About this opportunity

The U.S. Army Corps of Engineers, New England District will issue a Total Small Business set-aside Invitation for Bids for the East Bulkhead Replacement at the East Boat Basin on the Cape Cod Canal in Sandwich, Massachusetts, with the solicitation and response date available on or about December 1, 2026. The procurement is classified under NAICS 237990 (Other Heavy and Civil Engineering Construction) with a $45 million size standard and PSC Y1QA (Construction of Restoration of Real Property). The solicitation is available online only, and the notice states that neither telephonic, mailed, nor faxed requests for hard copies will be accepted.

The work replaces the east sheet pile bulkhead at the harbor entrance. Scope includes installing approximately 950 linear feet of steel sheet piles with interior whalers about five feet in front of the existing bulkhead; installing wood fender piles; cutting off existing steel sheet piles about 10 feet below grade and backfilling between old and new sheets with crushed stone; installing new concrete deadmen, tie rods, and walers connected to new PZ40 sheet piles; replacing the light system and existing conduits while protecting the associated power supply; and installing new bollards and cleats. Specific work tasks include, but are not limited to, these items.

Construction is expected to take about 23 months, including a 12-month turf establishment period. The estimated construction cost is between $10,000,000 and $25,000,000. The notice names no incumbent and no industry day, sources sought, or RFI.

Notice text

The U.S. Army Corps of Engineers, New England District will be issuing an Invitation for Bids for the East bulkhead Replacement project located in Sandwich, MA. This procurement is a  Small Business Set Aside Invitation for Bid (IFB). The NAICS code for the work is 237990, Other Heavy and Civil Engineering Construction, with a size standard of $45M. Construction is expected to take about 23 months to complete, including a 12 month turf establishment period. The estimated construction cost is between $10,000,000.00 and $25,000,000.00. Any responsible contractor meeting this standard may submit a bid to be considered by the New England District.

The East Boat Basin is a small sheltered harbor for small craft located near the east end of the Cape Cod Canal on the Cape side in Sandwich, Massachusetts.  On both sides of the entrance to the harbor, facing the canal, are sheet pile bulkheads.  This project will replace the east sheet pile bulkhead with a completely new bulkhead.

Specific work tasks include, but are not limited to, the following: install approximately 950 linear feet of steel sheet piles with interior whalers to create a new bulkhead about five feet in front of the existing bulkhead sheets; install a system of wood fender piles to protect against ships and boats; cut off the existing steel sheet piles about 10 feet below grade, backfill the space between old and new sheet piles with crushed stone; install new concrete dead men, tie rods and waler connected to new PZ40 sheet piles; replace light system and existing conduits and protect existing associated power supply system; install new bollards, and cleats.

This is not an invitation for bids at this time. The solicitation requirements and contract documents including instructions for submission and the response date will be available on or about December 1, 2026. Neither telephonic, mailed, nor faxed requests for hard copies of this solicitation will be accepted. The solicitation will only be available online; in order to download the solicitation, offerors must access the System of Award Management website (https://sam.gov/). All responsible sources may submit a bid which shall be considered by the New England District. Additional questions may be emailed to Kyle Hall, New England District Contract Specialist, at kyle.k.hall@usace.army.mil or by phone at (978) 318-8479

Notice history

Notice Type Posted
This notice Latest pre-solicitation Pre-Solicitation
East Bulkhead Replacement, East Boat Basin, Cape Cod Canal, Sandwich MA Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Construction Services for Confined Aquatic Disposal Cell Construction and Maintenance Dredging of the Providence River Federal Navigation Project, Providence, Rhode Island. Concord, Massachusetts 01742, United States · NAICS 237990 ENDIST New England No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors