Sacramento River East Levee (SREL) Contract 1

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W9123820B0003
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Sacramento, California, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks construction services for improvements to segments of the Sacramento River East Levee totaling approximately three miles in length. The U.S. Army Corps of Engineers, Engineering District Sacramento is procuring these services to include degrading and reconstructing over two miles of levee, constructing cutoff walls and berms of around 180,000 cubic yards, reusing and importing soils, removing and replacing bike paths and utilities, and restoring disturbed areas. The selected contractor must complete all work within one construction season by October 31, 2020. Bids are due by January 15, 2020. Evaluation will be based on best value determinations with price and technical factors considered.

No set-aside designation was used for this procurement. The primary NAICS code is 237990 and PSC code is Z1. The work location is along the Sacramento River East Levee in the city of Sacramento, California, USA. The total value of work is estimated between $25-100 million with 150,000 cubic yards of levee material to be degraded and reconstructed. The scope requires the contractor to complete all work, including operating multiple cutoff wall crews simultaneously, within the single 2020 construction season and fully restore the flood protection line by October 31st.

Notice text

5 versions

Update #5 · Latest ·

****Bid Abstract posted****

***Amendment 0002 includes another revised pricing schedule, revised specificaiton section, and revised drawings.  Previous out dated pricing schedules will be inactivated, and a revised, conformed solicitation will be posted, as the Contract Line Items have moved to match the pricing schedule.***

***Amendment 0001 includes revised plans, specs, new Exhibit A and B, price schedule, updates response date, changes acceptance period to 45 days and provides information on ProjNet and the PSL. Note: Due to ProjNet being down until 31 December 2019, the Government will open ProjNet back up from 2 Jan - 6 Jan 2020 and will respond to all inquiries by 8 Jan 2020. In the meantime, please send inquiries to DeAnna Mannel at DeAnna.L.Mannel@usace.army.mil. All inquireis that are emailed to DeAnna will also need to be submitted through ProjNet once the site opens back up. ***

***The drawings and specificaitons are too large to post to this notice.  Please contact DeAnna Mannel @ DeAnna.L.Mannel@usace.army.mil for the files to be sent via a file transfer site.  ***

The Project is located within the City of Sacramento, California, along various segments of the Sacramento River East Levee (SREL) from just north of US 50 to just west of Freeport Blvd. The combined length of the levee segments to be remediated under this contract is approximately 3.0 miles (see attached).  The SREL lies within a heavily urbanized area with residential, recreation, and industrial use areas.  Backyards and other structures are at or near the landside levee toe along significant stretches.

During the last three decades, Sacramento Area Flood Control Agency (SAFCA) and USACE have designed and constructed improvements along several portions of the subject levee. Improvements included shallow and deep seepage cutoff walls, seepage and stability berms, and erosion protection. The levee repair design is constrained by limited levee access, residences and other structures at or near the landside toe, and limited working space along the waterside berm, if present.

The work includes, but is not limited to, providing and maintaining all temporary facilities; implementing Storm Water Pollution Prevention Plan requirements; complying with all applicable permit requirements and environmental mitigation measures for the Project; developing staging areas designated for Contractor's use to the extent needed; coordinating with Agencies and stakeholders as necessary; degrading and reconstructing 2+ miles of levee (~150,000 cubic yards) to support construction of both Deep Mix Method (DMM) and slurry trench cutoff walls; constructing drained stability berms and seepage berms (~30,000 cubic yards); reusing excavated soils that meet specification criteria for reuse as levee fill; importing soil for levee fill as necessary; managing and disposing of excess excavated soils; removing and replacing 2+ miles of paved bike paths, researching, potholing, protecting, removing, and replacing existing utilities as shown on the plans and as needed to perform the work; removing all temporary facilities; and restoring and seeding all disturbed areas.

The work required under this contract must be completed within one season, which is likely to require multiple cutoff wall headings be constructed concurrently.

The contractor must finish within one construction season with all work completed within calendar year 2020. The line of flood protection must be fully restored not later than 31 October 2020.  Work at Miller Park must be completed after Labor Day.

Update #4 ·

***Amendment 0002 includes another revised pricing schedule, revised specificaiton section, and revised drawings.  Previous out dated pricing schedules will be inactivated, and a revised, conformed solicitation will be posted, as the Contract Line Items have moved to match the pricing schedule.***

***Amendment 0001 includes revised plans, specs, new Exhibit A and B, price schedule, updates response date, changes acceptance period to 45 days and provides information on ProjNet and the PSL. Note: Due to ProjNet being down until 31 December 2019, the Government will open ProjNet back up from 2 Jan - 6 Jan 2020 and will respond to all inquiries by 8 Jan 2020. In the meantime, please send inquiries to DeAnna Mannel at DeAnna.L.Mannel@usace.army.mil. All inquireis that are emailed to DeAnna will also need to be submitted through ProjNet once the site opens back up. ***

***The drawings and specificaitons are too large to post to this notice.  Please contact DeAnna Mannel @ DeAnna.L.Mannel@usace.army.mil for the files to be sent via a file transfer site.  ***

The Project is located within the City of Sacramento, California, along various segments of the Sacramento River East Levee (SREL) from just north of US 50 to just west of Freeport Blvd. The combined length of the levee segments to be remediated under this contract is approximately 3.0 miles (see attached).  The SREL lies within a heavily urbanized area with residential, recreation, and industrial use areas.  Backyards and other structures are at or near the landside levee toe along significant stretches.

During the last three decades, Sacramento Area Flood Control Agency (SAFCA) and USACE have designed and constructed improvements along several portions of the subject levee. Improvements included shallow and deep seepage cutoff walls, seepage and stability berms, and erosion protection. The levee repair design is constrained by limited levee access, residences and other structures at or near the landside toe, and limited working space along the waterside berm, if present.

The work includes, but is not limited to, providing and maintaining all temporary facilities; implementing Storm Water Pollution Prevention Plan requirements; complying with all applicable permit requirements and environmental mitigation measures for the Project; developing staging areas designated for Contractor's use to the extent needed; coordinating with Agencies and stakeholders as necessary; degrading and reconstructing 2+ miles of levee (~150,000 cubic yards) to support construction of both Deep Mix Method (DMM) and slurry trench cutoff walls; constructing drained stability berms and seepage berms (~30,000 cubic yards); reusing excavated soils that meet specification criteria for reuse as levee fill; importing soil for levee fill as necessary; managing and disposing of excess excavated soils; removing and replacing 2+ miles of paved bike paths, researching, potholing, protecting, removing, and replacing existing utilities as shown on the plans and as needed to perform the work; removing all temporary facilities; and restoring and seeding all disturbed areas.

The work required under this contract must be completed within one season, which is likely to require multiple cutoff wall headings be constructed concurrently.

The contractor must finish within one construction season with all work completed within calendar year 2020. The line of flood protection must be fully restored not later than 31 October 2020.  Work at Miller Park must be completed after Labor Day.

Update #3 ·

***Amendment 0001 includes revised plans, specs, new Exhibit A and B, price schedule, updates response date, changes acceptance period to 45 days and provides information on ProjNet and the PSL. Note: Due to ProjNet being down until 31 December 2019, the Government will open ProjNet back up from 2 Jan - 6 Jan 2020 and will respond to all inquiries by 8 Jan 2020. In the meantime, please send inquiries to DeAnna Mannel at DeAnna.L.Mannel@usace.army.mil. All inquireis that are emailed to DeAnna will also need to be submitted through ProjNet once the site opens back up. ***

***The drawings and specificaitons are too large to post to this notice.  Please contact DeAnna Mannel @ DeAnna.L.Mannel@usace.army.mil for the files to be sent via a file transfer site.  ***

The Project is located within the City of Sacramento, California, along various segments of the Sacramento River East Levee (SREL) from just north of US 50 to just west of Freeport Blvd. The combined length of the levee segments to be remediated under this contract is approximately 3.0 miles (see attached).  The SREL lies within a heavily urbanized area with residential, recreation, and industrial use areas.  Backyards and other structures are at or near the landside levee toe along significant stretches.

During the last three decades, Sacramento Area Flood Control Agency (SAFCA) and USACE have designed and constructed improvements along several portions of the subject levee. Improvements included shallow and deep seepage cutoff walls, seepage and stability berms, and erosion protection. The levee repair design is constrained by limited levee access, residences and other structures at or near the landside toe, and limited working space along the waterside berm, if present.

The work includes, but is not limited to, providing and maintaining all temporary facilities; implementing Storm Water Pollution Prevention Plan requirements; complying with all applicable permit requirements and environmental mitigation measures for the Project; developing staging areas designated for Contractor's use to the extent needed; coordinating with Agencies and stakeholders as necessary; degrading and reconstructing 2+ miles of levee (~150,000 cubic yards) to support construction of both Deep Mix Method (DMM) and slurry trench cutoff walls; constructing drained stability berms and seepage berms (~30,000 cubic yards); reusing excavated soils that meet specification criteria for reuse as levee fill; importing soil for levee fill as necessary; managing and disposing of excess excavated soils; removing and replacing 2+ miles of paved bike paths, researching, potholing, protecting, removing, and replacing existing utilities as shown on the plans and as needed to perform the work; removing all temporary facilities; and restoring and seeding all disturbed areas.

The work required under this contract must be completed within one season, which is likely to require multiple cutoff wall headings be constructed concurrently.

The contractor must finish within one construction season with all work completed within calendar year 2020. The line of flood protection must be fully restored not later than 31 October 2020.  Work at Miller Park must be completed after Labor Day.

Update #2 ·

***The drawings and specificaitons are too large to post to this notice.  Please contact DeAnna Mannel @ DeAnna.L.Mannel@usace.army.mil for the files to be sent via a file transfer site.  ***

The Project is located within the City of Sacramento, California, along various segments of the Sacramento River East Levee (SREL) from just north of US 50 to just west of Freeport Blvd. The combined length of the levee segments to be remediated under this contract is approximately 3.0 miles (see attached).  The SREL lies within a heavily urbanized area with residential, recreation, and industrial use areas.  Backyards and other structures are at or near the landside levee toe along significant stretches.

During the last three decades, Sacramento Area Flood Control Agency (SAFCA) and USACE have designed and constructed improvements along several portions of the subject levee. Improvements included shallow and deep seepage cutoff walls, seepage and stability berms, and erosion protection. The levee repair design is constrained by limited levee access, residences and other structures at or near the landside toe, and limited working space along the waterside berm, if present.

The work includes, but is not limited to, providing and maintaining all temporary facilities; implementing Storm Water Pollution Prevention Plan requirements; complying with all applicable permit requirements and environmental mitigation measures for the Project; developing staging areas designated for Contractor's use to the extent needed; coordinating with Agencies and stakeholders as necessary; degrading and reconstructing 2+ miles of levee (~150,000 cubic yards) to support construction of both Deep Mix Method (DMM) and slurry trench cutoff walls; constructing drained stability berms and seepage berms (~30,000 cubic yards); reusing excavated soils that meet specification criteria for reuse as levee fill; importing soil for levee fill as necessary; managing and disposing of excess excavated soils; removing and replacing 2+ miles of paved bike paths, researching, potholing, protecting, removing, and replacing existing utilities as shown on the plans and as needed to perform the work; removing all temporary facilities; and restoring and seeding all disturbed areas.

The work required under this contract must be completed within one season, which is likely to require multiple cutoff wall headings be constructed concurrently.

The contractor must finish within one construction season with all work completed within calendar year 2020. The line of flood protection must be fully restored not later than 31 October 2020.  Work at Miller Park must be completed after Labor Day.

Update #1 ·

***The drawings and specificaitons are too large to post to this notice.  Please contact DeAnna Mannel @ DeAnna.L.Mannel@usace.army.mil for the files to be sent via a file transfer site.  ***

The Project is located within the City of Sacramento, California, along various segments of the Sacramento River East Levee (SREL) from just north of US 50 to just west of Freeport Blvd. The combined length of the levee segments to be remediated under this contract is approximately 3.0 miles (see attached).  The SREL lies within a heavily urbanized area with residential, recreation, and industrial use areas.  Backyards and other structures are at or near the landside levee toe along significant stretches.

During the last three decades, Sacramento Area Flood Control Agency (SAFCA) and USACE have designed and constructed improvements along several portions of the subject levee. Improvements included shallow and deep seepage cutoff walls, seepage and stability berms, and erosion protection. The levee repair design is constrained by limited levee access, residences and other structures at or near the landside toe, and limited working space along the waterside berm, if present.

The work includes, but is not limited to, providing and maintaining all temporary facilities; implementing Storm Water Pollution Prevention Plan requirements; complying with all applicable permit requirements and environmental mitigation measures for the Project; developing staging areas designated for Contractor's use to the extent needed; coordinating with Agencies and stakeholders as necessary; degrading and reconstructing 2+ miles of levee (~150,000 cubic yards) to support construction of both Deep Mix Method (DMM) and slurry trench cutoff walls; constructing drained stability berms and seepage berms (~30,000 cubic yards); reusing excavated soils that meet specification criteria for reuse as levee fill; importing soil for levee fill as necessary; managing and disposing of excess excavated soils; removing and replacing 2+ miles of paved bike paths, researching, potholing, protecting, removing, and replacing existing utilities as shown on the plans and as needed to perform the work; removing all temporary facilities; and restoring and seeding all disturbed areas.

The work required under this contract must be completed within one season, which is likely to require multiple cutoff wall headings be constructed concurrently.

The contractor must finish within one construction season with all work completed within calendar year 2020. The line of flood protection must be fully restored not later than 31 October 2020.  Work at Miller Park must be completed after Labor Day.

Files

Show all 19

Notice history

Notice Type Posted
Sacramento River East Levee (SREL) Contract 1 Award Award Notice
This notice Latest solicitation Solicitation
Sacramento River East Levee (SREL) Contract 1 Pre-Solicitation
ARCF - Sacramento River East Levee (SREL) Contract 1 Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
USACE SPK DB Construction - Natomas NPP Named Pumping Plants - Sacramento, CA Sacramento, California 95837 · NAICS 237990 ENDIST Sacramento No set-aside
$465M SPK small business MATOC for DBB/DB construction Usace Sacramento District 1325 J Street Sacramento, CA 95814 95814 · NAICS 236220 ENDIST Sacramento Total Small Business
Mississippi River, Baton Rouge to the Gulf, Saltwater Barrier Sill, Cutterhead Dredge Contract No. 1-2025. Specification No. OM25135 Louisiana, United States · NAICS 237990 ENDIST New Orleans No set-aside
East canal efficiency improvements NAICS 237110 Bureau of Reclamation Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity