Pre-Proposal Conference Meeting Minutes 19 June 2009
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Conference Meeting Minutes for the Contractual Segment
Presentation by Gregory Tom on June 19, 2009 at 9:00 AM at Hill AFB, Utah
On behalf of the Corps of Engineers, I’d like to welcome you to today’s Pre-proposal
Conference for Solicitation W91238-09-R-0044, titled “RECOVERY – Child
Development Center”. My name is Gregory Tom. I am a Contract Specialist helping
Connie Newell who is the primary point of contact throughout the solicitation process and contract award. Ms Newell’s telephone number and email address are found in the synopsis that is posted on FedBizOpps and also in Section 00100-2 of the Request for
Proposal (RFP).
If you have any questions, whether contractual, technical, or otherwise, you must submit them via the Bidder Inquiry System. This database is being required to be utilized in an effort to ensure that unfair advantages are not given to anyone, even a perceived advantage. In order to submit a question, you will need to use the “Bidder’s Inquiry
Key”, which is a 12-digit pass-code found on the first page of Section 00100 of the RFP.
When a question is submitted, it is assigned to the appropriate individual for evaluation;
once the evaluation is provided, the question/comment is then replied to and then becomes viewable by anyone, as long as they use the Bidder’s Inquiry Key to log in. As
I stated earlier, by using this system a more appreciable level playing field is fostered. It may seem a bit cumbersome to some, but this is done so that everyone is able to see the questions and answers exactly the same. One note of caution: Questions will not be accepted in the Bidder’s Inquiry System as of Close of Business: July 6, 2009.
Please continue to monitor the FEDBIZOpps for amendments to this solicitation. These
Pre-proposal Conference Meeting minutes that I’m reading from right now and the sign-in sheet will be posted to the FedBizOpps website. When anything new is posted on
FedBizOpps, our office will try to post a notice on FedBizOpps indicating such.
Therefore, I strongly encourage each of you to register to receive notification of changes to the solicitation on FedBizOpps.
I need to emphasize at this point that nothing said here today qualifies or changes the terms and conditions of the solicitation. The solicitation can only be changed by formal amendment (Standard Form 30) to the RFP.
There are no amendments as of this date. Again, notices and amendments will be posted on FedBizOpps, it is the contractor’s ultimate responsibility to check FedBizOpps regularly for any updates.
The purpose of my briefing today is to briefly discuss the contractual aspects of the solicitation, with emphasis on the submission of your proposal and the evaluation process. We take the time to do this because many firms may not be familiar with the process we will be using, which is usually called either “competitive negotiation” or “best value trade-off source selection”. We have found from past experience that a small investment of our time, up front, greatly improves the quality and accuracy of proposals and reduces the likelihood that we will have to reject a proposal due to non-conformance with the solicitation’s submission requirements.
The information I’m going to review, and all information in the RFP, is very important.
The RFP procedures vary substantially from the sealed bidding/IFB process.
There will not be a public bid opening as occurs with Invitation For Bids, or IFBs.
Nonetheless, offers must be received by the specified time at the specified place.
Presently, offers are due by July 16, 2009 at 3:00 PM Local Time in our Sacramento
District office. There is no public parking in our building, so if you plan to hand-carry your proposal on the due date, be sure to allow sufficient time to find parking and submit your proposal package to the individual in our building’s lobby at 1325 J Street. We utilize a satellite clock for time accuracy and once the clock reaches 3:00 pm, any additional offers will be rejected in accordance with FAR 52.215-1. You are urged to pay attention to the Directions for Submitting Offers, which are spelled out on the 2nd and third pages of Section 00100 of the RFP.
Under a competitive IFB situation, after a bid opening the bids become public information. That is not the case in the RFP process. The only information you will receive during the evaluation process will pertain to your own proposal. We will not release the names of the firms that submitted offers. Even under the Freedom of
Information Act (FOIA), if RFP procedures are used, U.S. Code limits releasable information after contract award. Specifically, only the contract number, contract awardee and address, and contract amount is releasable; this is the same information that will be posted as an Award Announcement in FedBizOpps.
The RFP process takes much longer to get to an award than sealed bidding, since both price and technical evaluations are required.
The solicitation for this project is proceeding as a 100 % Small Business Set-Aside. This solicitation requires a 110-day government acceptance period.
At this point, I’d like to go through the solicitation and point out areas of special concern based on commonly made mistakes, and the general organizational structure of the RFP.
TABLE OF CONTENTS
At the front of the RFP on the third page is the Table of Contents, which lists the main sections of the Front End of the RFP, along with the Attachments and Notes. Below these Notes is a separate Table of Contents for the Technical Specifications.
STANDARD FORM 1442
Beginning on the 4th page of the RFP is the Standard Form 1442. This form is used for soliciting offers, submitting offers, and making the award. The bottom of the form provides the time and date set for receipt of proposals as previously discussed. It also indicates that an offer guarantee is required. The required amount is 20% of the total price, but Not To Exceed (NTE) $3 million. It also informs you the number of days the performance and payment bonds must be furnished after contract award equal to 100% of the contract price. The second page of the SF1442 (technically the reverse side of page
1) is critical. In Block 14, you must enter your company’s name and address exactly as it appears in Central Contractor Registration (CCR) and provide your CAGE code in the
‘Code’ block. Your telephone number is entered in Block 15. You must acknowledge all amendments (both Amendment number and date) in Block 19. Lastly, Block 20A is the typed or printed name of the individual authorized to sign the offer with their signature in
Block 20B, and the signature date is entered in Block 20C. If you are a joint venture, partnership, or corporation, you must also complete the continuation pages, three and four.
PRICING SCHEDULE
Behind the SF1442 continuation sheets is the pricing schedule. Prices must be submitted for all items as indicated. Please verify your calculations…errors are too common. Excel is a wonderful program; however do not “round off” extended totals and use only two decimal places. Using more than two decimal places creates mathematical issues. As you look through the Pricing Schedule, please note that the project is structured as required pricing for two (2) Base Line Items and nineteen(19) Option Line Items. Please note the last page of the Pricing Schedule, as it contains notes that should be read and understood.
SECTION 00100
Section 00100 is next. The RFP includes the full text of the FAR and DFARS provisions pertaining to this solicitation as well as any local supplements. Please note that this section specifies that FAX and telegraphic offers will not be accepted (Page 00100-14).
The provision at FAR 52.215-1, ‘Instructions to Offerors – Competitive Acquisition”, which begins on page 00100-17, summarizes the rules of the source selection process that we will use. It should be read very carefully. Note that it says that you need to submit your best offer up front, as you may not get another chance. Also note that a proposal can be rejected by the Government if the pricing is materially unbalanced.
The provision 52.216-1, Type of Contract, (Page 00100-20) says the Government contemplates award of a “firm, fixed-price construction contract”.
If an offeror is considering use of a foreign construction material, pay close attention to
FAR 52.225-24, Notice of Buy American Act Requirement – Construction Materials on page 00100-20. This provision cross-references Contract Clause 52.225-23, Buy
American Act – Construction Materials Under Trade Agreements of Section 00700.
SECTION 00111
PROPOSAL SUBMITTAL REQUIREMENTS, INSTRUCTIONS, BASIS OF AWARD,
AND EVALUATION CRITERIA
Section 00111 provides detailed instructions how to prepare and format your proposal for submission. In addition, it separates the Price Proposal Volume from the Technical
Proposal Volume and lists the respective submittals for each as Tabs 1 through 7 and
Tabs 1 through 3 respectively.
To reiterate, Section 00111 provides detailed instructions for preparing and submitting your proposal, which will consist of both a price proposal and a technical proposal. The technical and pricing proposals are to be submitted separately. You are required to submit one (1) original price proposal and no copies (Page 00111-32). For the Technical
Proposal, submit one (1) original plus seven (7) copies (Page 00111-44). In addition, we need one complete copy of the technical proposal on Compact Disk (CD) in PDF format.
In preparing your offer, do not presume that the Government has any prior knowledge of your firm. Be sure to structure your proposal in strict compliance with the instructions in the solicitation. Use the specified formats exactly; doing so is to your benefit and will aid the Source Selection Board evaluators in reviewing your proposal. In some areas, we may be requiring very specific information in specified formats and with page limits in order to streamline the evaluation.
The following suggestions are provided to help you avoid making mistakes that could negatively impact your competitive standing:
- When submitting information using a specified format, you do not have to include the instructions we give you for completing each block in your submission. Just identify the block with the number and heading and provide the required information.
If you have any questions as to our intent, please enter your question in the Bidder’s
Inquiry System. Remember, Bidder’s Inquiry System will become inoperable close of business 6 July 2009, so please don’t delay entering your questions.
--If a Key Subcontractor provides information to you about their experience in a different format than what the solicitation requires, you are responsible to modify that information into the required format. If you just submit the information “as is”, more than likely critical information will be missing that could impact your evaluation results.
Beginning on Page 32 in Section 00111, the Price Proposal Volume is discussed. The format for the price proposal is shown as Tabs 1 through 7. Please ensure that the specified requirements are complied with. Tab 4 is asking for a price breakout for 20 work breakout structures. Submit fully burden amounts for each of these elements.
At this time, I’d like to briefly review the Technical Proposal Volume, which begins in
Page 00111-44. This is a critical page to understand because it identifies the format, contents and list of Tabs for the Technical Proposal Volume. Each Tab and its required content are identified on the subsequent pages. The Evaluation Factors are:
1) Experience and Capability; 2) Past Performance; and 3); Management Approach.
There are sample submission documents within Section 00111 that you can refer to when preparing your proposal.
Preface
Discussion of this submission begins on Page 00111-45. The preface introduces the team proposed to perform on this project with an introduction narrative and a summary list.
The narrative provides information about the Prime and Key Subcontractor(s) to include their role, authority, and major work elements they will perform.
Factor 1: Experience and Capability
Factor 1 requires the offeror to provide specific information regarding both their own experience as well as any proposed Key Subcontractors and corporate resumes for prime and key subcontractor. The offeror is required to submit at least one example project and no more than three for themselves and each Key Subcontractors proposed for performance of the three (3) capability areas. The “example projects” must demonstrate capabilities in the following areas: 1) Construction; 2) Design; and 3) Design-Build
Project Management (Prime Contractor Only). Example projects completed after 2005 are considered recent. For each example project use the Project Information Form format to provide the requested information.
Factor 2: Past Performance
This factor concentrates on information that will be used to evaluate the past performance record of the offeror and proposed Key Subcontractors. Past performance evaluation information should be provided on the example projects submitted under the Experience and Capability factor. If an official written performance rating or evaluation is not available (e.g., Construction Contractor Appraisal Support System (CCASS)), have a reference submit a completed Past Performance Questionnaire. The Government may utilize information other than that supplied by the offeror in its evaluation of past performance.
For each example projects provide under Factor 1, six (6) additional items of information are used in the evaluation of past performance: (1) socio-economic consideration, 2) safety record, 3) performance problems, 4) quality award, 5) contract price, and 6) completion date.
Letters of Commitment and Authorization must be submitted from each proposed Key
Subcontractor.
Factor 3: Management Approach
Factor 3 has two (2) parts: a management narrative and an organizational chart.
The management narrative describes the offeror’s approach to effectively manage the designers, consultants and subcontractors and coordinate all work throughout design and construction phases. The organizational chart graphically depicts the proposed project team.
EVALUATION
Section 00111 includes information on how the price and technical proposals will be evaluated. Page 00111-25 through 31 states how the price proposal and technical proposal submissions will be evaluated.
Paragraph 2.3 on page 00111-25 is very important, as it gives the relative importance of technical and price considerations. In this solicitation, technical (non-price) factors, when combined, are approximately equal to price. The Relative Weighting of the
Technical Evaluation Factors and their relative weights are identified in paragraph 2.6 on
Page 00111-26. For this project, Factor 1 (Experience and Capability) is the most heavily weighted factor, while Factor 2 (Past Performance) is weighted less than Factor 1, and
Factor 3 (Management Approach) is weighted less than Factor 2 and Factor 4 (Technical
Approach) is the least heavily weighted factor.
How each Factor will be evaluated is described in more detail within each Factor’s requested information under the subparagraph entitled “Evaluation Criteria”. These subparagraphs explain how the Government intends to evaluate the proposals that are received.
In summary, we strongly recommend that you read and become familiar with this
Section. Refer to it often while preparing your technical proposal and then review it again before you finalize your technical proposal. Ensure that your technical proposal has accurately presented your company’s and your key subcontractors’ ability to successfully complete this project. Be sure that all required information has been provided, and prepared in the prescribed format, because with the exception of past performance, our evaluation must be based strictly on the information presented in your technical proposal. Omitted information could cause your proposal to be considered unacceptable, and therefore ineligible for award. Pay attention to the words “must” and
“shall”. If you fail to provide information the government tells the offeror he/she must or shall provide and he/she fails to provide it, it would likely result in a material omission and thereby a deficiency in the proposal.
You also need to be aware of the potential impacts of submitting excess information.
Excess information will NOT be evaluated. For example, if you were to submit three pages when only two pages were allowed, the third page would not be evaluated. This could have a major impact on your evaluation results if critical information is not considered because it was on the third page.
AWARD
Next I would like to briefly summarize the evaluation, selection, and award process.
Initially the price and technical evaluation of your proposal are done separately. This prevents the technical evaluators from being influenced by any pricing considerations.
After the conclusion of these two separate evaluations, the Contracting Officer will determine whether or not award can be made on the basis of initial offers. If this can’t be done, the Contracting Officer will determine the competitive range for the project. If and when the Contracting Officer determines the competitive range for the project, we will inform those offerors determined to be in the competitive range, that they are included in the competitive range for the purpose of discussions (negotiations). The competitive range will consist of the most highly rated proposals. When necessary, the competitive range can be further reduced for purposes of efficiency. Discussions may involve one, or multiple, revisions to an offeror’s proposal and could often include solicitation amendments. All firms still in the competitive range at the conclusion of discussions will be given the opportunity to submit a final proposal revision. But, I need to repeat… you need to submit your best offer initially. There may not be a second chance if you are eliminated from the competitive range on the basis of your initial offer.
The Contracting Officer will select for award the proposal which offers the best value to the Government, which may not be either the lowest priced offer or the offer with the highest technical rating. The decision will involve a comparison of the strengths, weaknesses, and risks in each proposal along with the prices offered. The award will be made to the Offeror that provides the best combination in the judgment of the Contracting
Officer, who will be the Source Selection Authority.
SECTION 00600
REPRESENTATIONS AND CERTIFICATIONS
The next section of the solicitation is 00600, which contains the Representations and
Certifications that must be completed by each offeror. For Joint Ventures, separate forms must be submitted. The forms must be completed in their entirety and submitted with your pricing proposal. Please be very sure to correctly indicate the proper size status for your company.
SECTION 00700
CONTRACT CLAUSES
Section 00700 contains the FAR and DFARS contract clauses required by law and regulation. They are provided in full text. These clauses contain important information, including the following:
--The performance period is 730 calendar days after notice to proceed as identified on the
SF Form 1442.
--Performance and payment bonds, each equal to 100% of the contract price, will be required (FAR 52.228-15, page 00700-131). The successful offeror will be required to provide payment and performance bonds within 10 calendar days after award of the contract.
--Progress payments will be made monthly or more frequently based on percentage of work satisfactorily completed (FAR 52.232-5, page 00700-132).
--The due date for invoice payments is 14 calendar days after receipt of a proper payment request by the designated billing office (FAR 52.232-27, page 00700-136).
-- Permits and Responsibilities (FAR 52.236-7, page 00700-147). This clause states that it is the contractor’s responsibility to obtain any necessary licenses and permits, at no additional cost to the Government. In addition, the contractor is responsible for compliance with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of work. Contractors are responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence; and contractors are responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
SECTION 00800
SPECIAL CONTRACT REQUIREMENTS
Section 00800 includes critical information, including the following:
--Security Requirements for Unclassified Contracts (FAR 52.204-4003, page 00800-187).
This clause identifies the requirements for those contractor or subcontractor employees requiring access to Automated Information Systems and also to foreign nationals working on the contract.
--Minimum Insurance Requirements (FAR 52.0228-4502, age 00800-190). This clause lists the various minimum required insurance.
--Partnering Clause (FAR 52.236.4901, page 00800-191). The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors. The objectives are effective and efficient contract performance and intended to achieve completion within budget, on schedule, and in accordance with plans and specifications.
This concludes my formal remarks. I need to remind you that all questions must be submitted via the Bidder’s Inquiry System, which will be unavailable as of the Close of
Business – 6 July 2009.
I would also like to remind you that anything discussed here today does not change the solicitation, unless incorporated into the solicitation by a formal amendment. This concludes our pre-proposal conference. I realize that your time is valuable and would like to thank you for your time to attend today, your attention and your interest in this project. We look forward to your proposals. We will now take a short break and meet in the parking lot to commence the site visit.
NOTES FROM SITE VISIT: There will most likely be a second site visit to see the buildings that will be demolished. At this site visit, only buildings 827 and 732 were viewed as a group. We will get photos of the buildings to post on FedBizOpps.
| TABLE OF CONTENTS |
| STANDARD FORM 1442 |
| PRICING SCHEDULE |
| SECTION 00100 |
| SECTION 00111 |
| PROPOSAL SUBMITTAL REQUIREMENTS, INSTRUCTIONS, BASIS OF AWARD, AND EVALUATION CRITERIA |
| SECTION 00600 |