Fermilab LBNF NSCF Construction - Beamline Complex

Closed Pre-Solicitation Posted

Not the latest version. See the latest solicitation from .

Solicitation number
LBNF-BC-350919-BWQ_Pre-Sol
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
23 Construction
Place of performance
Batavia, Illinois 60510, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of Energy Fermi National Accelerator Laboratory is seeking contractors to provide construction services for the Fermilab LBNF NSCF Construction - Beamline Complex project. This project is part of the Long-Baseline Neutrino Facilities (LBNF) Deep Underground Neutrino Experiment (DUNE) and will involve building a new high-intensity neutrino beam at Fermilab aimed at the LBNF Far Site, SURF, 1,300 km away. Key contract requirements include constructing the Pre-Target, Target Complex, Decay Region, and Absorber Complex facilities. The solicitation is expected to be released in May/June 2024, with a proposal due date of April 24, 2024. Interested parties should email Brian Quinn at bquinn@fnal.gov to be added to the list of Offerors.

This contract opportunity is not designated as a set-aside. The NAICS code is likely to be within the construction sector, but the specific code is not provided. No incumbent contractors are named. The total contract value is not specified, but the project aims to enable a world-class program in neutrino physics research.

Notice text

2 versions

Update #2 · Latest ·

The Long-Baseline Neutrino Facility / Deep Underground Neutrino Experiment - U.S.  (LBNF/DUNE-US) Project will provide facilities to enable a world-class program in neutrino physics that can measure fundamental physical parameters, explore physics beyond the Standard Model, and better elucidate the nature of matter and anti-matter. Specifically, the LBNF/DUNE-US Project will build a new high-intensity neutrino beam at Fermilab aimed at the LBNF Far Site, located at South Dakota’s Sanford Underground Research Facility (SURF), 1,300 km away; the associated DUNE subproject will build neutrino detectors at Fermilab and SURF. The experiment will be optimized for precision measurement of neutrino oscillations with the goal of searching for charge parity-violation in the neutrino sector, as well as making other precision oscillation measurements. The Near Site Conventional Facilities (NSCF) provides the new service buildings, underground enclosures, utilities, roads, hardstands, and other conventional facilities features needed for operation of the LBNF Beamline and DUNE Near Detector.

This requirement is for the NSCF Beamline Complex comprising the following elements.

1. Site Work

Site Work includes new utilities and roads, mass earthwork, and other site improvements necessary to accommodate the LBNF Beamline Complex enclosures and buildings.

2. Pre-Target

The Pre-Target includes the facilities necessary to extract a beam of protons (the primary beam) from Fermilab’s Main Injector accelerator and direct it toward the LBNF target on a trajectory toward the Far Detectors. These facilities include:

A. Extraction Enclosure

The Extraction Enclosure is an underground cast-in-place concrete enclosure that intersects and supports the existing Main Injector enclosure and allows the extraction of the LBNF primary beam from the Main Injector.

B. Primary Beam Enclosure

The Primary Beam Enclosure is an underground cast-in-place concrete enclosure that connects the Extraction Enclosure to the Target Hall Complex  and houses the primary beam magnet string. The majority of the Primary Beam Enclosure is founded on deep foundations.

C. Primary Beam Service Building (LBNF-5)

The Primary Beam Service Building is a single-story, at-grade, shallow-founded insulated metal panel building housing power supplies, heat rejection, and other facilities to support the primary beam.

3. Target Complex

The Target Complex is a large, complex, massively-shielded at-grade cast-in-place concrete and insulated metal panel building founded on deep foundations that houses the LBNF target pile where the primary beam interacts with the target to produce the beam of particles that decay into the neutrino beam.

4. Decay Region

The Decay Region includes a 194-meter long, 4-meter diameter, double-walled steel vessel set at a downward slope on a trajectory towards the Far Detector. The beam of particles leaving the Target Complex pass through the Decay Region where a portion decay into neutrinos. The Decay Region vessel is shielded with a minimum thickness of 5.6 meters of concrete and is enclosed in a below-grade concrete structure. The inner steel vessel contains helium and the outer vessel annulus is cooled with gaseous nitrogen supplied from the Target Complex.

5. Absorber Complex

The Absorber Complex is a multi-level structure that includes a service building (LBNF-30) at the surface and a concrete shaft structure housing underground levels for equipment and the Absorber. The Absorber prevents particles other than neutrinos from continuing downstream.

To be put on the list of Offerors to receive an RFP, please email Brian Quinn, bquinn@fnal.gov.

This solicitation is expected to be released in May/June 2024. NO ADDITIONAL INFORMATION WILL BE AVAILABLE UNTIL THE SOLICITATION IS RELEASED.

Update #1 ·

The Long-Baseline Neutrino Facilities (LBNF) Deep Underground Neutrino Experiment (DUNE) Project will provide facilities to enable a world-class program in neutrino physics that can measure fundamental physical parameters, explore physics beyond the Standard Model, and better elucidate the nature of matter and anti-matter. Specifically, the LBNF/DUNE-US Project will build a new high-intensity neutrino beam at Fermilab aimed at the LBNF Far Site, SURF, 1,300 km away; the associated DUNE Project will build neutrino detectors at Fermilab and SURF. The experiment will be optimized for precision measurement of neutrino oscillations with the goal of searching for charge parity-violation in the neutrino sector, as well as making other precision oscillation measurements. The Near Site Conventional Facilities (NSCF) provides the new service buildings, underground enclosures, utilities, roads, hardstands, and other conventional facilities features needed for operation of the LBNF Beamline and DUNE Near Detector.

This requirement is for the NSCF Beamline Complex and is comprised of the following elements.

1. Site Work

Site Work includes new utilities and roads, mass earthwork, and other site improvements necessary to accommodate the LBNF Beamline Complex enclosures and buildings.

2. Pre-Target

The Pre-Target are the facilities necessary to extract a beam of protons (the primary beam) from Fermilab’s Main Injector accelerator and direct it toward the LBNF target on a trajectory toward the Far Detectors. These facilities include:

A. Extraction Enclosure

The Extraction Enclosure is an underground cast-in-place concrete underground enclosure that intersects and supports the existing Main Injector enclosure and allows the extraction of the LBNF primary beam from the Main Injector.

B. Primary Beam Enclosure

The Primary Beam Enclosure is an underground cast-in-place and precast concrete underground enclosure that connects the Extraction Enclosure to the Target Hall Complex  and houses the primary beam magnet string used to direct the primary beam from the Main Injector toward the Target Hall Complex on a trajectory towards the DUNE Far Detector in South Dakota. The majority of the Primary Beam Enclosure is founded on deep foundations.

C. Primary Beam Service Building

The Primary Beam Service Building is a single-story, at-grade, shallow-founded insulated metal panel building housing power supplies, heat rejection, and other facilities to support the primary beam.

3. Target Complex

The Target Complex is a large, complex, massively-shielded at-grade cast-in-place concrete and insulated metal panel building founded on deep foundations that houses the LBNF target pile where the primary beam interacts with the target to produce the beam of particles that decay into the neutrino beam.

4. Decay Region

The Decay Region comprises a 194-meter long, 4-meter diameter, double-walled steel vessel set at a downward slope on a trajectory towards the Far Detector. The beam of particles leaving the Target Hall pass through the Decay Region where a portion decay into neutrinos. The Decay Region vessel is shielded with a minimum thickness of 5.6 meters of concrete and is enclosed in a below-grade concrete structure. The inner steel vessel contains helium and the outer vessel annulus is cooled with gaseous nitrogen supplied from the Target Hall Complex.

5. Absorber Complex

The Absorber Complex is a multi-level structure that includes a service building at the surface and concrete shaft structure housing underground levels for equipment and r the Absorber. The Absorber prevents particles other than neutrinos from continuing downstream.

To be put on the list of Offerors to receive an RFP, please email Brian Quinn, bquinn@fnal.gov.

This solicitation is expected to be released in May/June 2024. NO ADDITIONAL INFORMATION WILL BE AVAILABLE UNTIL THE SOLICITATION IS RELEASED.

Notice history

Notice Type Posted
Fermilab LBNF NSCF Construction - Beamline Complex RFP Latest solicitation Solicitation
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB Batavia, Illinois 60510, United States · NAICS 236210 Fermi National Accelerator Laboratory No set-aside
LBNF/DUNE-US South Dakota Scaffolding Services Lead, South Dakota, United States · NAICS 332323 Fermi National Accelerator Laboratory No set-aside
PIP-II f-37 building LWC pump room piping system installation Batavia, Illinois 60510, United States · NAICS 23822 Fermi National Accelerator Laboratory No set-aside