W50S6N-20-B-0003-0001.pdf

PDF 376 KB Posted

Attached to
Repair Electrical Distribution
Solicitation number
W50S6N-20-B-0003
Issued by

About this file

This document provides details for Amendment 0001 to solicitation number W50S6N-20-B-0003 for repair of the electrical distribution system at the 187th Fighter Wing in Montgomery, Alabama. The amendment removes the requirement for outer casings from the base bid and adds two additive bid items for steel and HDPE casings. It also adds DFARS provision 252.236-7007 for additive or deductive items. Offerors are required to acknowledge receipt of the amendment. The amendment establishes delivery dates of 270 days to the 187th Civil Engineering Squadron at the specified address and adds the applicable inspection and acceptance criteria.

View the file

Other files

File Type Posted
Abstract v2.pdf PDF
Abstract.pdf PDF
BID Opening Roster.pdf PDF
ABSTRACT ELEC DISTRO.1.xlsx XLSX spreadsheet
W50S6N20B0003 AMEND 2 (CONFORMED).pdf PDF
SF 30.pdf PDF
Addendum 2.pdf PDF
RFI 2.pdf PDF
FAKZ162003 Addendum 1.pdf PDF
FAKZ162003 Responses to RFI 001.pdf PDF
Pre-Bid slides Elect Distro.ppt PPT presentation
Pre-Bid_Site Visit Roster.pdf PDF
W50S6N20B0003.pdf PDF
Justification for Other Than Full Open Competition.2_Redacted.pdf PDF
FAKZ162003 - Type B3 REVISED SPECIFICATIONS 14 JULY 2020 (SIGNED).pdf PDF
FAKZ162003 - Type B3 REVISED DRAWINGS 14 JULY 2020 (SIGNED).pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F6L32D0070AW04

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Purpose of the Amendment is to post FAKZ162003 Addendum #1 and FAKZ162003 Responses to RFI #001. In accordance w ith Item No. 6 of Addendum #1 the Amendment w ill remove the requirement of outer casings from the base bid and add tw o Additive Bid Items (ABI). ABI 1 shall be to provide pricing for steel outer casings and ABI 2 shall be to provide pricing for HDPE outer casings. Only one ABI shall be aw arded, based on available funding. Adding DFARS Provision 252.236-7007 Additive or Deductive Items.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Sep-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W50S6N20B0003

X 9B. DATED (SEE ITEM 11)

13-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Sep-2020

CODE

USPFO AL 187 MISSION SUPPORT CONTRACTING

5187 SELMA HIGHWAY

MONTGOMERY AL 36108-4824

W50S6N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S6N20B0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

CLIN 0003 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0003 1 Each

ABI 1

FFP

Steel Casing of Directional Borings; Installation of an exterior steel casing housing all required directional borings included within the scope of work. Refer to detail “A” on drawing sheet E3.1 for requirements associated with the steel casing included in this Alternate Bid Item.

FOB: Destination MFR PART NR: Null

PSC CD: Z1NZ

NET AMT

CLIN 0004 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0004 1 Each

ABI 2

FFP

HDPE Casing of Directional Borings: Installation of an HDPE casing housing all required directional borings included in the scope of work. Refer to detail “A” on drawing sheet E3.1 for requirements associated with the HDPE casing included in this Alternate Bid Item.

FOB: Destination MFR PART NR: Null

PSC CD: Z1NZ

NET AMT

DELIVERIES AND PERFORMANCE

The following Delivery Schedule for CLIN 0003 has been added:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

270 dys. ANP 1 F6L32D--187TH CIVIL ENGINEERING /

FOMA

ADAM SANDERS

5187 SELMA HIGHWAY

BLDG 1801

MONTGOMERY AL 36108

334-394-7418 FOB: Destination

F6L32D

The following Delivery Schedule for CLIN 0004 has been added:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

270 dys. ANP 1 F6L32D--187TH CIVIL ENGINEERING /

FOMA

ADAM SANDERS

5187 SELMA HIGHWAY

BLDG 1801

MONTGOMERY AL 36108

334-394-7418 FOB: Destination

F6L32D

INSPECTION AND ACCEPTANCE

The following Acceptance/Inspection Schedule was added for CLIN 0003:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

Destination Government Destination Government

The following Technical Office was added for CLIN 0003:

F6L32D--187TH CIVIL ENGINEERING / FOMA

ADAM SANDERS

5187 SELMA HIGHWAY

BLDG 1801

MONTGOMERY AL 36108

The following Acceptance/Inspection Schedule was added for CLIN 0004:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

Destination Government Destination Government

The following Technical Office was added for CLIN 0004:

F6L32D--187TH CIVIL ENGINEERING / FOMA

ADAM SANDERS

5187 SELMA HIGHWAY

BLDG 1801

MONTGOMERY AL 36108

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been added by full text:

252.236-7007 ADDITIVE OR DEDUCTIVE ITEMS. (DEC 1991)

(a) The low offeror and the items to be awarded shall be determined as follows --

(1) Prior to the opening of bids, the Government will determine the amount of funds available for the project.

(2) The low offeror shall be the Offeror that --

(i) Is otherwise eligible for award; and

(ii) Offers the lowest aggregate amount for the first or base bid item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive items that provide the most features within the funds determined available.

(3) The Contracting Officer shall evaluate all bids on the basis of the same additive or deductive items.

(i) If adding another item from the bid schedule list of priorities would make the award exceed the available funds for all offerors, the Contracting Officer will skip that item and go to the next item from the bid schedule of priorities;

and

(ii) Add that next item if an award may be made that includes that item and is within the available funds.

(b) The Contracting Officer will use the list of priorities in the bid schedule only to determine the low offeror. After determining the low offeror, an award may be made on any combination of items if --

(1) It is in the best interest of the Government;

(2) Funds are available at the time of award; and

(3) The low offeror's price for the combination to be awarded is less than the price offered by any other responsive, responsible offeror.

(c) "Example." The amount available is $100,000. Offeror A's base bid and four additives (in the order stated in the list of priorities in the bid Schedule) are $85,000, $10,000, $8,000, $6,000, and $4,000. Offeror B's base bid and four additives are $80,000, $16,000, $9,000, $7,000, and $4,000. Offeror A is the low offeror. The aggregate amount of offeror A's bid for purposes of award would be $99,000, which includes a base bid plus the first and fourth additives. The second and third additives were skipped because each of them would cause the aggregate bid to exceed $100,000.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .