/So il Disturbance Request
RD Y STR/ES&H(*)
4.19 Gas Cylinder Use and Storage Procedure F35.5 M ES&H plan RD Y STR/ES&H(*)
4.20 Traffic Control Plan F37.1 M ES&H plan RD Y STR/ES&H(*)
4.21 Sampling and Analysis Plan F39 W Z RD Y STR
4.22 Spill Prevention Control and
Countermeasure (SPCC), including spill inspection records and waste water discharge records
F42.1 M ES&H plan RD Y STR/ES&H(*)
4.23 New Mexico Environment
Department (NMED) Air Quality notification forms/letters in accordance with New Mexico Administrative Code
20.2.78 and 40 CFR 61.145
F51.5 W, at least 15 working days prior to the start
RD Y STR
4.24 Industrial Hygiene Program F52.1 M ES&H Plan RD Y STR/ES&H(*)
5.0 Exhibit G Security
5.1 Vehicle Information G4.4 M, Z RD N STR/SEC(*)
5.2 Foreign Ownership, Control or Influence
(FOCI)
G5.4 M RD Y STR/SEC(*)
6.0 Exhibit H Quality Assurance Requirements
6.1 Project Specific Quality Assurance
Program QC-01B 30 calendar days after award
RD Y STR/QA(*)
6.2 Design/Change Control for Subcontractor
Provided Design
QC-02 Z RD Y STR/QA(*)
6.3 Design/Change Control for Contractor
Provided Design
QC-02A Z RD Y STR/QA(*)
6.4 Qualification and Certification of Personnel
and Staff
QC-03 M RD Y STR/QA(*)
6.5 Traceability - Item QC-04 Z RD Y STR/QA(*)
6.6 Manufacturing, Inspection, Maintenance, Repair, and/or Test Procedures
QC-07 Z RD Y STR/QA(*)
6.7 Inspection, Examination, and Test Reports QC-08 Z RD Y STR/QA(*)
6.8 Engineering Evaluation / Analysis Report QC-08A Z RD Y STR/QA(*)
6.9 Engineering Drawings QC-11 Z RD Y STR/QA(*)
6.10 Certification of Calibration QC-12 Z RD Y STR/QA(*)
6.11 Certified Material Test Reports QC-13 Z RD N STR/QA(*)
6.12 Shelf Life Certifications/Storage
Requirements QC-16 Prior to first shipment
RD N STR/QA(*)
6.13 Manual / Instructions QC-17 Z RD N STR/QA(*)
6.14 Catalog Data QC-17A Z RD N STR/QA(*)
6.15 Contractor’s Right of Access to
Subcontractor’s Facility
QC-22 Z RD N STR/QA(*)
6.15 Design Review Prior to Production QC-24 Z RD Y STR/QA(*)
6.16 Nonconformance Reporting QC-25 Within 3 days
of occurrence
RD Y STR/QA(*) /
TL/PM
6.17 Corrective Action Reports QC-26 Z RD Y STR/QA(*)/ TL
6.18 Suspect/Counterfeit Items QC-27 Z RD Y STR/QA /
TL(*)/PM
6.20 Serialization and Marking QC-28 Z RD N STR/QA(*)
6.21 Handling, Receiving, Storage, Shipping, and Packaging
QC-29 Z RD N STR/QA(*) /
TL/PM
6.22 Contractor Approval of IBC Field and
Laboratory Testing Agencies and Special Inspection Agencies
QC-32 Z RD Y STR/QA(*)
6.23 Documents and Records QC-34 Z RD Y STR/QA(*) / TL
6.24 Documents and Records: Environmental
Work
QC-34A Z RD Y STR/QA(*)
6.25 Certificates of Analysis QC-35A Z RD Y STR/QA(*)
6.26 Other QC-37 Z RD Y STR/QA(*)