The Department of Energy's Fermi National Accelerator Laboratory (Fermilab) is seeking a subcontractor to replace an end-of-life water-cooled HVAC system located in Proton West 7 (PW7) at their Batavia, Illinois facility. The solicitation requires a qualified contractor to provide full-scope services including purchasing a new 20-ton water-cooled system, removing the existing York E#1922 unit, performing electrical and water line disconnections, installing new components, and completing all necessary startup and testing procedures. The contract opportunity (ID: 7d19fab4951641d18ce501ba8a5c7446) was posted on February 18, 2025, with proposals due by April 4, 2025. Contractors must have expertise in HVAC system replacement, electrical work, and mechanical installations, with specific qualifications in plumbing, heating, and air-conditioning contracting. The evaluation will likely focus on technical capabilities, compliance with detailed scope of work requirements, and ability to complete all specified installation and testing tasks.

The solicitation does not indicate any specific set-aside designations, meaning the opportunity is open to all qualified contractors. The project is classified under NAICS Category 238220 for Plumbing, Heating, and Air-Conditioning Contractors and PSC Category 4120 for Air Conditioning Equipment. While no specific budget range is mentioned, the comprehensive scope suggests a moderate-sized project involving significant equipment replacement and installation. The entire project will be performed at the Fermilab facility in Batavia, Illinois, with an in-house overhead crane technician assisting in equipment positioning. The contractor will be responsible for providing all necessary materials, including a new 20-ton water-cooled system, electrical components, refrigeration valves, copper piping, insulation, and completing all required documentation such as manufacturer start-up paperwork and equipment manuals.

Notice text

This statement of work (SOW) aims to obtain supervision, expertise, labor, materials, and equipment for the work indicated below.

The work will be completed at Proton West 7 (PW7) at the Fermilab facility in Batavia, Illinois. Fermilab is operated by the Fermi Forward Discovery Group (FFDG). FFDG will provide a Task Manager / Construction Coordinator (TM/CC) to oversee the project. 

The subcontractor will replace the existing water-cooled HVAC unit at PW7. The subcontractor will purchase and provide the replacement unit. This is an end-of-life replacement of the HVAC system.

The subcontractor will be responsible for all installation, labor, supervision, equipment, measurements, programming, and testing needed to complete this project before turning it over to FFDG.

SCOPE OF WORK

Subcontractor shall perform the following:

  1. Mobilize to PW7 FIMS 626
  2. The contractor will remove the existing York E#1922 water-cooled cooling-only unit.
    1. LOTO (lock out tag out) electrical panel PHP-WB-2-1 Circ.7-9-11.
    2. Isolate 2” water lines.
    3. Remove existing electrical wiring.  Ensure line voltage and control wiring are removed and disposed of as required.
    4. Disconnect both supply and return water lines.
    5. Disconnect condensate line.
    6. Once the unit is completely disconnected, TM/CC will work with an in-house overhead crane technician to assist with the removal.
  3. The contractor will provide and install a new 20-ton water-cooled system as indicated below.
    1. TM/CC will install a new unit with an in-house overhead crane technician.
    2. The contractor will provide vibration pads for the new unit to sit on.
    3. The contractor will provide a new 2” Penn refrigeration regulator valve.
      1. The contractor will install a 2” Penn valve with a 1/4-inch refrigeration line from the high side of the regulator valve.
      2. The contractor will install a refrigeration tee for service and pressure testing.
    4. The contractor is to supply all 2” copper and materials necessary to connect the supply and return water lines properly.
    5. The contractor will supply and install new insulation on water lines after the leak is checked.
    6. The contractor will install a new electrical 460VAC-3 phased, fused disconnect.
      1. The contractor must supply appropriately sized fuses to match unit MOCP.
      2. The contractor must supply an appropriately sized wire and conduit for the new unit.
      3. The contractor will make the final connections and check the phasing.
  4. The contractor is to install an FFDG-supplied thermostat.
    1. The contractor will install a new 8-wire thermostat wire from the unit to the thermostat.
    2. The contractor is to land low-voltage wiring.
  5. The contractor must supply proper duct supplies (e.g., a Pair of pants) for adequate amperage and airflow.
    1. The TM/CC will provide an in-house overhead crane technician to lift ductwork for final installation.
  6. The contractor is to start up the equipment.
    1. Provide an amp draw on motors to ensure proper ducting.
    2. Adjust the Pen valve to the proper height to ensure an appropriate flow and pressure.
    3. The contractor is to fill out manufacturer start-up paperwork.
  7. Demobilize, final clean up, and check.

The contractor must provide TM/CC with all manuals and a picture of the manufacturer's nameplate

Files

Show all 18

Similar open opportunities

Opportunity Agency Set-aside Responses due
PIP-II f-37 building LWC pump room piping system installation Batavia, Illinois 60510, United States · NAICS 23822 Fermi National Accelerator Laboratory No set-aside
Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB Batavia, Illinois 60510, United States · NAICS 236210 Fermi National Accelerator Laboratory No set-aside
TAN AHU Replacement Idaho 83415, United States Department of Energy No set-aside
E21 prca HVAC replacement NAICS 238220 Bureau of Reclamation Total Small Business
Replace HVAC Rooftop Units at Building 2275 March Air Reserve Base, California 92518, United States · NAICS 238220 Army National Guard No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity