UT NP ARCH 100(2) Bridges on Delicate Arch Road

Open Solicitation Posted

Solicitation number
6982AF27B000005
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Moab, Utah 84532, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The Federal Highway Administration Central Federal Lands Highway Division is soliciting sealed bids for the UT NP ARCH 100(2) Bridges on Delicate Arch Road project in Arches National Park, with offers due November 17, 2026 at 2:00 p.m. local time under Amendment A002, which superseded the November 26, 2026 date in Amendment A001. The Set Aside line reads "No Set-Aside Used." A Justification for Other Than Full and Open Competition, dated August 13, 2026, authorizes a sole-source award for Item 63309-0100, DELINEATOR, TYPE 1 (Shur-Flex HD Tubular Markers and Shur-Flex Driveable Delineators, 100 each), and the justification is posted with the solicitation. The Federal Highway Administration prepares the project in coordination with the National Park Service.

Place of performance is Moab, UT 84532, in Grand County, Utah. The base project spans 0.99 miles, with options for an additional 0.35 miles and one additional parking lot. Scope includes three 100-foot span concrete bridges at Salt Valley Wash, Salt Wash, and Winter Camp Wash to replace mid-1990s culverts, with a 10-year design frequency and medium-sized excavator access to each wash. Salt Valley Wash requires roadway realignment north of the existing crossing. Remaining sections, including all parking areas, receive full depth reclamation or pavement removal followed by a 4-inch overlay. The designation is 4R reconstruction with one 3R segment. Principal quantities are 10,000 cubic yards of embankment, 1,725 cubic yards of Class 3 riprap, 5,140 tons of roadway aggregate, and asphalt concrete pavement.

Steel bridge railing (pay item 55601-1100) must be fabricated at an AISC-certified plant at SBR (Certified Bridge Fabricator) level or higher, and no alternatives will be considered. Welding follows FP-14 555.17 and AASHTO/AWS D1.5 with certified welders. Steel erector certification under FP-14 555.18 is not required for railing installation limited to setting posts on anchor bolts and bolting rail tubes without field welding. Powder coating and potential hot-dip galvanizing follow Section 563. Contractors must bid work as shown, and alternate removal methods may be submitted as Requests for Information or Value Engineering Proposals during construction.

The estimated project cost ranges from $10 million to $20 million. Performance begins within 10 calendar days of notice to proceed, and completion follows Special Contract Requirements Section 108.01. Bidders submit original bid bonds with corporate seals, and performance and payment bonds are due within 10 calendar days of award. Large businesses exceeding $45 million in average annual gross receipts must submit an acceptable small business subcontracting plan within 7 days of award request if they are the apparent successful low bidder. Offerors must hold active SAM registration, complete annual representations and certifications, and submit VETS-4212 reporting if applicable. Offers must remain valid at least 60 calendar days after the due date, and offerors must acknowledge Amendment A002 or risk bid rejection. Bids are delivered to the FHWA Central Federal Lands Highway Division office at 12300 West Dakota Avenue, Lakewood, Colorado 80228. Contract Specialist Laura Slauter is the point of contact.

Notice text

PROJECT NUMBER: UT NP ARCH 100(2)

PROJECT NAME: Bridges on Delicate Arch Road

PROJECT DESCRIPTION: 

Delicate Arch Road (DAR) is within Arches National Park (Park) and provides access to Delicate Arch. DAR is a functional class 1 roadway (Principal Park Road) and is heavily traveled by visitors and often congested during periods with moderate-to-high levels of visitation.

DAR crosses three low-gradient ephemeral washes (Salt Valley Wash, Salt Wash, and Winter Camp Wash) near their confluence in the Salt Wash Basin downstream of Wolfe Ranch. Culverts installed during original road construction in the mid-1990s and during subsequent upgrades are inadequate to allow unobstructed stream flow and sediment transport downstream. This existing condition produces flooding and sediment deposition, which creates unsafe conditions for visitors, triggers road closures, potentially strands Park visitors, diminishes visitor experience of the Park, and generates high operational costs associated with traffic management, visitor safety, and cleanup operations.

SCOPE OF THE WORK: 

This project will be designated as Reconstruction (4R) with one segment of restoration (3R), and will design and construct 100’ span concrete bridges at the Salt Valley Wash, Salt Wash, and Winter Camp Wash. The DA roadway profile at each Wash will be raised to accommodate a 10-year design frequency and allow a medium-sized excavator to access each wash. The DA will be realigned at the Salt Valley wash, moving the roadway and new bridge location to the north of the existing roadway and drainage crossing. The remaining 3R sections of the roadway will receive full depth reclamation (FDR) or removal of pavement, including all parking areas, followed by a 4-inch pavement overlay. 

PRINCIPAL WORK ITEMS:

  • 20420-0000 Embankment Construction: 10,000 CUYD
  • 25101-0300 Placed Riprap, Class 3: 1,725 CUYD
  • 30202-2000 Roadway Aggregate, Method 2: 5,140 TON
  • 40101-5600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch or 3/4-Inch Nominal Maximum Size Aggregate, 0.3 To <3 Million ESAL: 8,300 TON
  • 55201-0200 Structural Concrete, Class A (AE): 752 CUYD
  • 55401-2000 Reinforcing Steel, Epoxy Coated: 138,000 LB
  • 55601-1100 Bridge Railing, Steel, Two Rail: 642 LNFT
  • 56501-0200 Drilled Shaft, 24-Inch Diameter: 750 LNFT
  • 56501-0300 Drilled Shaft, 30-Inch Diameter: 890 LNFT
  • 60901-1300 Curb, Concrete, 15-Inch Depth (Reinforced, Colored): 3,921 LNFT
  • 61701-4500 Guardrail System Mgs, Type 2, Class A Steel Posts: 1,290 LNFT
  • 63506-0500 Temporary Traffic Control, Flagger: 5,800 HOUR

ANTICIPATED SCHEDULE: 

Advertisement – September 2026

Award – November 2026

NTP – December 2026

Contract Completion – December 2028

ESTIMATED COST RANGE: 

Total estimated cost between $10,000,000 and $20,000,000

This will be solicited as a full and open competition.

Files

Show all 16

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
UT NP ARCH 100(2) Bridges on Delicate Arch Road Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Northeast Region Pavement and Bridge Preservation Construction - NP NER PMS BMS FY25(2) Pennsylvania, United States · NAICS 237310 Federal Highway Administration Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity