Excitation Rehabilitation Single Award Task Order Contract (SATOC) for Nashville District Power Plants
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912P519R0001
- Agency
-
ENDIST Nashville
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- Place of performance
- Carthage TN 37030 USA
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers, Nashville District is soliciting proposals for an Excitation Rehabilitation Single Award Task Order Contract to replace excitation equipment at up to eight hydropower generation plants along the Cumberland River in Tennessee. Offerors must propose designs to replace existing excitation systems with new static digital excitation systems at each site. Proposals will be evaluated based on past performance, technical design, safety, small business participation, and price. The deadline for proposals is September 28, 2020. The prototype project involves replacing equipment at the Cordell Hull Power Plant, estimated between $1-5 million.
The solicitation uses NAICS code 237130, Power and Communication Line and Related Structures Construction, with a size standard of $39.5 million. There is no set-aside designation. The SATOC has a maximum value of $30 million over a ten-year period, including a four-year base and three two-year options. The minimum guarantee is $25,000. Key locations for performance include the Cordell Hull Power Plant and up to seven additional hydropower plants along the Cumberland River in Tennessee and Kentucky.
Notice text
8 versions
Update #8 · Latest ·
AMENDMENT 0008 Posted September 21, 2020; included General Wage Decision TN20200142, Modification 1, dated 24 January 2020 primarily for the inclusion of the wage rate for an electrician.
AMENDMENT 0007 Posted September 16, 2020; Published a revised Section 00 41 00; Bid Schedule. Due dates for proposals remains unchanged.
AMENDMENT 0006 Posted September 10, 2020: Published second and final of two amendments for questions and answers. Amends technical specifications, revises Description of Prototype Task Order Price Schedule CLIN 0014, and updates Telecommunications and Video Surveillance Services or Equipment provision 52.204-24 and clause 52.204-25.
AMENDMENT 0005 Posted August 17, 2020: Extended due date for proposals to 10:00 am central time on Monday 28 Sep 2020. Published first of two amendments for questions and answers.
AMENDMENT 0004 Posted July 16, 2020: Extended due date for Questions to 1:00 pm Central Time on Friday, 24 Jul 2020 and Proposals until 10:00 am Central Time on Wednesday, 2 Septemner 2020
AMENDMENT 003 Posted June 18, 2020: Removed the limitation on the number of registered persons attending the virtual site visit - Reference removal of the verbiage "Only two persons from each business entity will be permitted to attend." from Instructions to Offerors, paragraph 1.10, Requirements to Attend the Site Visit
AMENDMENT 002 Posted June 13, 2020: Revised Solicitation to change the Virtual Site Visit Date to 1 July 2020 at 10:00 am central time and the deadline for questions to 8 July 2020 at 1:00 pm central time.
AMENDMENT 001 Posted June 10, 2020: Revised Solicitation to update the Virtual Site Visit Video Conference to 10:00AM central on Tuesday June 16, 2020
PROJECT DESCRIPTION: The Nashville District US Army Corps of Engineers is issuing Request for Proposal (RFP) W912P519R0001 for a firm-fixed price construction contract to improve the efficiency and reliability of excitation equipment located at up to eight (8) of the hydropower generation plants along the Cumberland River by replacing the existing excitation systems with new, fully static, digital excitation systems at up to eight (8) Hydropower Generation Plants. This will be a Full and Open procurement. In accordance with Federal Acquisition Regulation 19.1307, this project will require the HUBZone 10% price evaluation for a competitive acquisition for the award of a Single Award Indefinite Delivery/Indefinite Quantity, Firm-Fixed-Price construction contract. The Government anticipates recurring requirements (i.e., replacement of up to eight (8) excitation systems), but cannot predetermine, above a specified minimum, the precise quantities the Government will require during the contract period. The Single Award Task Order Contract (SATOC) will be awarded in an amount not to exceed $30M with a minimum guarantee of $25,000. The contract will be structured as a base (4 years) and three (3) options (2 years each). If all options are exercised, the total ordering period will be 10 years.
The SATOC will be acquired on an Unrestricted basis with award made to the responsible Offeror whose proposal is fair and reasonable and has been determined the best value to the Government, when past performance, technical, safety, small business and price factors are considered. The basis of award is best value trade-off; therefore, the Government has the right to accept other than the lowest offer. The right is also reserved to reject any and all offers and the Government make award without discussions.
The prototype project, which involves replacing excitation equipment at the Cordell Hull Power Plant located in Carthage, Tennessee, is anticipated to be the first task order awarded and is included in this acquisition for the purpose of evaluating the Offerors’ price reasonableness. The estimated magnitude of the prototype project is between $1,000,000 and $5,000,000.
