About this opportunity

The U.S. Army Corps of Engineers, New England District is soliciting bids for electrical upgrades to the gatehouse at East Brimfield Lake in Fiskdale, Massachusetts. The work includes upgrading the existing 100A switchboard and lighting panel, replacing the gatehouse feeder from the utility building, and removing and replacing branch circuit conductors. Optional items may include replacing floodlights, interior lighting fixtures, and the electric unit heater. The project is being set aside for small businesses, with an estimated value between $250,000 and $500,000 and a period of performance of approximately 180 days.

The NAICS code for this work is 238210. The solicitation is planned to be issued in March 2023, with bids due by April 16, 2024. The U.S. Army Corps of Engineers, New England District is the issuing agency, and the place of performance is Sturbridge, MA 01518. Potential offerors should review the attached construction specifications, drawings, and bid abstract for additional details on the project requirements and evaluation criteria.

Notice text

2 versions

Update #2 · Latest ·

The U.S. Army Corps of Engineers, New England District is issuing a set aside for small business contractors to perform Gatehouse Electrical Upgrades at East Brimfield Lake in Fiskdale, Massachusetts. The NAICS code for the work described below is 238210. The project is planned to be issued in March 2023 and will be set aside for Small Businesses. The period of performance will be approximately 180 days. The estimated magnitude of this project is between $250,000 and $500,000. The work of this project involves electrical upgrades to the gatehouse at East Brimfield Dam. The work shall include the following at a minimum: . Upgrade the existing 100A, 120/208V, 3 , 4W switchboard and 100A MLO, 120/208V, 3 , 4W lighting panel within the same enclosure inside the gatehouse at East Brimfield Lake Dam. . The gatehouse feeder from the existing 100A-3P circuit breaker in the panelboard within the utility building, routed to the gatehouse switchboard in steel conduit in the dam?s concrete envelope, shall be pulled back, removed, and replaced in existing conduit. . Branch circuit conductors from the gatehouse switchboard and lighting panel (i.e. Gate Hoist Motors, Electric Unit Heater, Lighting, Receptacles) shall be removed and replaced to the first device, within existing conduit. . Optional items to be included in this project include removal and replacement of existing floodlights; removal and replacement of interior lighting fixtures; and removal and replacement of the existing unit heater.

Update #1 ·

The U.S. Army Corps of Engineers, New England District is issuing a set aside for small business
contractors to perform Gatehouse Electrical Upgrades at East Brimfield Lake in Fiskdale, Massachusetts.
The NAICS code for the work described below is 238210. The project is planned to be issued in March
2023 and will be set aside for Small Businesses. The period of performance will be approximately 180
days. The estimated magnitude of this project is between $250,000 and $500,000.
The work of this project involves electrical upgrades to the gatehouse at East Brimfield Dam. The work
shall include the following at a minimum:
. Upgrade the existing 100A, 120/208V, 3Ø, 4W switchboard and 100A MLO, 120/208V, 3Ø, 4W
lighting panel within the same enclosure inside the gatehouse at East Brimfield Lake Dam.
. The gatehouse feeder from the existing 100A-3P circuit breaker in the panelboard within the
utility building, routed to the gatehouse switchboard in steel conduit in the dam’s concrete
envelope, shall be pulled back, removed, and replaced in existing conduit.
. Branch circuit conductors from the gatehouse switchboard and lighting panel (i.e. Gate Hoist
Motors, Electric Unit Heater, Lighting, Receptacles) shall be removed and replaced to the first
device, within existing conduit.
. Optional items to be included in this project include removal and replacement of existing
floodlights; removal and replacement of interior lighting fixtures; and removal and replacement
of the existing unit heater.

Files

Similar open opportunities

Opportunity Agency Set-aside Responses due
Dike B Generator Installation, Mansfield Hollow Dam, Mansfield Center, CT Mansfield Center, Connecticut, United States · NAICS 238290 ENDIST New England Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors