RECOVERY--Y--PROJECT NUMBER KRSM083003, Child Development Center, Hill Air Force Base, UT

Award Notice Posted

Solicitation number
W91238-09-R-0044
Agency
Awarded
to HHI Corporation
Set-aside
No set-aside

Opportunity facts

Contract number
W91238-09-C-0022 Federal contract award
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

Design-Build (D-B) Child Development Center, Hill AFB, Utah.

Single story building to include multi-purpose, isolation and storage rooms, kitchen area and equipment, administrative space, playground area and equipment, fire protection, utilites, emergency detection/annunciation system and CCTV system. Project also includes demolition of several buildings.

Update #5 ·

2nd SITE VISIT for the Child Development Center, Hill AFB, UT

DATE & TIME:

Tuesday, 7 July 2009 @ 9:00 AM (Local Time Hill AFB, Utah)


Participants will meet at

Utah Resident Office
7227 6th Street
Building 366
Hill AFB, UT 84056

(Please Meet In Front of Bldg 366 No Later Than 8:45 am)

Second (2nd) Site Visit for the RECOVERY - Child Development Center is scheduled as attendees at the first Pre-Construction Site Visit were unable to fully inspect all the buildings to be demolished under this solicitation. This second site visit is to allow contractors the opportunity to inspect buildings that were not visited fully the first time and to gather additional pertinent information for development of their cost proposals.


For all attendees needing Security Access/Temporary Pass onto Hill Air Force Base:
Please contact Linda Lebo (for SECURITY ACCESS ONLY), no later than, close of business, four (4) working days before the planned Visit/Site Walk, via EMAIL at: Linda.G.Lebo@usace.army.mil or Linda.Lebo@us.army.mil
Please provide the following required information in your E-MAIL request: Name, Driver's License Number (with State of Issuance), Company, Phone Number and E-MAIL address. A confirmation will be sent to your E-MAIL address. For further information, phone: Linda Lebo @ 801-586-3067.

Alternate Contacts:
Vivienne Hammer @ 801-586-3070 - Vivienne.Hammer@usace.army.mil
or
Regina Gray @ 801-586-3039 - Regina.L.T.Gray@usace.army.mil

On day of the Site Walk: Participants should enter through the Bases Main South Gate Visitor Center to obtain a temporary visitor pass, well before the intended meeting/site walk. Attendees should expect to travel directly to Building 366s Conference Room for a Pre-Brief , prior to the actual site walk. Travel through the Gate, turn left at the first Stop Light, take the first right turn. Bldg 366 is on right side of road.

Participants will be notified of any changes no later than a day prior to the site walk.

Update #4 ·

This acquisition is proceeding as a 100% Small Business Set-Aside Request for Proposal (RFP).

Estimated Cost Range is between $ 10,000,000 and $ 25,000,000

Period of Performance for Design and Construction: Not to Exceed 730 Days

This Procurement will be conducted under FSC CODE: Y139, SIC CODE: 1542, NAICS Code: 236220. The size standard for this code is $33,500,000. All questions should be directed to the Contract Specialist, Connie Newell, at (916) 557-5229, FAX: No.: (916) 557-5278, EMAIL: Connie.L.Newell@usace.army.mil.
U.S. Army Corps of Engineers, Military Construction CECT-SPK, 1325 J Street, Sacramento, CA 95814-2922

This RECOVERY Design-Build Child Development Center project provides for a single story (35,697 SF), concrete slab, steel frame, masonry exterior walls, and standing seam metal roof. Project includes multi-purpose rooms, isolation rooms, storage rooms, kitchen area and equipment, administrative space, playground area and equipment, fire protection, and utilities. Also includes emergency detection/ annunciation system and CCTV system. Comply with DoD force protection requirements per Unified Facilities Criteria. This project also includes demolition of 6 buildings (total 35,731 SF).

The Contractor shall develop and complete the design and construct the facility. Sustainable design (LEEDS) is required for this project.

The Design-Build (D-B) Contractor will be required to perform a geotechnical investigation yielding a geotechnical report that shall be used as a basis for design. Likewise, the D-B Contractor will be required to perform a topographical survey; also a basis for design. Following award, the contract will proceed as follows:

This project will follow a Fast Track process. The D-B Contractor will have discretion as to when submittals will be made and the content of the submittals --- within the guidelines of the RFP. All design review comments for the work and applicable construction techniques for unusual construction conditions must be appropriately addressed and direction received from Contracting Officer prior to the start of construction activities.

This project will follow completing design before construction begins process. All review comments for the work must be appropriately addressed and applicable construction techniques for unusual construction conditions must be properly defined and accepted and direction received from Contracting Officer prior to the start of construction.

The RFP is anticipated to be posted on or about 10 June, 2009. Proposals are due on or about 16 July 2009, 3:00 pm (PDT).

A SITE VISIT/PRE-PROPOSAL CONFERENCE IS On/Or About 18 June 2009 @ 0900 Hours (PDT), Bldg 366, Hill AFB, Utah.
All PROPOSALS will be due on/about 16 July 2009/3:00 pm PST. The specific date and time will be identified in the solicitation. OFFERORS ARE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELED OR REVISED AT ANY TIME DURING THE SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.

ORDERING SOLICITATION: Plans and specifications will NOT be provided in hard paper copy or CD-ROM format. The solicitation and all amendments for this acquisition will be posted on a secure Government website known as FedBizOpps (www.fbo.gov) once the RFP is issued. Viewing/downloading documents from FedBizOpps will require prior registration in Central Contractor Registration (www.ccr.gov). If you are a first-time FedBizOpps user, you will also be required to register in FedBizOpps (www.fbo.gov) before accessing the RFP documents. To register, click on the Register Now button in the Vendors Block and follow the instructions. The following information will be required:

Update #3 ·


IMPORTANT REMINDER!!!!  Please also note change in document requirements for security access!!!        

 





 



A Site Visit for the RECOVERY - Child Development CENTER has been scheduled for:

Friday,  19 June 2009  @  9:00 AM  (Local Time Hill AFB, Utah)


Participants will meet at the: 


 Utah Resident Office


7227 - 6th Street


Building 366


Hill AFB, UT 84056


  


For all attendees needing Security Access/Temporary Pass onto Hill Air Force Base: 


Please contact Linda Lebo (for SECURITY ACCESS ONLY), no later than, close of business, four (4) working days before the planned Visit/Site Walk, via EMAIL at:  Linda.G.Lebo@usace.army.mil or Linda.Lebo@us.army.mil


Please provide the following required information in your E-MAIL request:  Name, Driver's License Number (with State of Issuance), Company, Phone Number and E-MAIL address.  A confirmation will be sent to your E-MAIL address.   For further information, phone:  Linda Lebo @ 801-586-3067.


 Alternate Contacts: 


Vivienne Hammer @  801-586-3070  -  Vivienne.Hammer@usace.army.mil  


or 


Regina Gray @  801-586-3039  -  Regina.L.T.Gray@usace.army.mil


 


On day of the Site Walk:   Participants should enter through the Base's Main South Gate Visitor Center to obtain a temporary visitor pass, well before the intended meeting/site walk.  Attendees should expect to travel directly to Building 366's Conference Room for a Pre-Brief , prior to the actual site walk.  Travel through the Gate, turn left at the first Stop Light, take the first right turn.  Bldg  366 is on right side of road. 


Participants will be notified of any changes no later than a day prior to the site walk. 


 


 

Update #2 ·

IMPORTANT NOTICE!!!!


Site Visit for the RECOVERY Design-Building Child Development Center has been scheduled as follows:


FRIDAY, 19 JUNE 2009  @  0900 Hours (Local Hill AFB Time)


Please follow the below instructions for access:



- A site walk/Pre-Proposal conference will be conducted at 9:00 AM (local time Hill AFB) on Friday, June 19, 2009. For all attendees needing security access/temporary pass onto Hill Air Force Base, please contact Resident Office representative; Linda Lebo, no later than close of business, four (4) working days before the Site Walk, via e-mail at:


Linda.G.Lebo@usace.army.mil or linda.lebo@us.army.mil


Please provide the following required Information:


Name, Social Security Number, Company, Phone Number and e-mail address.


(A confirmation will be sent to your e-mail address)


For further information, phone: Linda Lebo at (801) 586-3067.


Alternate Contacts: Vivienne.Hammer@usace.army.mil or Regina.L.T.Gray@usace.army.mil



Update #1 ·

This acquisition is proceeding as a 100% Small Business Set-Aside Request for Proposal (RFP).

Estimated Cost Range is between $ 10,000,000 and $ 25,000,000

Period of Performance for Design and Construction: Not to Exceed 730 Days

This Procurement will be conducted under FSC CODE: Y139, SIC CODE: 1542, NAICS Code: 236220. The size standard for this code is $33,500,000. All questions should be directed to the Contract Specialist, Connie Newell, at (916) 557-5229, FAX: No.: (916) 557-5278, EMAIL: Connie.L.Newell@usace.army.mil.
U.S. Army Corps of Engineers, Military Construction CECT-SPK, 1325 J Street, Sacramento, CA 95814-2922

This RECOVERY Design-Build Child Development Center project provides for a single story (35,697 SF), concrete slab, steel frame, masonry exterior walls, and standing seam metal roof. Project includes multi-purpose rooms, isolation rooms, storage rooms, kitchen area and equipment, administrative space, playground area and equipment, fire protection, and utilities. Also includes emergency detection/ annunciation system and CCTV system. Comply with DoD force protection requirements per Unified Facilities Criteria. This project also includes demolition of 6 buildings (total 35,731 SF).

The Contractor shall develop and complete the design and construct the facility. Sustainable design (LEEDS) is required for this project.

The Design-Build (D-B) Contractor will be required to perform a geotechnical investigation yielding a geotechnical report that shall be used as a basis for design. Likewise, the D-B Contractor will be required to perform a topographical survey; also a basis for design. Following award, the contract will proceed as follows:

This project will follow a Fast Track process. The D-B Contractor will have discretion as to when submittals will be made and the content of the submittals --- within the guidelines of the RFP. All design review comments for the work and applicable construction techniques for unusual construction conditions must be appropriately addressed and direction received from Contracting Officer prior to the start of construction activities.

This project will follow completing design before construction begins process. All review comments for the work must be appropriately addressed and applicable construction techniques for unusual construction conditions must be properly defined and accepted and direction received from Contracting Officer prior to the start of construction.

The RFP is anticipated to be posted on or about 10 June, 2009. Proposals are due on or about 16 July 2009, 3:00 pm (PDT).

A SITE VISIT/PRE-PROPOSAL CONFERENCE IS On/Or About 18 June 2009 @ 0900 Hours (PDT), Bldg 366, Hill AFB, Utah.
All PROPOSALS will be due on/about 16 July 2009/3:00 pm PST. The specific date and time will be identified in the solicitation. OFFERORS ARE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELED OR REVISED AT ANY TIME DURING THE SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.

ORDERING SOLICITATION: Plans and specifications will NOT be provided in hard paper copy or CD-ROM format. The solicitation and all amendments for this acquisition will be posted on a secure Government website known as FedBizOpps (www.fbo.gov) once the RFP is issued. Viewing/downloading documents from FedBizOpps will require prior registration in Central Contractor Registration (www.ccr.gov). If you are a first-time FedBizOpps user, you will also be required to register in FedBizOpps (www.fbo.gov) before accessing the RFP documents. To register, click on the Register Now button in the Vendors Block and follow the instructions. The following information will be required:

Files

File Type Posted
J A SPK09-17 ASSA.pdf PDF
J A SPK09-18 Monaco.pdf PDF
J A SPK09-19 Vindicator.pdf PDF
RPF_09-R-0044_Am0006.pdf PDF
CDC Second Site Visit 7Jul09 Sign-In Sheet.pdf PDF
RFP_09-R-0044_CDC_Am0005.pdf PDF
RFP_09-R-0044_CDC_Am0004.pdf PDF
Amendment 0003 6Jul09.pdf PDF
RFP_09-R-0044_CDC_Am0002.pdf PDF
RFP 09-R-0044 CDC Am0001.pdf PDF
PreProposal Conference 19Jun09 R1.pdf PDF
CDC Sign In Sheet 19Jun09.pdf PDF
1623_dwgs.pdf PDF
1623_Specs.pdf PDF
Show all 14

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors