About this opportunity
The Library of Congress requires a contractor to replace the independent HVAC unit that conditions the Secured Storage Facility holding the institution's priceless National Treasures. The existing 30-year-old unit has become unreliable due to refrigerant leaks and obsolete controls, posing unacceptable risk to the Treasures. The Library has instituted a two-phase down-select process - Phase One quotations due 12/02/2024 to demonstrate minimum qualifications, and Phase Two responses due 01/16/2025 for the full proposal. The solicitation is unrestricted but may be set aside for small businesses. The Library will evaluate proposals on technical approach and qualifications, and has attached a price schedule for offerors to submit firm fixed pricing.
This procurement is for the design, fabrication, de-installation, and installation of a new HVAC unit capable of maintaining the required temperature and humidity to protect the National Treasures. The contract period is 06/18/2025 to 09/30/2025 with a one-year warranty, and the contractor must ensure technical resources exist for onsite maintenance and repair after the warranty. The Library anticipates a robust competition for this requirement at its facility in Washington, D.C.
Notice text
3 versions
Update #3 · Latest ·
The Library of Congress (Library) requires a contractor to replace the independent HVAC unit that conditions the Secured Storage Facility (SSF) that holds the institution’s priceless National Treasures. The existing unit was first built 30 years ago and received an overhaul in 2006. In the past two years, loss of pressure has caused equipment malfunction. When investigated, the drop in pressure was attributed to small leaks in the refrigeration system, which in turn has required the periodic addition of refrigerant to ensure maintenance of the prescribed collection environment. The constant addition of refrigerant is not a sustainable long-term strategy. Moreover, the process of adding refrigerant itself heightens the risk of creating more leaks.
Comprehensive refurbishment of the unit, if even possible, cannot be completed onsite as the service would require hot work in very close proximity to the National Treasures and would need to be conducted after hours. Finally, the existing electronic controls have become obsolete. Therefore, given the low reliability of having the unit comprehensively repaired, coupled with unacceptable risk to the Treasures, replacement of the existing HVAC unit is the safest and most effective strategy going forward.
Contractor must ensure technical resources exist to maintain and repair the new HVAC unit onsite at the Library under separate contract after the initial warranty period.
The Library anticipates a robust competition. Therefore, the Library has instituted a Two-Phase Down-Select process which involves an initial response to demonstrate offeror meets the minimum qualifications for Phase One. The Phase One quotation is due no later than 12/02/2024 at 12:00 PM Eastern Time. If offeror's quotiation passes Phase One, offeror shall be able to attend a one-time site visit at the Library. Offeror shall RSVP for the site visit per the solicitation requirements and continue to Phase Two. The Phase Two response is due no later than 01/16/2025 at 12:00 Noon.
Offeror is strongly encouraged to read solicitation sections L and M carefully for a comprehensive explanation of the instructions for the responses and of how the Library will evaluate the responses. The Library's responses to offeror questions will be posted as amendments to the solicitation at the same page where the solicitation is located.
Amendment 0001 adds new text to Section C.3.8. The new text has been italicized and underlined. See the amendment for details.
Amendment 0002 provides Attachment J2 - Responses to Offeror Questions.
Update #2 ·
The Library of Congress (Library) requires a contractor to replace the independent HVAC unit that conditions the Secured Storage Facility (SSF) that holds the institution’s priceless National Treasures. The existing unit was first built 30 years ago and received an overhaul in 2006. In the past two years, loss of pressure has caused equipment malfunction. When investigated, the drop in pressure was attributed to small leaks in the refrigeration system, which in turn has required the periodic addition of refrigerant to ensure maintenance of the prescribed collection environment. The constant addition of refrigerant is not a sustainable long-term strategy. Moreover, the process of adding refrigerant itself heightens the risk of creating more leaks.
Comprehensive refurbishment of the unit, if even possible, cannot be completed onsite as the service would require hot work in very close proximity to the National Treasures and would need to be conducted after hours. Finally, the existing electronic controls have become obsolete. Therefore, given the low reliability of having the unit comprehensively repaired, coupled with unacceptable risk to the Treasures, replacement of the existing HVAC unit is the safest and most effective strategy going forward.
Contractor must ensure technical resources exist to maintain and repair the new HVAC unit onsite at the Library under separate contract after the initial warranty period.
The Library anticipates a robust competition. Therefore, the Library has instituted a Two-Phase Down-Select process which involves an initial response to demonstrate offeror meets the minimum qualifications for Phase One. The Phase One quotation is due no later than 12/02/2024 at 12:00 PM Eastern Time. If offeror's quotiation passes Phase One, offeror shall be able to attend a one-time site visit at the Library. Offeror shall RSVP for the site visit per the solicitation requirements and continue to Phase Two. The Phase Two response is due no later than 01/16/2025 at 12:00 Noon.
Offeror is strongly encouraged to read solicitation sections L and M carefully for a comprehensive explanation of the instructions for the responses and of how the Library will evaluate the responses. The Library's responses to offeror questions will be posted as amendments to the solicitation at the same page where the solicitation is located.
Amendment 0001 adds new text to Section C.3.8. The new text has been italicized and underlined. See the amendment for details.
Update #1 ·
The Library of Congress (Library) requires a contractor to replace the independent HVAC unit that conditions the Secured Storage Facility (SSF) that holds the institution’s priceless National Treasures. The existing unit was first built 30 years ago and received an overhaul in 2006. In the past two years, loss of pressure has caused equipment malfunction. When investigated, the drop in pressure was attributed to small leaks in the refrigeration system, which in turn has required the periodic addition of refrigerant to ensure maintenance of the prescribed collection environment. The constant addition of refrigerant is not a sustainable long-term strategy. Moreover, the process of adding refrigerant itself heightens the risk of creating more leaks.
Comprehensive refurbishment of the unit, if even possible, cannot be completed onsite as the service would require hot work in very close proximity to the National Treasures and would need to be conducted after hours. Finally, the existing electronic controls have become obsolete. Therefore, given the low reliability of having the unit comprehensively repaired, coupled with unacceptable risk to the Treasures, replacement of the existing HVAC unit is the safest and most effective strategy going forward.
Contractor must ensure technical resources exist to maintain and repair the new HVAC unit onsite at the Library under separate contract after the initial warranty period.
The Library anticipates a robust competition. Therefore, the Library has instituted a Two-Phase Down-Select process which involves an initial response to demonstrate offeror meets the minimum qualifications for Phase One. The Phase One quotation is due no later than 12/02/2024 at 12:00 PM Eastern Time. If offeror's quotiation passes Phase One, offeror shall be able to attend a one-time site visit at the Library. Offeror shall RSVP for the site visit per the solicitation requirements and continue to Phase Two. The Phase Two response is due no later than 01/16/2025 at 12:00 Noon.
Offeror is strongly encouraged to read solicitation sections L and M carefully for a comprehensive explanation of the instructions for the responses and of how the Library will evaluate the responses. The Library's responses to offeror questions will be posted as amendments to the solicitation at the same page where the solicitation is located.
Files
| File | Type | Posted |
|---|---|---|
| 030ADV25Q0042 0002.pdf | ||
| Attachment J2 - Responses to Offeror Questions - 11-22-2024.pdf | ||
| 030ADV25Q0042 0001.pdf | ||
| 030ADV25Q0042.pdf | ||
| Attachment J1 - Price Schedule 11-12-24 - 1 page.xlsx | XLSX spreadsheet |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| HVAC Unit Replacement | National Oceanic and Atmospheric Administration | Total Small Business | |
| FY27 HVAC Maintenance Service | MICC Fort Sam Houston | Total Small Business | |
| Replace HVAC Rooftop Units at Building 2275 | Army National Guard | No set-aside | |
| OK-deep fork NWR-quarters HVAC replacem | — | Total Small Business | |
| Replacement of 10 Ton HVAC Unit, Bldg. 11, PR ANG | Army National Guard | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity