C04 Attachment 3 - Specifications Tony Grove.pdf
PDF 2 MB Posted
- Attached to
- GAOA Tony Grove Dam Spillway Capacity & Seismic Mitigation, Uinta/Wasatch/Cache National Forest
- Solicitation number
- 1240BH27Q0002
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a construction specifications document for the Tony Grove Reservoir Outlet project on the Uinta-Wasatch-Cache National Forest in Cache County, Utah, prepared for the US Forest Service in March 2026. The specifications provide detailed technical requirements for multiple construction work items and material standards.
The document outlines nine primary bid items: (1) Clearing, Grubbing and Stripping of designated excavation and embankment areas with removal of rocks larger than 4 inches; (2) Pollution Control including Storm Water Pollution Prevention Plan (SWPPP) development and Utah Pollutant Discharge Elimination System (UPDES) permit procurement, with payment prorated monthly over estimated project duration; (3) Construction Surveys performed by experienced surveyors under a licensed Professional Land Surveyor, with payment based on percentage of planned work; (4) Mobilization and Demobilization with staged payments at 5%, 10%, and 25% contract milestones; (5) Removal of Water requiring dewatering and surface water diversion with a mandatory dewatering plan submitted two weeks prior to work commencement; (6) Unclassified Excavation with blasting prohibited and waste materials disposed in designated borrow areas; (7) Earthfill using Class A compaction to 96% of maximum laboratory density with moisture content within 1% below to 2% above optimum; (8) Roadbase material from commercial sources meeting specified durability and abrasion requirements, compacted to 95% maximum laboratory density; (9) Filter Sand and (10) Gravel Drain materials meeting specified gradation requirements. Additional material specifications address aggregates, Portland cement, steel reinforcement, plastic pipe, concrete, geotextiles, and various structural components. The project requires contractor quality control testing, adherence to OSHA excavation standards, environmental protection measures, and compliance with state and local regulations regarding dust control, waste disposal, and water pollution prevention.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C04 Attachment 5 - DBA WD UT20260105 Cache Co 051826.pdf | ||
| C04 Attachment 2 - SOI Tony Grove.xlsx | XLSX spreadsheet | |
| C04 Attachment 4 - Drawings Tony Grove.pdf | ||
| C04 Attachment 1 - Solicitation Tony Grove.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION SPECIFICATIONS
GGAAOOAA TToonnyy GGrroovvee RReesseerrvvooiirr
OOuuttlleett Uinta-Wasatch-Cache National Forest
Cache County, Utah
Prepared for:
US Forest Service
March 2026
201901-020
TABLE OF CONTENTS
Tony Grove Reservoir Outlet
US Forest Service Uinta-Wasatch-Cache National Forest
Cache County, Utah
CONSTRUCTION SPECIFICATIONS
Title Section Clearing and Grubbing Structure Removal Pollution Control Construction Surveys Mobilization and Demobilization Water for Construction Removal of Water Excavation Earthfill Drainfill Concrete for Major Structures Steel Reinforcement Plastic Pipe Steel Pipe Miscellaneous Pipeline Appurtenances Articulating Concrete Block Revetment System Water Control Gates Metal Fabrication Instrumentation Contractor Quality Control Field Office Precast Concrete Vault Restroom Roadways
MATERIAL SPECIFICATIONS
Title Section Aggregates for Drainfill and Filters Aggregates for Portland Cement Concrete Portland Cement Supplementary Cementitious Materials Chemical Admixtures for Concrete Concrete Curing Compound Steel Reinforcement (for concrete) Plastic Pipe Slide Gates Metal Galvanizing Geotextile
(210-VI-NEH, May 2001) 2-1
Construction Specification 2—Clearing and Grubbing
1. Scope The work consists of clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated areas.
2. Protection of existing vegetation Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the duration of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.
Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic shall not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.
Any cuts, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.
Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk. All roots 1-inch or larger in diameter that are cut, broken, or otherwise severed during construction operations shall have the end smoothly cut perpendicular to the root. Roots exposed during excavation or other operations shall be covered with moist earth or backfilled as soon as possible to prevent the roots from drying out.
3. Marking The limits of the area(s) to be cleared and grubbed will be marked by stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunk about 6 feet above the ground surface.
4. Clearing and grubbing All trees not marked for preservation and all snags, logs, brush, stumps, shrubs, rubbish, and similar materials shall be cleared from within the limits of the designated areas. Unless otherwise specified, all stumps, roots, and root clusters that have a diameter of 1 inch or larger shall be grubbed out to a depth of at least 2 feet below subgrade for concrete structures and 1 foot below the ground surface at embankment sites and other designated areas.
5. Disposal All materials cleared and grubbed from the designated areas shall be disposed of at locations shown on the drawings or in a manner specified in section 7. The contractor is responsible for complying with all local rules and regulations and the payment of any and all fees that may result from disposal at locations away from the project site.
6. Measurement and payment Method 1—For items of work for which specific units prices are established in the contract, the cleared and grubbed area is measured to the nearest 0.1 acre. Payment for clearing and grubbing is made for the total area within the designated limits at the contract unit price. Such payment will
(210-VI-NEH, May 2001) 2-2 constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 2—For items of work for which specific unit prices are established in the contract, the length of the cleared and grubbed area is measured to the nearest full station (100 feet) along the line designated on the drawing or identified in the specifications. Payment for clearing and grubbing is made for the total length within the designated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 3—For items of work for which specific unit prices are established in the contract, each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet are measured before removal. The size of each tree and snag is determined by measuring its trunk at breast height above the natural ground surface. The size of each log is determined by measuring the butt and by measuring its length from butt to tip.
The size of each stump is measured at the top. Diameter is determined by dividing the measured circumference by 3.14.
Payment for clearing and grubbing of each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet or larger is made at the contract unit price for its size designation as determined by the following schedule:
Measured diameter Size designation
(in) (in)
4 to 8
8 to 12 10
12 to 24 18
24 to 36 30
36 to 60 48 Over 60 60
The sum of such payments shall constitute full compensation for clearing and grubbing (including the clearing and grubbing of smaller trees, stumps, snags, logs, brush, shrubs, and roots), applicable permits and associated fees, and rubbish removal. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 4—For items of work for which specific lump sum prices are established in the contract, payment for clearing and grubbing is made at the contract lump sum price. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 7.
7. Items of work and construction details Section 1, Scope is modified to include stripping. Items of work to be performed in conformance with this specification and the construction details are:
Bid Item 1 – Clearing, Grubbing and Stripping
This item shall consist of clearing the area within the excavation and embankment footprints.
Approximately 6 inches of soil, as directed by the Engineer, shall be stripped from the footprint of the excavation and embankments to remove excess organic matter. This work shall include removing the existing rocks larger than 4 inches in size from the embankment footprints.
Measurement and Payment shall be in accordance with Method 1 of Section 6.
UT – Tony Grove Reservoir Outlet, December 2021 2-3
Construction Specification 3—Structure Removal
The work shall consist of the removal, salvage, and disposal of structures (including fences) from the designated areas.
2. Marking Each structure or structure part to be removed will be marked with stakes, flags, paint, or other suitable method.
3. Removal All structures designated for removal in the contract shall be removed to the specified extent and depth.
4. Salvage Structures or structure parts that are designated to be salvaged shall be carefully removed and neatly placed in the specified or approved storage location. Salvaged structures that are capable of being disassembled shall be dismantled into individual members or sections. Such structures shall be neatly and systematically match marked with paint before disassembly. All connectors and other parts shall be marked to indicate their proper location within the structure and shall be fastened to the appropriate structural member or packed in suitable containers.
Material from fences designated to be salvaged shall be placed outside the work area on the property on which the fence was originally located. Fence wire shall be rolled into uniform rolls of suitable size and neatly piled with other salvaged materials. Posts and rails shall be neatly stacked.
5. Disposal of refuse materials Refuse materials resulting from structure removal shall be disposed of in a manner and at locations specified in section 7 of this specification or in an acceptable manner and at locations approved by the contracting officer. Disposal by burning shall be in accordance with local rules and regulations.
6. Measurement and payment For items of work for which specific lump sum prices are established by the contract, payment for structure removal is made at the contract lump sum price.
Such payment will constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and
Compensation for any item of work described in the contract, but not listed as a contract line item number in the bid schedule, is included in the payment for the item of work to which it is made subsidiary. Such items and items to which they are made subsidiary are identified in section 7 of this specification.
UT – Tony Grove Reservoir Outlet, December 2021
(210-VI-NEH, May 2001) 3-1
7. Items of work and construction details The work shall consist of the structural removal work as specified below.
Subsidiary Item – Existing Structure Demolition
This item shall consist of the work required to demolish the existing outlet works designated for removal on the Drawings.
Blasting will not be allowed.
The structures to be demolished shall be disposed by the Contractor at sites of his own choosing away from the site of the work. The disposal shall be in an environmentally acceptable manner that does not violate applicable laws, rules, and regulations.
Section 6 of this specification, Measurement and payment, shall not apply. Demolition of existing structures is subsidiary to the Excavation bid item.
UT – Tony Grove Reservoir Outlet, December 2021 3-2
(210-VI-NEH, January 2014) 5–1
Construction Specification 5—Pollution Control
The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.
The following BioPreferred® product categories are applicable to this specification:
— mulch and compost materials
— erosion control materials
— fertilizers
— agricultural spray adjuvants
Material
Silt fence shall conform to the requirement of Materials Specification 592, Geotextile. All other material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.
2. Erosion and sediment control measures and works
The measures and works shall include, but are not limited to, the following:
Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.
Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.
Mulching—Mulching to provide temporary protection of the soil surface from erosion.
Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.
Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.
Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
(210-VI-NEH, January 2014) 5–2
Sediment filters—Straw bale filters or geotextile silt fences trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under or around them. Silt fences shall be installed and maintained in accordance with ASTM D6462. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Other—Additional protection measures as specified in section 8 of this specification or required by Federal, State, or local government.
4. Chemical pollution
The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to collect and temporarily contain chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer washwater, or asphalt, produced as a by-product of the construction activities. Pollutants shall be disposed of in accordance with appropriate state and Federal regulations. At the completion of the construction work, tanks, barrels, and sumps shall be removed and the area restored to its original condition as specified in section 8 of this specification. Sump removal shall be conducted without causing pollution.
Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.
5. Air pollution
The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.
Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.
All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.
6. Maintenance, removal, and restoration
All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed, and the site restored to near original condition.
(210-VI-NEH, January 2014) 5–3
7. Measurement and payment
Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.
Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.
Method 3—For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.
8. Items of work and construction details
The Biopreferred categories listed in Section 1 of this specification are not applicable to this project.
Items of work to be performed in conformance with this specification and the construction details are:
Bid Item 2 - Pollution Control
The work shall consist of performing the work described in Section 1 of this specification. The work shall also include developing a Storm Water Pollution Prevention Plan (SWPPP) and procuring a Utah Pollutant Discharge Elimination System (UPDES) Storm Water permit. The SWPPP shall be developed by the Contractor or an experienced consultant in the employ of the Contractor. This bid item shall also include all work required to provide, install, maintain, and remove the items required by the permit.
Concrete trucks, pumpers and equipment clean-up shall be completed in an existing disturbed area away from streams and vegetation.
An access plan shall be submitted in writing prior to beginning construction.
The Contractor shall provide and maintain, in a neat sanitary condition, such accommodations for the use of his employees as may be necessary to comply with the requirements of the State and Local Boards of Health, or of other bodies or tribunals having jurisdiction therewith. Attention is directed to federal, state, and local laws, rules, and regulations concerning construction safety and health standards. The contractor shall not require any worker to work in surroundings or under conditions which are unsanitary, hazardous or dangerous to his health or safety.
The Contractor shall provide toilet facilities for his employees, subcontractors, and the representatives of the Owner and regulatory agencies on the project site.
Payment for this bid item shall be made in accordance with Method 3, Section 7, of this specification. Payment for this item shall constitute full compensation for the portions of Subsidiary Item – Water for Construction that is associated with this bid item.
UT – Tony Grove Reservoir Outlet, December 2021 5–4
(210-VI-NEH, January 2009) 7-1
Construction Specification 7—Construction Surveys
The work consists of performing all surveys, measurements, and computations required by this specification.
2. Equipment and material
Equipment for construction surveys shall be of a quality and condition to provide the required accuracy. The equipment shall be maintained in good working order and in proper adjustment at all times. Records of repairs, calibration tests, accuracy checks, and adjustments shall be maintained and be available for inspection by the engineer. Equipment shall be checked, tested, and adjusted as necessary in conformance with manufacturer's recommendations.
Material is field notebooks, stakes, templates, platforms, equipment, spikes, steel pins, tools, and all other items necessary to perform the work specified.
3. Quality of work
All work shall follow recognized professional practice and the standards of the industry unless otherwise specified in section 9 of this specification. The work shall be performed to the accuracy and detail appropriate for the type of job. Notes, sketches, and other data shall be complete, recorded neatly, legible, reproducible and organized to facilitate ease in review and allow reproduction of copies for job documentation. Survey equipment that requires little or no manual recording of field data shall have survey information documented as outlined in section 9 of this specification.
All computations shall be mathematically correct and shall include information to identify the bid item, date, and who performed, checked, and approved the computations. Computations shall be legible, complete, and clearly document the source of all information used including assumptions and measurements collected.
If a computer program is used to perform the computations, the contractor shall provide the engineer with the software identification, vendor's name, version number, and other pertinent data before beginning survey activities. Computer generated computations shall show all input data including values assigned and assumptions made.
The elevations of permanent and temporary bench marks shall be determined and recorded to the nearest 0.01 foot. Differential leveling and transit traverses shall be of such precision that the error of vertical closure in feet shall not exceed plus or minus 0.1 times the square root of the traverse distance in miles. Linear measurements shall be accurate to within 1 foot in 5,000 feet, unless otherwise specified in section 9 of this specification. The angular error of closure for transit traverses shall not exceed 1 minute times the square root of the number of angles turned.
The minimum requirements for placing slope stakes shall be at 100-foot stations for tangents, as little as 25 feet for sharp curves, breaks in the original ground surface and at any other intermediate stations necessary to ensure accurate location for construction layout and measurement. Slope stakes and cross sections shall be perpendicular to the centerline. Significant breaks in grade shall be determined for cross sections. Distances shall be measured horizontally
(210-VI-NEH, January 2009) 7-2 and recorded to the nearest 0.1 foot. Side shots for interim construction stakes may be taken with a hand level.
Unless otherwise specified in section 9 of this specification, measurements for stationing and establishing the location of structures shall be made to the nearest 0.1 foot.
Elevations for concrete work, pipes, and mechanical equipment shall be determined and recorded to the nearest 0.01 foot. Elevations for earth work shall be determined and recorded to the nearest
0.1 foot.
4. Primary control
The baselines and bench marks for primary control, necessary to establish lines and grades needed for construction, are shown on the drawings and have been located on the job site.
These baselines and bench marks shall be used as the origin of all surveys, layouts, and measurements to establish construction lines and grades. The contractor shall take all necessary precautions to prevent the loss or damage of primary control points. Any stakes or control points lost or damaged by construction activity will be reestablished by the contractor or at contractor expense.
5. Construction surveys
Before work starts that requires contractor performed surveys, the contractor shall submit in writing for the engineer's review: the name, qualifications, and experience of the individuals to be assigned to the survey tasks.
Method 1—Contractor performed surveys shall include:
• checking and any supplemental or interim staking
• performing quantity surveys, measurements, and computations for progress payment
• other surveys as described in section 9 of this specification
Method 2—Contractor performed surveys shall consist of all work necessary for:
• establishing line and grade for all work
• setting slope stakes for all work
• checking and any supplemental or interim staking
• establishing final grade stakes
• performing quantity surveys, measurements, and computations for progress payment
• other surveys as described in section 9 of this specification
(210-VI-NEH, January 2009) 7-3
Method 3—Contractor performed surveys shall consist of all work necessary for:
• establishing line and grade for all work
• setting slope stakes for all work
• checking and any supplemental or interim staking
• establishing final grade stakes
• performing quantity surveys, measurements, and computations for progress payments
• performing original (initial) and final surveys for determinations of final quantities
• other surveys as described in section 9 of this specification.
6. Staking
The construction staking required for the item shall be completed before work on any item starts.
Construction staking shall be completed as follows or as otherwise specified in section 9 of this specification:
Clearing and grubbing—The boundary of the area(s) to be cleared and grubbed shall be staked or flagged at a maximum interval of 200 feet, closer if needed, to clearly mark the limits of work.
When contractor staking is the basis for determining the area for final payment, all boundary stakes will be reviewed by the engineer before start of this work item.
Excavation and fill—Slope stakes shall be placed at the intersection of the specified slopes and ground line. Slope stakes and the reference stakes for slopes shall be marked with the stationing, required cut or fill, slope ratio, and horizontal distance from the centerline or other control line.
The minimum requirements for placing slope stakes is outlined in section 3, Quality of work.
Structures—Centerline and offset reference line stakes for location, alignment, and elevation shall be placed for all structures.
7. Records
All survey data shall be recorded in fully identified standard hard-bound engineering survey field notebooks with consecutively numbered pages. All field notes and printed data shall include the purpose or description of the work, the date the work was performed, weather data, sketches, and the personnel who performed and checked the work. Electronically generated survey data and computations shall be bound, page numbered, and cross referenced in a bound field notebook containing the index for all survey activities. All work shall follow recognized professional practice.
The construction survey records shall be available at all times during the progress of the work for examination and use by the engineer and when requested, copies shall be made available. The original field notebooks and other records shall be provided to and become the property of the owner before final payment and acceptance of all work.
(210-VI-NEH, January 2009) 7-4
Complete documentation of computations and supporting data for progress payments shall be submitted to the engineer with each invoice for payment as specified in section 9 of the specification. When the contractor is required to conduct initial and final surveys as outlined in section 5, Construction Surveys, notes shall be provided as soon as possible after completion to the engineer for the purpose of determining final payment quantities.
8. Payment
Method 1—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds, after presentation of correct and accurate invoices by the contractor showing related costs and evidence of the charges of suppliers, subcontractors, and others for supplies furnished and work performed. Invoices for the total amount of the contract price will not be accepted until all surveys are complete and required documentation has been determined complete. If the total of such payments is less than the lump sum contract price for this item, the unpaid balance will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of all work under the bid item.
Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds with progress payment amounts determined as a percentage of the total work planned as projected from the contractor's approved construction schedule. Payment of the lump sum contract price will constitute full compensation for completion of all work under this bid item.
All Methods—Payment will not be provided under this item for the purchase price of materials or equipment having a residual value.
Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the item to which they are made subsidiary are identified in section 9 of this specification.
9. Items of work and construction details
Items of work to be performed in conformance with this specification and the construction details are:
Bid Item 3 - Construction Surveys
The personnel who perform the survey work shall be experienced construction surveyors (crew chief) under supervision and direction of a professional land surveyor (PLS) licensed in the State of Utah. The crew chief shall have a minimum of 5 years of experience in responsible charge of construction surveys for construction similar in nature to that required for this contract. A resume detailing the experience of the PLS and the crew chief shall be submitted to the Engineer.
Construction surveys shall be performed in accordance with Method 2 of Section 5.
Hard copy survey records need not be submitted if all described information is contained in electronic files transmitted to the Engineer.
Payment for this item will be made in accordance with Method 2 described in Section 8 of this specification.
UT – Tony Grove Reservoir Outlet, December 2021 7-5
Construction Specification 8—Mobilization and Demobilization
The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.
2. Equipment and material
Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable;
and other items specified in section 4 of this specification.
Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.
This work includes mobilization and demobilization required by the contract at the time of award.
If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.
3. Payment
Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.
Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.
(210-VI-NEH, May 2001) 8-1
4. Items of work and construction details are:
Bid Item 4 - Mobilization and Demobilization
This item shall consist of the mobilization and demobilization of the Contractor’s forces and equipment necessary to perform the work required under the contract. The work shall also include participation of Contractor’s key personnel in weekly coordination meetings with the Engineer.
Section 3 of this specification, “Payment” shall not apply. Payment for mobilization and demobilization will be made as follows:
A. When 5% of the original contract amount is earned, 35% of the amount bid for mobilization and demobilization will be paid.
B. When 10% of the original contract amount is earned, an additional 35% of the amount bid for mobilization and demobilization will be paid.
C. When 25% of the original contract amount is earned, the remaining amount bid for mobilization and demobilization will be paid.
D. For purposes of payment, the bid amount for mobilization and demobilization shall not be included in the calculation of the original contract amount or the percentage of the contract earned.
UT – Tony Grove Reservoir Outlet, December 2021 8-2
(210-VI-NEH, January 2009) 10-1
Construction Specification 10—Water for Construction
The work consists of furnishing, transporting, measuring, and applying water as specified.
2. Facilities and equipment
The contractor shall install and maintain access and haul roads and furnish, operate, and maintain all pumps, meters, piping, tanks, storage, and other facilities required to load, transport, store, distribute, and use construction water as specified.
These facilities shall be equipped with accurate, work dedicated meters; tanks of known volume;
or other devices that provide a correct measurement of water supplied. Meters shall be installed at the point of delivery into water hauling equipment or application system, such as sprinkler systems or flooding systems, as specified.
3. Dust abatement and haul road maintenance
Water for dust abatement and haul road maintenance shall be applied to haul roads and other dust producing areas as needed to prevent air pollution or excessive dust (which causes impaired vision on trafficked roads and in work areas) and to maintain the roads in good condition for safe and efficient operation during periods of use. Roads that may be jointly used with the public and by the contractor's equipment shall have dust abatement provisions acceptable to the public entity that has road maintenance responsibility. Compensation for water used for dust abatement and haul road maintenance shall be as specified in section 8 of this specification.
4. Earthfill, drainfill, and rockfill
Water required for proper installation of earthfill, drainfill, and/or rockfill shall be used in the fill materials as specified in the applicable construction specification(s). Compensation for construction water used for earthfill, drainfill, and/or rockfill shall be as specified in section 8 of this specification.
5. Concrete, mortar, and grout
Water required in the mixing or curing of concrete, shotcrete, roller compacted concrete, or other portland cement mortar or grout shall meet the requirements of the applicable construction specifications and shall be used in conformance with those specifications. Payment for construction water used in these items is covered by the applicable concrete, mortar, or grout specification, or a combination of these.
6. Other construction requiring water
Water required and used for other construction activities under this contract, but not specifically covered by this specification shall be considered subsidiary to the item(s) of work that requires its use.
(210-VI-NEH, January 2009) 10-2
7. Measurement and payment
Method 1—For water items for which specific unit prices are established in the contract, the volume of water furnished and used in accordance with the specifications will be measured to the nearest 1,000 gallons.
Payment for water is made at the contract unit price. Such payment will constitute full compensation for the direct costs of water. All other costs necessary for transportation, distribution, and application are subsidiary to the items of work with which they are associated.
Method 2—For water items for which specific unit prices are established in the contract, the volume of water furnished and used in accordance with the specifications will be measured to the nearest 1,000 gallons.
Payment for water and the cost associated with transportation, distribution, and application is made at the contract unit price. Such payment will constitute full compensation for completion of the work.
Method 3—For water items for which specific unit prices are established in the contract, the volume of water used in accordance with the specifications will be measured to the nearest 1,000 gallons.
Payment for water is made at the contract unit price. Such payment, excluding water cost, will constitute full compensation for completion of the work.
All methods—The following provisions apply to all methods of measurement and payment:
• The measurement for payment will include all water used except as noted in sections 5, 6, and 8 of this specification. Measurement for payment will not include water that is used inappropriately or in excess of that needed to accomplish the specified task.
• Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary.
Such items and the items to which they are made subsidiary are identified in section 8 of are:
Subsidiary Item - Water for Construction
This item shall consist of obtaining, transporting, and applying all water required to complete the work. The Contractor will be allowed to use water from the Tony Grove Reservoir for earthfill moisture conditioning, dust abatement, and other work where the reservoir water quality meets the specified requirements for the intended use.
No separate payment shall be made for this item. Compensation for water used shall be subsidiary to the items of work that require its use.
UT – Tony Grove Reservoir Outlet, December 2021 10-3
(210-VI-NEH, May 2001) 11-1
Construction Specification 11—Removal of Water
The work consists of the removal of surface water and ground water as necessary to perform the construction required by the contract in accordance with the specifications. It shall include: (1) constructing, installing, building, and maintaining all necessary temporary water containment facilities, channels, and diversions; (2) furnishing, installing, and operating all necessary pumps, piping, and other facilities and equipment; and (3) removing all such temporary works and equipment after their intended function is no longer required.
2. Diverting surface water
The contractor shall install, maintain, and operate all cofferdams, channels, flumes, sumps, and all other temporary diversion and protective works needed to divert streamflow and other surface water through or around the construction site. Control of surface water shall be continuous during the period that damage to construction work could occur. Unless otherwise specified and/or approved, the diversion outlet shall be into the same drainageway that the water would have reached before being diverted.
The contractor shall furnish the contracting officer, in writing, a proposed plan for diverting surface water before beginning any construction activities for which a diversion is required, unless waived in section 8 of this specification. Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities related to this activity during the process of completing the work as specified.
3. Dewatering the construction site
Foundations, cutoff trenches, and all other parts of the construction site shall be dewatered and kept free of standing water and muddy conditions as necessary for the proper execution of the work. The contractor shall furnish, install, operate, and maintain all drains, sumps, pumps, casings, well points, and all other equipment required to properly dewater the site as specified.
Dewatering systems that cause a loss of soil fines from the foundation areas will not be permitted.
The contractor shall furnish the contracting officer, in writing, a proposed plan for dewatering before commencing with any construction activity for which dewatering may be required, unless waived in section 8 of this specification. Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities for completing the specified work.
4. Dewatering borrow areas
The contractor shall maintain all borrow areas free of surface water or otherwise provide for timely and effective removal of surface and subsurface water that accumulates within the borrow area, unless waived in section 8 of this specification. Borrow material shall be processed as necessary to achieve proper and uniform moisture content at the time of placement.
(210-VI-NEH, May 2001) 11-2
If pumping to dewater borrow areas is included as a bid item of work in the bid schedule, each pump discharge pipe shall be equipped with a water meter. The meter shall be such that the measured quantity of water is accurate within 3 percent of the true quantity. The contractor shall provide necessary support to perform accuracy tests of the water meter when requested by the contracting officer.
5. Erosion and pollution control
Removal of water from the construction site, including the borrow areas, shall be accomplished so that erosion and the transporting of sediment and other pollutants are minimized. Dewatering activities shall be accomplished in a manner that the water table water quality is not altered.
Pollution control activities shall not conflict with the requirements of Construction Specification 5, Pollution Control, if it is a part of this contract.
6. Removal of temporary works
When temporary works are no longer needed, the contractor shall remove and return the area to a condition similar to that which existed before construction. Areas where temporary works were located shall be graded for sightly appearance with no obstruction to natural surface waterflows or the proper functioning and access to the works of improvement installed. The contractor shall exercise extreme care during the removal stages to minimize the loss of soil sediment and debris that was trapped during construction.
Pipes, casings, and any other material used to dewater the site shall be removed from temporary wells. The wells shall be filled to ground level with clean gravel or other suitable material approved by the contracting officer. The contractor shall exercise extreme care to prevent pollution of the ground water by these actions.
7. Measurement and payment
Method 1—Items of work listed in the bid schedule for removal of water, diverting surface water, and dewatering construction sites and borrow areas are paid for at the contract lump sum prices.
Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 2—Items of work listed in the bid schedule for removal of water, diverting surface water, dewatering construction sites, and dewatering borrow areas are paid for at the contract lump sum prices. Such payment will constitute full compensation for furnishing, installing, operating, and maintaining the necessary trenches, drains, sumps, pumps, and piping and for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work. The exception is that additional payment for pumping to dewater borrow areas and the removal of water will be made as described in the following paragraph.
If pumping to dewater borrow areas is a contract bid item, payment is made at the contract unit price, which shall be the price per 1,000 gallons shown in the bid schedule. Such payment will constitute full compensation for pumping only. Compensation for equipment and preparation and for other costs associated with pumping is included in the lump sum payment for removal of water or the lump sum payment for dewatering the borrow areas. Payment is made only for pumping that is necessary to dewater borrow areas that cannot be effectively drained by gravity
(210-VI-NEH, May 2001) 11-3 or that must have the water table lowered to be usable as a suitable borrow source. Pumping for other purposes will not be included for payment under this item.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the contract line item to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 8 of this specification.
are:
Bid Item 5 - Removal of Water
This item shall consist of the work required to dewater the excavation areas and divert surface water within the project limits.
It is required that the ground water level be maintained at least 2 feet below the bottom of all excavations and subgrade elevations. Dewatering will likely require wells, trenches, and/or sumps. Routing reservoir inflows or constructing temporary retention of reservoir inflows will likely be required to construct the new outlet conduit.
The Contractor is required to submit a dewatering plan for review by the Engineer. Submit the plan at least 2 weeks prior to beginning the work. The plan shall include details regarding the operation and maintenance of the dewatering elements. The need for redundant power systems, continuous operation and maintenance, and back-up pumping systems shall be addressed.
Dewatering elements shall be designed to provide filtration for surrounding soils and prevent migration of fine soil particles.
The dewatering plan shall provide details regarding the proposed installation and abandonment methods of the individual elements. Installation and abandonment of the elements shall be accomplished without excessive disturbance to surrounding soils. Abandonment of elements shall prevent the possibility that undesirable seepage paths develop after completion of the project.
All installation, operation, and abandonment of dewatering and bypass systems shall be performed in a manner considered acceptable to the Engineer.
Payment for this item shall be made in accordance with Method 1 of Section 7 of this specification.
UT – Tony Grove Reservoir Outlet, December 2021 11-4
(210-VI-NEH, May 2001) 21-1
Construction Specification 21—Excavation
The work shall consist of the excavation required by the drawings and specifications and disposal of the excavated materials.
2. Classification
Excavation is classified as common excavation, rock excavation, or unclassified excavation in accordance with the following definitions.
Common excavation is defined as the excavation of all materials that can be excavated, transported, and unloaded using heavy ripping equipment and wheel tractor-scrapers with pusher tractors or that can be excavated and dumped into place or loaded onto hauling equipment by excavators having a rated capacity of one cubic yard or larger and equipped with attachments (shovel, bucket, backhoe, dragline, or clam shell) appropriate to the material type, character, and nature of the materials.
Rock excavation is defined as the excavation of all hard, compacted, or cemented materials that require blasting or the use of ripping and excavating equipment larger than defined for common excavation. The excavation and removal of isolated boulders or rock fragments larger than 1 cubic yard encountered in materials otherwise conforming to the definition of common excavation shall be classified as rock excavation. The presence of isolated boulders or rock fragments larger than 1 cubic yard is not in itself sufficient cause to change the classification of the surrounding material.
For the purpose of these classifications, the following definitions shall apply:
Heavy ripping equipment is a rear-mounted, heavy duty, single-tooth, ripping attachment mounted on a track type tractor having a power rating of at least 250 flywheel horsepower unless otherwise specified in section 10.
Wheel tractor-scraper is a self-loading (not elevating) and unloading scraper having a struck bowl capacity of at least 12 cubic yards.
Pusher tractor is a track type tractor having a power rating of at least 250 flywheel horsepower equipped with appropriate attachments.
Unclassified excavation is defined as the excavation of all materials encountered, including rock materials,…
This is the start of the file's text. The full file is on GovTribe.