As set forth in the technical plans and specifications, which are incorporated in the request for proposals, the scope of work requires the contractor to furnish all supervision, engineering, labor, materials, and equipment to perform the following work:
a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver F.O.B. destination three (3) complete static digital excitation systems.
b. Remove three (3) existing excitation systems.
c. Install, test, commission, and make ready for commercial operation three (3) excitation systems including, but not limited to: furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.
d. Conduct equipment model validation tests and prepare test reports suitable for use by SERC Reliability Corporation (SERC).
The scope of work is attached to the solicitation. The intended start date for this project is approximately 60 days after contract award.
NAICS CODE AND SBA SIZE STANDARD: 237130 and $39,500,000.00
TYPE OF SET-ASIDE: None (Full and Open)
ADDITIONAL INFORMATION: It is, and will continue to be, the responsibility of all potential offerors to monitor the Beta.sam.gov Contract Opportunities website for any amendments, updates, responses to industry questions/comments, etc. The Government will not be maintaining a mailing list.
POINT-OF-CONTACT: The Primary Contract Specialist for this solicitation is Rob Holdsworth, email: Robert.B.Holdsworth@usace.army.mil . Secondary Contract Specialist for this solicitation is Stacy Wiggins, email: Stacy.S.Wiggins@usace.army.mil. Any communication regarding this notice should be made in writing sent via email and must identify the Solicitation number, company name, address, email address, phone number including area code, and point of contact.
Place of Contract Performance for the Prototype Project:
Cordell Hull Power Plant
150 Corps Lane
Carthage, TN 37030
United States
VIRTUAL SITE VISIT: Due to the social distancing guidelines put forth by the Centers for Disease Control and Prevention (CDC) because of the COVID-19 situation, one (1) virtual site visit will be held for this project. The site visit will be held virtually via teleconference and is scheduled for 10:00am Central Time on Monday, June 16, 2020. Additional information in regard to the site visit is contained in the solicitation.
Update #7 ·
AMENDMENT 0007 Posted September 16, 2020; Published a revised Section 00 41 00; Bid Schedule. Due dates for proposals remains unchanged.
AMENDMENT 0006 Posted September 10, 2020: Published second and final of two amendments for questions and answers. Amends technical specifications, revises Description of Prototype Task Order Price Schedule CLIN 0014, and updates Telecommunications and Video Surveillance Services or Equipment provision 52.204-24 and clause 52.204-25.
AMENDMENT 0005 Posted August 17, 2020: Extended due date for proposals to 10:00 am central time on Monday 28 Sep 2020. Published first of two amendments for questions and answers.
AMENDMENT 0004 Posted July 16, 2020: Extended due date for Questions to 1:00 pm Central Time on Friday, 24 Jul 2020 and Proposals until 10:00 am Central Time on Wednesday, 2 Septemner 2020
AMENDMENT 003 Posted June 18, 2020: Removed the limitation on the number of registered persons attending the virtual site visit - Reference removal of the verbiage "Only two persons from each business entity will be permitted to attend." from Instructions to Offerors, paragraph 1.10, Requirements to Attend the Site Visit
AMENDMENT 002 Posted June 13, 2020: Revised Solicitation to change the Virtual Site Visit Date to 1 July 2020 at 10:00 am central time and the deadline for questions to 8 July 2020 at 1:00 pm central time.
AMENDMENT 001 Posted June 10, 2020: Revised Solicitation to update the Virtual Site Visit Video Conference to 10:00AM central on Tuesday June 16, 2020
PROJECT DESCRIPTION: The Nashville District US Army Corps of Engineers is issuing Request for Proposal (RFP) W912P519R0001 for a firm-fixed price construction contract to improve the efficiency and reliability of excitation equipment located at up to eight (8) of the hydropower generation plants along the Cumberland River by replacing the existing excitation systems with new, fully static, digital excitation systems at up to eight (8) Hydropower Generation Plants. This will be a Full and Open procurement. In accordance with Federal Acquisition Regulation 19.1307, this project will require the HUBZone 10% price evaluation for a competitive acquisition for the award of a Single Award Indefinite Delivery/Indefinite Quantity, Firm-Fixed-Price construction contract. The Government anticipates recurring requirements (i.e., replacement of up to eight (8) excitation systems), but cannot predetermine, above a specified minimum, the precise quantities the Government will require during the contract period. The Single Award Task Order Contract (SATOC) will be awarded in an amount not to exceed $30M with a minimum guarantee of $25,000. The contract will be structured as a base (4 years) and three (3) options (2 years each). If all options are exercised, the total ordering period will be 10 years.
The SATOC will be acquired on an Unrestricted basis with award made to the responsible Offeror whose proposal is fair and reasonable and has been determined the best value to the Government, when past performance, technical, safety, small business and price factors are considered. The basis of award is best value trade-off; therefore, the Government has the right to accept other than the lowest offer. The right is also reserved to reject any and all offers and the Government make award without discussions.
The prototype project, which involves replacing excitation equipment at the Cordell Hull Power Plant located in Carthage, Tennessee, is anticipated to be the first task order awarded and is included in this acquisition for the purpose of evaluating the Offerors’ price reasonableness. The estimated magnitude of the prototype project is between $1,000,000 and $5,000,000.
As set forth in the technical plans and specifications, which are incorporated in the request for proposals, the scope of work requires the contractor to furnish all supervision, engineering, labor, materials, and equipment to perform the following work:
a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver F.O.B. destination three (3) complete static digital excitation systems.
b. Remove three (3) existing excitation systems.
c. Install, test, commission, and make ready for commercial operation three (3) excitation systems including, but not limited to: furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.
d. Conduct equipment model validation tests and prepare test reports suitable for use by SERC Reliability Corporation (SERC).
The scope of work is attached to the solicitation. The intended start date for this project is approximately 60 days after contract award.
NAICS CODE AND SBA SIZE STANDARD: 237130 and $39,500,000.00
TYPE OF SET-ASIDE: None (Full and Open)
ADDITIONAL INFORMATION: It is, and will continue to be, the responsibility of all potential offerors to monitor the Beta.sam.gov Contract Opportunities website for any amendments, updates, responses to industry questions/comments, etc. The Government will not be maintaining a mailing list.
POINT-OF-CONTACT: The Primary Contract Specialist for this solicitation is Rob Holdsworth, email: Robert.B.Holdsworth@usace.army.mil . Secondary Contract Specialist for this solicitation is Stacy Wiggins, email: Stacy.S.Wiggins@usace.army.mil. Any communication regarding this notice should be made in writing sent via email and must identify the Solicitation number, company name, address, email address, phone number including area code, and point of contact.
Place of Contract Performance for the Prototype Project:
Cordell Hull Power Plant
150 Corps Lane
Carthage, TN 37030
United States
VIRTUAL SITE VISIT: Due to the social distancing guidelines put forth by the Centers for Disease Control and Prevention (CDC) because of the COVID-19 situation, one (1) virtual site visit will be held for this project. The site visit will be held virtually via teleconference and is scheduled for 10:00am Central Time on Monday, June 16, 2020. Additional information in regard to the site visit is contained in the solicitation.
Update #6 ·
AMENDMENT 0006 Posted September 10, 2020: Published second and final of two amendments for questions and answers. Amends technical specifications, revises Description of Prototype Task Order Price Schedule CLIN 0014, and updates Telecommunications and Video Surveillance Services or Equipment provision 52.204-24 and clause 52.204-25.
AMENDMENT 0005 Posted August 17, 2020: Extended due date for proposals to 10:00 am central time on Monday 28 Sep 2020. Published first of two amendments for questions and answers.
AMENDMENT 0004 Posted July 16, 2020: Extended due date for Questions to 1:00 pm Central Time on Friday, 24 Jul 2020 and Proposals until 10:00 am Central Time on Wednesday, 2 Septemner 2020
AMENDMENT 003 Posted June 18, 2020: Removed the limitation on the number of registered persons attending the virtual site visit - Reference removal of the verbiage "Only two persons from each business entity will be permitted to attend." from Instructions to Offerors, paragraph 1.10, Requirements to Attend the Site Visit
AMENDMENT 002 Posted June 13, 2020: Revised Solicitation to change the Virtual Site Visit Date to 1 July 2020 at 10:00 am central time and the deadline for questions to 8 July 2020 at 1:00 pm central time.
AMENDMENT 001 Posted June 10, 2020: Revised Solicitation to update the Virtual Site Visit Video Conference to 10:00AM central on Tuesday June 16, 2020
PROJECT DESCRIPTION: The Nashville District US Army Corps of Engineers is issuing Request for Proposal (RFP) W912P519R0001 for a firm-fixed price construction contract to improve the efficiency and reliability of excitation equipment located at up to eight (8) of the hydropower generation plants along the Cumberland River by replacing the existing excitation systems with new, fully static, digital excitation systems at up to eight (8) Hydropower Generation Plants. This will be a Full and Open procurement. In accordance with Federal Acquisition Regulation 19.1307, this project will require the HUBZone 10% price evaluation for a competitive acquisition for the award of a Single Award Indefinite Delivery/Indefinite Quantity, Firm-Fixed-Price construction contract. The Government anticipates recurring requirements (i.e., replacement of up to eight (8) excitation systems), but cannot predetermine, above a specified minimum, the precise quantities the Government will require during the contract period. The Single Award Task Order Contract (SATOC) will be awarded in an amount not to exceed $30M with a minimum guarantee of $25,000. The contract will be structured as a base (4 years) and three (3) options (2 years each). If all options are exercised, the total ordering period will be 10 years.
The SATOC will be acquired on an Unrestricted basis with award made to the responsible Offeror whose proposal is fair and reasonable and has been determined the best value to the Government, when past performance, technical, safety, small business and price factors are considered. The basis of award is best value trade-off; therefore, the Government has the right to accept other than the lowest offer. The right is also reserved to reject any and all offers and the Government make award without discussions.
The prototype project, which involves replacing excitation equipment at the Cordell Hull Power Plant located in Carthage, Tennessee, is anticipated to be the first task order awarded and is included in this acquisition for the purpose of evaluating the Offerors’ price reasonableness. The estimated magnitude of the prototype project is between $1,000,000 and $5,000,000.
As set forth in the technical plans and specifications, which are incorporated in the request for proposals, the scope of work requires the contractor to furnish all supervision, engineering, labor, materials, and equipment to perform the following work:
a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver F.O.B. destination three (3) complete static digital excitation systems.
b. Remove three (3) existing excitation systems.
c. Install, test, commission, and make ready for commercial operation three (3) excitation systems including, but not limited to: furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.
d. Conduct equipment model validation tests and prepare test reports suitable for use by SERC Reliability Corporation (SERC).
The scope of work is attached to the solicitation. The intended start date for this project is approximately 60 days after contract award.
NAICS CODE AND SBA SIZE STANDARD: 237130 and $39,500,000.00
TYPE OF SET-ASIDE: None (Full and Open)
ADDITIONAL INFORMATION: It is, and will continue to be, the responsibility of all potential offerors to monitor the Beta.sam.gov Contract Opportunities website for any amendments, updates, responses to industry questions/comments, etc. The Government will not be maintaining a mailing list.
POINT-OF-CONTACT: The Primary Contract Specialist for this solicitation is Rob Holdsworth, email: Robert.B.Holdsworth@usace.army.mil . Secondary Contract Specialist for this solicitation is Stacy Wiggins, email: Stacy.S.Wiggins@usace.army.mil. Any communication regarding this notice should be made in writing sent via email and must identify the Solicitation number, company name, address, email address, phone number including area code, and point of contact.
Place of Contract Performance for the Prototype Project:
Cordell Hull Power Plant
150 Corps Lane
Carthage, TN 37030
United States
VIRTUAL SITE VISIT: Due to the social distancing guidelines put forth by the Centers for Disease Control and Prevention (CDC) because of the COVID-19 situation, one (1) virtual site visit will be held for this project. The site visit will be held virtually via teleconference and is scheduled for 10:00am Central Time on Monday, June 16, 2020. Additional information in regard to the site visit is contained in the solicitation.
Update #5 ·
AMENDMENT 0005 Posted August 17, 2020: Extended due date for proposals to 10:00 am central time on Monday 28 Sep 2020. Published first of two amendments for questions and answers.
AMENDMENT 0004 Posted July 16, 2020: Extended due date for Questions to 1:00 pm Central Time on Friday, 24 Jul 2020 and Proposals until 10:00 am Central Time on Wednesday, 2 Septemner 2020
AMENDMENT 003 Posted June 18, 2020: Removed the limitation on the number of registered persons attending the virtual site visit - Reference removal of the verbiage "Only two persons from each business entity will be permitted to attend." from Instructions to Offerors, paragraph 1.10, Requirements to Attend the Site Visit
AMENDMENT 002 Posted June 13, 2020: Revised Solicitation to change the Virtual Site Visit Date to 1 July 2020 at 10:00 am central time and the deadline for questions to 8 July 2020 at 1:00 pm central time.
