Z2DZ--Refeed Electrical from Generator Room to ATS# 3
Closed Solicitation Posted
- Solicitation number
- 36C25925Q0638
- Agency
- Veterans Integrated Service Network 19 Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238210 Electrical Contractors and Other Wiring Installation Contractors
- Points of contact
-
- Frances Basham frances.basham@va.gov (918) 577-3923
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19 is soliciting quotes for electrical infrastructure work at the Oklahoma City VA Medical Center to remove and replace electrical feeder wire from the generator room to Automatic Transfer Switch (ATS) #3 in substation #3. This project requires a Service-Disabled Veteran-Owned Small Business (SDVOSB) contractor to perform comprehensive electrical work including demolishing existing feeder cables, installing a new 225A feeder with (4) 4/0s and (1) #4 ground in 2.5" or 3" conduit, and coordinating final connections with facility power systems. The work must comply with VA sustainable acquisition requirements, OSHA and EPA regulations, and specific limitations on subcontracting, with contractors required to be verified in the SBA certification database. Contract award will be based on the lowest reasonable proposed price methodology. Critical dates include the question submission deadline of August 4, 2025 at 10:00 AM CST, and proposal submissions due by August 18, 2025 at 10:00 AM CST, with a non-mandatory site visit having occurred on July 24, 2025.
This solicitation does not utilize any set-aside designation beyond the SDVOSB requirement, and no incumbent contractors are identified in the documentation. The project magnitude is estimated between $25,000 and $100,000, with work to be performed at the Oklahoma City VA Medical Center within a 30-day performance period following contract award. The project presents significant operational constraints, including a critical 4-hour maximum downtime limit for ATS-3 which powers the hospital's MRI machines, requiring careful coordination with emergency room operations that can only have one tile out at a time when both ER rooms are accessed simultaneously. Work must be scheduled during normal Contracting Officer Representative hours of 7:00 AM to 3:30 PM, with the new electrical feeder required to be installed before demolishing the existing system to maintain continuous power to critical hospital operations. The contractor must submit an overall work schedule as a pre-work submittal and comply with Davis-Bacon wage requirements with weekly certified payroll submissions.
Notice text
3 versions
Update #3 · Latest ·
RFQ 36C25925Q0638
Refeed Electrical from Generator Room to ATS #3
Vendor Questions and VA answers in red
CONTRACTOR Q&As #1
Question No. 1: How many days' notice do we need to provide to access the two ER rooms and pipe out of both?
Answer No. 1: Please provide an overall schedule to include the days that you will need access to the rooms as a submittal prior to start of work
Question No. 2: How long can each ER be shut down? And can both be shut down simultaneously, or will they need to be phased down?
Answer No. 2: Please provide an overall schedule to include the days that you will need access to the rooms as a submittal prior to start of work
Question No. 3: Is there a way to coordinate access to the 2 ER Rooms in the same day, shut down the ATS 3, which powers all or most of the hospitals MRI machines, and Panel EGR to tie it all in, in the same week and shut down ATS#3 and the panel feeding it, all in the same week?
Answer No. 3: Part 1: both ER rooms would be able to be closed at the same time, in doing so a barrier would have to be placed at the entrances, as only one tile can be out at a time otherwise.
Part 2: ATS-3 is critical and down time is limited to four hours in total, it can not be down for a week.
Question No. 4: What are the hours we can work, without noise affecting patients with drilling through concrete walls?
Answer No. 4: There is no best time to work. Patient occupancy fluctuates. COR work hours are 7:00am to 1530pm.
Question No. 5: What are the busiest days for MRIS?
Answer No. 5: It varies, as it supports our emergency patients as well as regularly scheduled patients, two weeks notice and coordination will ensure goal is met for outage.
Question No. 6: How long can we shut MRIS down?
Answer No. 6: No more than 4 hours. Provide schedule of work
Question No. 7: Do we need to shut down the Panel EGP, which supplies ATS #3 and features a 225 amp breaker, in order to work on it, or can we work on it while it's live?
Answer No. 7: Panel EGP is only energized when the generator is running, there will be no problem in shutting the main breaker off, located left of the panel in generator control gear, as long as electrical staff is made aware at the time, no notice would be required for this portion of the project.
Question No. 8. Please confirm award contractor will have access to the emergency room during construction.
Answer No. 8: Yes, the contractor will have access to the emergency room, however, the COR will have to badge the contractors in
Question No. 9: Since construction will be performed in an active emergency room, will an ICRA plan be provided to all bidders?
Answer No. 9: Yes an ICRA will be provided to all bidders
Question No. 10: Can the VA specify conduit and wire size/type that needs to be installed?
Answer No. 10: 4) 4/0s 1) #4 ground, in a 2 1/2' or 3 conduit, contractor s choice.
Question No 11: Can an alternate route be considered? Outside above the canopy walkway possibly? This would keep us from having to go through ER areas.
Answer No. 11: Conduit needs to be ran with existing conduits, everything currently ran on the outside is for temporary equipment only, permanent utilities need to be physically secured and away from damage.
Question No. 12: Does the new feeder need to be in place and ready to terminate before we can demo the old feeder? Or can we demo old feeder as we install new feeder?
Answer No. 12: Yes, new feeder needs to be in place prior to demo of existing feeder, providing continuity of backup generator feed serving critical loads and patients.
Question No. 13: Please confirm if we can do all of the install during normal working hours.
Answer No. 13: Normal business hours would be best as this is an emergency room, which never shuts down.
Update #2 ·
36C25925Q0638 0001
Update #1 ·
REQUEST FOR QUOTE (RFQ) 36C25925Q0638
Attachments
| File | Type | Posted |
|---|---|---|
| 36C25925Q0638 0002.docx | DOCX document | |
| VHA ICRA-1.3 Electrical.pdf | ||
| 36C25925Q0638 0001.docx | DOCX document | |
| S04 - Site Visit Meeting Doc.docx | DOCX document | |
| Pre-Bid Site Visit Sign-In.pdf | ||
| S02 Self-Performed and Subcontracted Worksheet.docx | DOCX document | |
| Project Photos.pdf | ||
| S22 - 852.219-75 LOS Certification.docx | DOCX document | |
| 36C25925Q0638.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Z2DZ--Refeed Electrical from Generator Room to ATS# 3 | Solicitation | |
| Z2DZ--Refeed Electrical from Generator Room to ATS# 3 | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity