Rehabilitate Ellis Island Service Bridge and Ellis Island Paving

Award Notice Posted

Solicitation number
140P2018R0004
Agency
Awarded
to Kiewit Infrastructure CO.
Set-aside
No set-aside

Opportunity facts

Contract number
140P2018C0006 Federal contract award
PSC
Not on record
Place of performance
Statue of Liberty National Monument and Ellis Island New York, New York 10004, United States

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

The purpose of Amendment No. 005 is to:

1.  Change the Liability Insurance Clause in Section H as follows:  The United States of America shall be listed as an additional insured on Contractors insurance policies. The requirement for listing the United States of America as a named insured is deleted.

2.  Provide the missing SF30 for Amendment No. 004.

The proposal submission deadline date/time remains 17:00 ET, Thursday, January 04, 2018.

Update #5 ·

AMENDMENT 0004

STLI - 213901, 224214 - Rehabilitation and Repair of Structural Components Mission Critical Ellis Island Bridge and Paved Areas at the North End of Ellis Island Bridge in support of Statue of Liberty National Monument and Ellis Island, New York and New Jersey.


The purpose of this amendment is to:

1.  Incorporate additional Questions and Answers contained in the attachment for this amendment.

2.  Incorporate Sheet C3 - Spot Elevation, as attached

All other terms and conditions remain unchanged.

The proposal submission date/time remains unchanged at 17:00, ET, 4 January 2018

Update #4 ·

AMENDMENT 0003

STLI - 213901, 224214 - Rehabilitation and Repair of Structural Components Mission Critical Ellis Island Bridge and Paved Areas at the North End of Ellis Island Bridge in support of Statue of Liberty National Monument and Ellis Island, New York and New Jersey

The purpose of this amendment is to:


1. Incorporate Amendment 0002, Standard Form 30 as attached.

2.  Incorporate Amendment 0003, Standard Form 30 as attached.


3. Incorporate pre-proposal Questions and Answers


4. Incorporate the Cathodic Protection Drawings as attached


5. Extend the proposal submission deadline date/time to 17:00, ET, Thursday 4 January 2018


All other terms and conditions remain unchanged.

Update #3 ·

Amendment 0002

The purpose of this amendment is to:

1.  Incorporate revised specifications dated 7 December 2017 as attached.

     All previous versions of the specifications package are hereby removed from the solicitation and are replaced with the above specified version.

2.  Extend the Question submission deadline date/time to 1700 ET, Friday, 8 December 2017.

     Questions shall be submitted not later than the date/time specified in this amendment to:

Monica_divelbess@nps.gov

with a courtesy copy to:

Victoria_nosal@nps.gov


This amendment DOES NOT change the proposal submission deadline which remains unchanged.

All other terms and conditions remain unchanged.


Update #2 ·

STLI - 213901, 224214 - REHABILITATION AND REPAIR OF STRUCTURAL COMPONENTS MISSION CRITICAL ELLIS ISLAND BRIDGE AND PAVED AREAS AT THE NORTH END OF ELLIS ISLAND BRIDGE IN SUPPORT OF STATUE OF LIBERTY NATIONAL MONUMENT AND ELLIS ISLAND, NEW YORK AND NEW JERSEY

Amendment NO. 0001 (A1)

The purpose of this amendment is to:

1.  Extend the proposal submission deadline to 1500, MT, Thursday, 21 December 2017

2.  Incorporate the Pre-Proposal Meeting Slideshow, Attendance Roster, and Pre-Proposal Questions and Answers

3.  Correct the Estimated Period of Performance

4.  Incorporate updated DOL Wage Determination Rates for New Jersey

5.  Incorporate Specification Addendum 001

See Solicitation Amendment 0001 attachments for further detailed information.

Update #1 ·

The National Park Service (NPS), Department of Interior (DOI), Denver Service Center (DSC), is soliciting proposals on a full and open basis from all interested businesses having the capability to perform the work described below.  


Title of Project:  Rehabilitation and Repair of Structural Components Mission Critical Ellis Island Bridge and Rehab Current Paved Areas at the North End of the Ellis Island Bridge.


Description:  The Work consists of repairing, strengthening or replacing deteriorated portions of the existing bridge.  The work includes:  replace the entire decking systems; install a crutch bent; clean and paint all exposed portions of piles, bent caps, floor beams, and trusses; and install a concrete jacket on one sister pile; repairing existing lighting and electrical service; repairing existing guardrail system; and concrete repair and repointing at abutments on the service bridge.  Work also includes rehabilitation of the pave areas and site around the Power House with options to regrade, treat and stripe the gravel parking area and repave the approach drive to the bridge on the Ellis Island side. 


 Estimated Price Range:  $5 million - $10 million


 Estimated Period of Performance:  March 2018 through December 2019


A pre-proposal meeting has been scheduled for 10:00 a.m. ET, Thursday, November 30, 2017.  


1. The pre-proposal meeting will be held at 10:00 am ET, on November 30, 2017, in the New Immigration Building (NIB) Large Conference Room, Ellis Island, New York.


2. Potential Offerors will need to send their names and vehicle information (plate number) at least 72 hours in advance of the meeting to both monica_divelbess@nps.gov and victoria_nosal@nps.gov.


3. All attendees must have a photo ID and allow sufficient time for security screening.


4. At this time, attendees will be allowed to park on-island that morning. There are limited spaces so potential offerors are encouraged to carpool as much as possible.

Files

Show all 24

Notice history

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors