Repair Electrical Distribution
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W50S6N-20-B-0003
- Agency
-
Alabama National Guard
Army National Guard, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- PSC
- Y1NZ Construction Of Other Utilities
- Place of performance
- Montgomery AL 36108 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks electrical distribution repair services for the 187th Fighter Wing in Montgomery, Alabama. The Department of the Army Alabama Army National Guard is procuring the removal of existing overhead distribution lines and structures, replacement with an underground primary system installed using directional boring, and ancillary work to provide a complete operational system. Proposals will be evaluated based on technical qualifications, past performance, and price. The deadline for responses is September 15, 2020.
The requirement has been set aside 100% for small businesses. The NAICS code is 238210 and PSC code is R499. Work includes reconnecting and replacing facility transformers over a period of 425 calendar days. The place of performance is the 187th Fighter Wing facility in Montgomery, Alabama. Eight vendors submitted bids ranging from $3.6 million to $10.7 million for base work and additive items by the September 15th deadline.
Notice text
7 versions
Update #7 · Latest ·
Pupose of this posting is to publish the corrected Abstract.
Services, non-personal, to provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary for the repair of the Electrical Distribution System at the 187 Fighter Wing, Montgomery, AL 36108
This project will remove existing overhead primary distribution lines and structures and replace the existing distribution system with a new underground primary distribution system using underground directional boring. Ancillary work required to provide a complete and operational electrical distribution system will also be required and includes, but is not limited to, reconnection of existing facility transformers, replacement of existing facility transformers, installation of new secondary service laterals to various facilities, replacement of existing service entrance panel boards at various facilities, installation of new switches, installation of new sectionalizing cabinets, installation of new hand holes/pull boxes, and documentation of new underground primary lines for future reference and service. Also included in the project scope if installation of new street lighting, parking lot lighting, flight line security lighting, and new electrical metering at various facilities.
Update #6 ·
Pupose of this posting is to publish the updated abstract, with Contracting Officer signature.
Services, non-personal, to provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary for the repair of the Electrical Distribution System at the 187 Fighter Wing, Montgomery, AL 36108
This project will remove existing overhead primary distribution lines and structures and replace the existing distribution system with a new underground primary distribution system using underground directional boring. Ancillary work required to provide a complete and operational electrical distribution system will also be required and includes, but is not limited to, reconnection of existing facility transformers, replacement of existing facility transformers, installation of new secondary service laterals to various facilities, replacement of existing service entrance panel boards at various facilities, installation of new switches, installation of new sectionalizing cabinets, installation of new hand holes/pull boxes, and documentation of new underground primary lines for future reference and service. Also included in the project scope if installation of new street lighting, parking lot lighting, flight line security lighting, and new electrical metering at various facilities.
Update #5 ·
Pupose of this posting is to publish the abstract and bid opening attendance roster.
Services, non-personal, to provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary for the repair of the Electrical Distribution System at the 187 Fighter Wing, Montgomery, AL 36108
This project will remove existing overhead primary distribution lines and structures and replace the existing distribution system with a new underground primary distribution system using underground directional boring. Ancillary work required to provide a complete and operational electrical distribution system will also be required and includes, but is not limited to, reconnection of existing facility transformers, replacement of existing facility transformers, installation of new secondary service laterals to various facilities, replacement of existing service entrance panel boards at various facilities, installation of new switches, installation of new sectionalizing cabinets, installation of new hand holes/pull boxes, and documentation of new underground primary lines for future reference and service. Also included in the project scope if installation of new street lighting, parking lot lighting, flight line security lighting, and new electrical metering at various facilities.
Update #4 ·
Pupose of this posting is to publish Amendment W50S6N-20-B-0003 0002. Amendment 0002 is to post Addendum No. 2, RFI #2 and updated "conformed" copy of solicitation for use in preparing bid.
Purpose of Addendum No. 2 is to 1) extend the period of perf romance f rom 270 calendar days after notice to proceed to 425 calendar days after notice to proceed and 2) make correction to draw ing sheet E4.1 "Electric Details".
Services, non-personal, to provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary for the repair of the Electrical Distribution System at the 187 Fighter Wing, Montgomery, AL 36108
This project will remove existing overhead primary distribution lines and structures and replace the existing distribution system with a new underground primary distribution system using underground directional boring. Ancillary work required to provide a complete and operational electrical distribution system will also be required and includes, but is not limited to, reconnection of existing facility transformers, replacement of existing facility transformers, installation of new secondary service laterals to various facilities, replacement of existing service entrance panel boards at various facilities, installation of new switches, installation of new sectionalizing cabinets, installation of new hand holes/pull boxes, and documentation of new underground primary lines for future reference and service. Also included in the project scope if installation of new street lighting, parking lot lighting, flight line security lighting, and new electrical metering at various facilities.
Update #3 ·
Pupose of this posting is to publish Amendment W50S6N-20-B-0003 0001, Addendum #1 and Responses to RFI #001. There is no extension of the bid opening date.
Services, non-personal, to provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary for the repair of the Electrical Distribution System at the 187 Fighter Wing, Montgomery, AL 36108
This project will remove existing overhead primary distribution lines and structures and replace the existing distribution system with a new underground primary distribution system using underground directional boring. Ancillary work required to provide a complete and operational electrical distribution system will also be required and includes, but is not limited to, reconnection of existing facility transformers, replacement of existing facility transformers, installation of new secondary service laterals to various facilities, replacement of existing service entrance panel boards at various facilities, installation of new switches, installation of new sectionalizing cabinets, installation of new hand holes/pull boxes, and documentation of new underground primary lines for future reference and service. Also included in the project scope if installation of new street lighting, parking lot lighting, flight line security lighting, and new electrical metering at various facilities.
Update #2 ·
Pupose of this posting is to publish the pre bid/site visit slides and sign in roster.
Services, non-personal, to provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary for the repair of the Electrical Distribution System at the 187 Fighter Wing, Montgomery, AL 36108
This project will remove existing overhead primary distribution lines and structures and replace the existing distribution system with a new underground primary distribution system using underground directional boring. Ancillary work required to provide a complete and operational electrical distribution system will also be required and includes, but is not limited to, reconnection of existing facility transformers, replacement of existing facility transformers, installation of new secondary service laterals to various facilities, replacement of existing service entrance panel boards at various facilities, installation of new switches, installation of new sectionalizing cabinets, installation of new hand holes/pull boxes, and documentation of new underground primary lines for future reference and service. Also included in the project scope if installation of new street lighting, parking lot lighting, flight line security lighting, and new electrical metering at various facilities.
Update #1 ·
Services, non-personal, to provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary for the repair of the Electrical Distribution System at the 187 Fighter Wing, Montgomery, AL 36108
This project will remove existing overhead primary distribution lines and structures and replace the existing distribution system with a new underground primary distribution system using underground directional boring. Ancillary work required to provide a complete and operational electrical distribution system will also be required and includes, but is not limited to, reconnection of existing facility transformers, replacement of existing facility transformers, installation of new secondary service laterals to various facilities, replacement of existing service entrance panel boards at various facilities, installation of new switches, installation of new sectionalizing cabinets, installation of new hand holes/pull boxes, and documentation of new underground primary lines for future reference and service. Also included in the project scope if installation of new street lighting, parking lot lighting, flight line security lighting, and new electrical metering at various facilities.
Files
| File | Type | Posted |
|---|---|---|
| Abstract v2.pdf | ||
| Abstract.pdf | ||
| BID Opening Roster.pdf | ||
| ABSTRACT ELEC DISTRO.1.xlsx | XLSX spreadsheet | |
| RFI 2.pdf | ||
| W50S6N20B0003 AMEND 2 (CONFORMED).pdf | ||
| SF 30.pdf | ||
| Addendum 2.pdf | ||
| W50S6N-20-B-0003-0001.pdf | ||
| FAKZ162003 Responses to RFI 001.pdf | ||
| FAKZ162003 Addendum 1.pdf | ||
| Pre-Bid_Site Visit Roster.pdf | ||
| Pre-Bid slides Elect Distro.ppt | PPT presentation | |
| Justification for Other Than Full Open Competition.2_Redacted.pdf | ||
| FAKZ162003 - Type B3 REVISED DRAWINGS 14 JULY 2020 (SIGNED).pdf | ||
| FAKZ162003 - Type B3 REVISED SPECIFICATIONS 14 JULY 2020 (SIGNED).pdf | ||
| W50S6N20B0003.pdf |
Show all 17
Notice history
| Notice | Type | Posted |
|---|---|---|
| Repair Electrical Distribution | Award Notice | |
| This notice | Solicitation | |
| Repair Electrical Distribution | Pre-Solicitation | |
| Repair Electrical Distribution | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Repair Electrical Systems | AFLCMC Wright Patterson AFB | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity