Amendment 0002 - Revised Pricing Schedule.pdf
PDF 288 KB Posted
- Attached to
- Sacramento River East Levee (SREL) Contract 1
- Solicitation number
- W9123820B0003
About this file
This solicitation is for construction services along various segments of the Sacramento River East Levee totaling approximately three miles. The scope of work includes degrading and reconstructing over two miles of levee, constructing drained stability berms and seepage berms, installing both Deep Mix Method and slurry trench cutoff walls, reusing and importing soils, removing and replacing bike paths and utilities, and restoring all disturbed areas. The contractor must complete all work within one construction season by October 31, 2020, with cutoff wall construction requiring multiple headings. The Department of the Army Corps of Engineers is the contracting agency.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pricing Schedule - American River Common Features 2016 - Sacramento River East Levee, Contract 1
Page 1 of 13 AMD - 02
CLIN 0001 - CUTOFF: SB Wall to (-35' to -30') Stations: 1199+00 - 1207+75 (875')
Contract Line
Item No.
Item Description Estimated
Quantity Unit Unit Price Total Price
1.1 Mobilization and Demobilization 1 JOB $ $
1.2 Traffic Control 1 JOB $ $
1.3 Storm Water Pollution Control 1 JOB $ $
1.4 Vibration Monitoring 1 JOB $ $
1.5 Clearing and Grubbing* 1.5 AC $ $
1.6 Remove Asphalt Concrete* 990 SY $ $
1.7 Remove Stairway and Foundations, and Restore
Levee Slope 1 EA $ $
1.8 Levee Excavation (Levee Degrade and Cutoff
Trench)* 15,998 CY $ $
1.9 SB Cutoff Wall* 59,314 SF $ $
1.10 Levee Embankment Fill (Soil Type 1)* 15,299 CY $ $
1.11 Class 2 Aggregate Base* 670 TN $ $
1.12 Asphalt Concrete Paving* 190 TN $ $
1.13 Striping* 1,040 LF $ $
1.14 Erosion Control Seeding* 1.5 AC $ $
TOTAL $
NOTE: AC is acre, CY is cubic yard, TN is ton, SF is square Foot, and SY is square yard.
*Indicates quantity is estimated and subject to Federal Acquisition Regulation clause 52.211-18 Variation in Estimated Quantity.
Bold Italic font signifies revised or newly added information
Page 2 of 13 AMD - 02
CLIN 0002 3 - CUTOFF: DMM Wall to (-105') Stations: 1534+00 - 1547+50 (1,350')
Line Item
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
32.1 Mobilization and Demobilization 1 JOB $ $
32.2 Traffic Control 1 JOB $ $
32.3 Storm Water Pollution Control 1 JOB $ $
32.4 Vibration Monitoring 1 JOB $ $
32.5 Clearing and Grubbing * 2.7 AC $ $
32.6 Stripping * 1,319 CY $ $
32.7 Remove Asphalt Concrete* 740 SY $ $
32.8 Remove Aggregate Surfacing* 1,579 SY $ $
32.9 Remove and Dispose Grouted 8" Pipe (STA
1534+81) 1 JOB $ $
32.10 Remove and Dispose 6" Steel Irrigation Pipe
(STA 1540+27) 1 JOB $ $
32.11 Remove and Replace 3" Electrical Conduit
(STA 1549+54) 1 JOB $ $
32.12 Remove and Dispose 8" Steel Pipe Encased in
Concrete (STA 1547+61) 1 JOB $ $
32.13 Levee Excavation (Levee Degrade and Cutoff
Trench)* 7,040 CY $ $
32.14 DMM Cutoff Wall* 166,500 SF $ $
32.15 Levee Embankment Fill (Soil Type 1)* 7,332 CY $ $
32.16 Class 3 Aggregate Surface Course* 1,141 TN $ $
32.17 Erosion Control Seeding* 2.7 AC $ $
TOTAL $
Page 3 of 13 AMD - 02
CLIN 0003 4 - CUTOFF: SB Wall and SCCB Wall to (-55' to -30') Stations: 1547+20 - 1640+00 (9,260')
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
4 3.1 Mobilization and Demobilization 1 JOB $ $
4 3.2 Traffic Control 1 JOB $ $
4 3.3 Storm Water Pollution Control 1 JOB $ $
4 3.4 Vibration Monitoring 1 JOB $ $
4 3.5 Clearing and Grubbing* 18.5
16.1 AC $ $
4 3.6 Stripping* 9,488
8,449 CY $ $
4 3.7 Remove Asphalt Concrete* 8,637
7,637 SY $ $
4.8 Remove Concrete Retaining Wall (STA
1549+80) 1 JOB $ $
4.9 3.8 Remove Aggregate Surfacing* 1,111
889 SY $ $
4.10 Remove Curb* 78 LF $ $
4.11 Remove and Dispose - Irrigation Line
(STA 1552+10) 1 JOB $ $
4.12 3.9 Remove and Dispose Abandoned 2" Electrical Conduit (STA 1634+00) 1 JOB $ $
4.13 3.10 Remove and Dispose Abandoned 10" Steel Electrical Pipe (STA 1635+16) 1 JOB $ $
4.14 3.11 Remove and Dispose Abandoned Irr Pipe (STA
1635+16) 1 JOB $ $
4.15 Remove and Dispose of Irrigation systems (STA
1549+89 to 1557+50) 1 JOB $ $
4.16 3.12 Remove and Dispose - Abandoned 12" Steel Irrigation Line (STA 1571+84) 1 JOB $ $
4.17 3.13 Remove and Dispose Irrigation Line
(STA 1576+52) 1 JOB $ $
4.18 3.14 Remove and Dispose - 2" PVC Within Levee Crest (STA 1579+50) 1 JOB $ $
4.19 3.15 Remove and Dispose 4" Irrigation Pipe (STA
1613+07) 1 JOB $ $
4.20 Remove and Dispose Existing Pipe, Details
Unknown (STA 1554+44) 1 JOB $ $
4.21 3.16 Remove and Dispose Abandoned 4" Pipe Riser
(STA 1613+48) 1 JOB $ $
Page 4 of 13 AMD - 02
4.22 Remove and Dispose Chain Posts (STA 1550+20
- 1554+20) 87 EA $ $
4.23 Median Curb, Type 14 A* 480 LF $ $
4.24 Remove and Replace Concrete Median* 84 LF $ $
4.25 Remove Stairway and Foundations, and Restore
Levee Slope 5 EA $ $
4.26 Remove and Replace Concrete Walkway with
Handrail 1 JOB $ $
4.27 Remove and Replace 1.25" Galvanized Steel
Electrical Conduit (STA 1552+68) 1 JOB $ $
4.28 Remove and Replace Pipe Gate 3 EA $ $
4.29 Remove and Replace Sign 2 EA $ $
4.30 Remove and Dispose Abandoned Gate Posts 3 EA $ $
4.31 Remove and Dispose Monitoring Well 1 JOB $ $
4.32 3.17 Levee Excavation (Levee Degrade and Cutoff Trench)*
90,802
79,782 CY $ $
4.33 3.18 SB Cutoff Wall* 613,640
549,290 SF $ $
4.34 3.19 SCCB Cutoff Wall* 120,000 SF $ $
4.35 3.20 Levee Embankment Fill (Soil Type 1)* 92,402
81,722 CY $ $
4.36 3.21 Class 2 Aggregate Base* 7,800
7,485 TN $ $
4.37 3.22 Asphalt Concrete Paving* 2,169
2,082 TN $ $
4.38 Handicap Ramp per COS Std Drawing
T-71 1 EA $ $
4.39 Curb (Type 3)* 151 LF $ $
4.40 Traffic Rated Vault and Cover 1 EA $ $
4.41 Temporary Railing (Type K) 1 EA $ $
4.42 Traffic Sign 14 EA $ $
4.43 Striping* 2,420 LF $ $
4.44 Garcia Bend Traffic Markings 1 JOB $ $
4.45 3.23 Erosion Control Seeding 18.5
16.1 AC $ $
4.46 Temporary Delineators 17 EA $ $
Page 5 of 13 AMD - 02
CLIN 0004 - CUTOFF: Cutoff Wall to (-30') Stations: 1547+20 – 1558+20 (1,100')
Contract Line Item
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
4.1 Mobilization and Demobilization 1 JOB $ $
4.2 Traffic Control 1 JOB $ $
4.3 Storm Water Pollution Control 1 JOB $ $
4.4 Vibration Monitoring 1 JOB $ $
4.5 Clearing and Grubbing* 2.4 AC $ $
4.6 Stripping* 1,124 CY $ $
4.7 Remove Asphalt Concrete* 867 SY $ $
4.8 Remove Concrete Retaining Wall (STA
1549+80) 1 JOB $ $
4.9 Remove Aggregate Surfacing* 222 SY $ $
4.10 Remove Curb* 78 LF $ $
4.11 Remove and Dispose - Irrigation Line
(STA 1552+10) 1 JOB $ $
4.12 Remove and Dispose of Irrigation systems (STA
1549+89 to 1557+50) 1 JOB $ $
4.13 Remove and Dispose Existing Pipe, Details
Unknown (STA 1554+44) 1 JOB $ $
4.14 Remove and Dispose Chain Posts (STA
1550+20 - 1554+20) 87 EA $ $
4.15 Median Curb, Type 14 A* 480 LF $ $
4.16 Remove and Replace Concrete Median* 84 LF $ $
4.17 Remove Stairway, Foundations and Restore
Levee Slope 5 EA $ $
4.18 Remove and Replace Concrete Walkway with
Handrail 1 JOB $ $
4.19 Remove and Replace 1.25" Galvanized Steel
Electrical Conduit (STA 1552+68) 1 JOB $ $
4.20 Remove and Replace Pipe Gate 3 EA $ $
4.21 Remove and Replace Sign 2 EA $ $
4.22 Remove and Dispose Abandoned Gate Posts 3 EA $ $
Page 6 of 13 AMD - 02
4.23 Remove and Dispose Monitoring Well 1 JOB $ $
4.24 Levee Excavation (Levee Degrade and Cutoff
Trench)* 11,020 CY $ $
4.25 Cutoff Wall Station 1547+20 to 1557+20*† 64,350 SF $ $
4.26 Levee Embankment Fill (Soil Type 1)* 10,680 CY $ $
4.27 Class 2 Aggregate Base* 315 TN $ $
4.28 Asphalt Concrete Paving* 87 TN $ $
4.29 Handicap Ramp per COS Std Drawing T-71 1 EA $ $
4.30 Curb (Type 3)* 151 LF $ $
4.31 Traffic Rated Vault and Cover 1 EA $ $
4.32 Temporary Railing (Type K) 1 EA $ $
4.33 Traffic Sign 14 EA $ $
4.34 Striping* 2,420 LF $ $
4.35 Garcia Bend Traffic Markings 1 JOB $ $
4.36 Erosion Control Seeding 2.4 AC $ $
4.37 Temporary Delineators 17 EA $ $
† Indicates this pay item will be paid per the type of cutoff wall selected (SB or SCCB) by the Contractor per the contract requirements
Page 7 of 13 AMD - 02
CLIN 0005 - EROSION REPAIR: PL 84-99 SITE 0441-21
Stations: 1274+55 - 1274+85 (30')
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
5.1 Mobilization and Demobilization 1 JOB $ $
5.2 Storm Water Pollution Control 1 JOB $ $
5.3 Clearing and Grubbing* 0.1 AC $ $
5.4 Stripping* 15 CY $ $
5.5 Levee Excavation And Disposal (Offsite)* 90 CY $ $
5.6 Soil-Filled Quarry Stone* 90 CY $ $
5.7 Erosion Control Seeding* 0.1 AC $ $
Page 8 of 13 AMD - 02
CLIN 0006 - EROSION REPAIR: PL 84-99 SITE 0441-23
Stations: 1578+75 - 1579+25 (50')
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
6.1 Mobilization and Demobilization 1 JOB $ $
6.2 Storm Water Pollution Control 1 JOB $ $
6.3 Clearing and Grubbing* 0.1 AC $ $
6.4 Tree Removal 1 JOB $ $
6.5 Stripping* 40 CY $ $
6.6 Quarry Stone* 1,230 TN $ $
6.7 Soil-Filled Quarry Stone* 730 CY $ $
6.8 Coir Fabric* 190 SY $ $
6.9 Soil Fill Material* 50 CY $ $
6.10 Levee Embankment Fill (Soil Type 2)* 10 CY $ $
6.11 Class 2 Aggregate Base* 200 TN $ $
6.12 Erosion Control Seeding* 0.2 AC $ $
Page 9 of 13 AMD - 02
OPTION ITEMS
OPTION 1
OPTIONAL CLIN 1001 – BERM: Seepage Berm Stations: 1125+52 – 1130+00 (448’)
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
1001.1 Mobilization & Demobilization 1 JOB $ $
1001.2 Traffic Control 1 JOB $ $
1001.3 Storm Water Pollution Control 1 JOB $ $
1001.4 Vibration Monitoring 1 JOB $ $
1001.5 Clearing and Grubbing* 2.1 AC $ $
1001.6 Tree Stump Removal 71 EA $ $
1001.7 Stripping* 1,718 CY $ $
1001.8 Remove and Dispose – Concrete Encased Storm Drain Lines and Headwall (STA 1127+42 – 1127+61)
1 JOB
1001.9 Remove and Dispose - Abandoned Gas Main
(STA 1126+50 – 1130+20) 1 JOB $ $
1001.10 Remove and Dispose – Existing Rails, Ties and
Ballast (STA 1126+00 – 1130+50) 1 JOB $ $
1001.11 Remove and Replace Chain Link Fence* 740 LF $ $
1001.12 Levee Embankment Fill (Soil Type 2)* 12,700 CY $ $
1001.13 18” Storm Drain* 660 LF $ $
1001.14 Type G2 Drainage Inlet (STA 1128+18) 1 EA $ $
1001.15 OMPI Steel Pipe Inlet (STA 1124+96, STA
1127+09, STA 1130+20) 3 EA $ $
1001.16 Drainage Swale (STA 1126+89 – 1128+18)* 280 LF $ $
1001.17 16’ Wide Gate (Caltrans Standard Plan A85)
(STA 1128+84) 2 EA $ $
1001.18 Erosion Control Seeding* 2.1 AC $ $
Page 10 of 13 AMD - 02
OPTION 2
OPTIONAL CLIN 1002 – Tree Removal Stations: 1125+52 - 1130+00 (448')
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
1002 Tree Removal 71 EA $ $
OPTION 3
OPTIONAL CLIN 1003 - CUTOFF: SCCB Wall to -10' Stations: 1116+00 - 1125+50 (950')
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
1003.1 Mobilization and Demobilization 1 JOB $ $
1003.2 Traffic Control 1 JOB $ $
1003.3 Storm Water Pollution Control 1 JOB $ $
1003.4 Vibration Monitoring 1 JOB $ $
1003.6 Remove Asphalt Concrete* 3,378 SY $ $
1003.7 Remove and Replace Curb and Gutter* 25 LF $ $
1003.8 Remove and Replace Irrigation Utilities
(STA 1115+75) 1 JOB $ $
1003.9 Remove and Replace 8" PVC Storm Drain Pipe
(STA 1120+00) 1 JOB $ $
1003.10 Remove and Replace 8" PVC Storm Drain Pipe
(STA 1124+38) 1 JOB $ $
1003.11 Expose 8" Asbestos Water line for SAFCA Removal and abandonment
(STA 1121+47)*
44 LF
1003.12 Expose 8" Asbestos Water line for SAFCA
Removal (STA 1123+95)* 22 LF $ $
1003.13 Expose 6" Sewer Force Main for SAFCA
Removal (STA 1124+77)* 24 LF $ $
1003.14 Place 6" DR-18 C900 PVC SSFM with 2
transition couplings* 15 LF $ $
Page 11 of 13 AMD - 02
1003.15 Remove and Replace 1.25" Electrical Conduit
(STA 1125+15) 1 JOB $ $
1003.16 Remove and Replace Gutter Drain (COS STD
DWG 8-42) (STA 1124+25) 1 JOB $ $
1003.17 20 LF DR-18 C900 PVC Pipe with 10LF 16"Ø steel casing centered on pipe for protection & 2 transition couplings.
1 EA
1003.18 SCCB Cutoff Wall* 48,023 SF $ $
1003.19 Class 2 Aggregate Base* 294 TN $ $
1003.20 Asphalt Concrete Paving* 960 TN $ $
1003.21 Relocate Water Main 1 JOB $ $
1003.22 3-Foot by 4-Foot by 10-Foot Trench Box 2 EA $ $
1003.23 Striping 1 JOB $ $
OPTION 4
OPTIONAL CLIN 1004
Stations: 1610+00 – 1611+50 (150')
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
1004.1 Remove and Dispose Faucet
(STA 1611+09) 1 JOB $ $
1004.2 Clearing and Grubbing at levee toe from STA
1610+00 to 1611+50* 0.1 AC $ $
OPTION 5
OPTIONAL CLIN 1005 - BERM: Thicken Berm, Drained Berm Stations: 1096+75 - 1102+00 (525')
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
1005.1 Mobilization and Demobilization 1 JOB $ $
1005.2 Traffic Control 1 JOB $ $
Page 12 of 13 AMD - 02
1005.3 Storm Water Pollution Control 1 JOB $ $
1005.4 Vibration Monitoring 1 JOB $ $
1005.5 Clearing and Grubbing* 1.5 AC $ $
1005.6 Tree Stump Removal 1 EA $ $
1005.7 Stripping* 948 CY $ $
1005.8 Remove and Replace Chain Link Fence* 590 LF $ $
1005.9 16' CLF Gate 1 EA $ $
1005.10 Levee Excavation And Disposal (Offsite)* 3074 CY $ $
1005.11 Levee Embankment Fill (Soil Type 2)* 10,368 CY $ $
1005.12 Berm Drainage Layer - Filter Layer* 1,469 CY $ $
1005.13 6" Slotted PVC (SDR 26) Pipe* 530 LF $ $
1005.14 6" Solid PVC (SDR 26) Pipe* 50 LF $ $
1005.15 Connect 6" PVC Drain to SDMH (STA
1098+74) 1 JOB $ $
1005.16 CIPP Lining* 484 LF $ $
1005.17 Raise Storm Drain Manhole 1 EA $ $
1005.18 Raise Collector Pipe Cleanout 1 EA $ $
1005.19 Erosion Control Seeding* 2 AC $ $
1005.20 Raise Vent Stack 1 EA $ $
1005.21 Temporary Railing (Type K) 2 EA $ $
OPTION 6
OPTIONAL CLIN 1006 - CUTOFF: DMM Wall to (-95' to -15') Stations: 1282+90 - 1300+80 (1,790')
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
1006.1 Mobilization and Demobilization 1 JOB $ $
Page 13 of 13 AMD - 02
1006.2 Traffic Control 1 JOB $ $
1006.3 Storm Water Pollution Control 1 JOB $ $
1006.4 Vibration Monitoring 1 JOB $ $
1006.5 Clearing and Grubbing* 5.4 AC $ $
1006.6 Tree Stump Removal 2 EA $ $
1006.7 Stripping * 4,363 CY $ $
1006.8 Remove Stairway and Foundations, and Restore
Levee Slope 5 EA $ $
1006.9 Remove Aggregate Surfacing* 3,978 SY $ $
1006.10 Remove and Dispose Existing Standpipe (STA
1291+35) 1 JOB $ $
1006.11 Levee Excavation (Levee Degrade and Cutoff
Trench)* 13,058 CY $ $
1006.12 DMM Cutoff Wall*
204,830 SF
1006.13 Levee Embankment Fill (Soil Type 1)* 12,074 CY $ $
1006.14 Class 3 Aggregate Surface Course* 1,547 TN $ $
1006.15 Erosion Control Seeding* 5.4 AC $ $
OPTION 7
OPTIONAL CLIN 1007 – Controlled Levee Degrade Stations: 1282+00 – 1301+00 and 1600+00 – 1640+00 (1,000')
No.
Item Description Estimated
Quantity Unit Unit Price Total Price
1007.1 Controlled Levee Degrade* 1,000 LF $ $
GRAND TOTAL, including ALL OPTIONS $