AMENDMENT 001 Posted June 10, 2020: Revised Solicitation to update the Virtual Site Visit Video Conference to 10:00AM central on Tuesday June 16, 2020
PROJECT DESCRIPTION: The Nashville District US Army Corps of Engineers is issuing Request for Proposal (RFP) W912P519R0001 for a firm-fixed price construction contract to improve the efficiency and reliability of excitation equipment located at up to eight (8) of the hydropower generation plants along the Cumberland River by replacing the existing excitation systems with new, fully static, digital excitation systems at up to eight (8) Hydropower Generation Plants. This will be a Full and Open procurement. In accordance with Federal Acquisition Regulation 19.1307, this project will require the HUBZone 10% price evaluation for a competitive acquisition for the award of a Single Award Indefinite Delivery/Indefinite Quantity, Firm-Fixed-Price construction contract. The Government anticipates recurring requirements (i.e., replacement of up to eight (8) excitation systems), but cannot predetermine, above a specified minimum, the precise quantities the Government will require during the contract period. The Single Award Task Order Contract (SATOC) will be awarded in an amount not to exceed $30M with a minimum guarantee of $25,000. The contract will be structured as a base (4 years) and three (3) options (2 years each). If all options are exercised, the total ordering period will be 10 years.
The SATOC will be acquired on an Unrestricted basis with award made to the responsible Offeror whose proposal is fair and reasonable and has been determined the best value to the Government, when past performance, technical, safety, small business and price factors are considered. The basis of award is best value trade-off; therefore, the Government has the right to accept other than the lowest offer. The right is also reserved to reject any and all offers and the Government make award without discussions.
The prototype project, which involves replacing excitation equipment at the Cordell Hull Power Plant located in Carthage, Tennessee, is anticipated to be the first task order awarded and is included in this acquisition for the purpose of evaluating the Offerors’ price reasonableness. The estimated magnitude of the prototype project is between $1,000,000 and $5,000,000.
As set forth in the technical plans and specifications, which are incorporated in the request for proposals, the scope of work requires the contractor to furnish all supervision, engineering, labor, materials, and equipment to perform the following work:
a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver F.O.B. destination three (3) complete static digital excitation systems.
b. Remove three (3) existing excitation systems.
c. Install, test, commission, and make ready for commercial operation three (3) excitation systems including, but not limited to: furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.
d. Conduct equipment model validation tests and prepare test reports suitable for use by SERC Reliability Corporation (SERC).
The scope of work is attached to the solicitation. The intended start date for this project is approximately 60 days after contract award.
NAICS CODE AND SBA SIZE STANDARD: 237130 and $39,500,000.00
TYPE OF SET-ASIDE: None (Full and Open)
ADDITIONAL INFORMATION: It is, and will continue to be, the responsibility of all potential offerors to monitor the Beta.sam.gov Contract Opportunities website for any amendments, updates, responses to industry questions/comments, etc. The Government will not be maintaining a mailing list.
POINT-OF-CONTACT: The Primary Contract Specialist for this solicitation is Rob Holdsworth, email: Robert.B.Holdsworth@usace.army.mil . Secondary Contract Specialist for this solicitation is Stacy Wiggins, email: Stacy.S.Wiggins@usace.army.mil. Any communication regarding this notice should be made in writing sent via email and must identify the Solicitation number, company name, address, email address, phone number including area code, and point of contact.
Place of Contract Performance for the Prototype Project:
Cordell Hull Power Plant
150 Corps Lane
Carthage, TN 37030
United States
VIRTUAL SITE VISIT: Due to the social distancing guidelines put forth by the Centers for Disease Control and Prevention (CDC) because of the COVID-19 situation, one (1) virtual site visit will be held for this project. The site visit will be held virtually via teleconference and is scheduled for 10:00am Central Time on Monday, June 16, 2020. Additional information in regard to the site visit is contained in the solicitation.
Update #4 ·
AMENDMENT 0004 Posted July 16, 2020: Extended due date for Questions to 1:00 pm Central Time on Friday, 24 Jul 2020 and Proposals until 10:00 am Central Time on Wednesday, 2 Septemner 2020
AMENDMENT 003 Posted June 18, 2020: Removed the limitation on the number of registered persons attending the virtual site visit - Reference removal of the verbiage "Only two persons from each business entity will be permitted to attend." from Instructions to Offerors, paragraph 1.10, Requirements to Attend the Site Visit
AMENDMENT 002 Posted June 13, 2020: Revised Solicitation to change the Virtual Site Visit Date to 1 July 2020 at 10:00 am central time and the deadline for questions to 8 July 2020 at 1:00 pm central time.
AMENDMENT 001 Posted June 10, 2020: Revised Solicitation to update the Virtual Site Visit Video Conference to 10:00AM central on Tuesday June 16, 2020
PROJECT DESCRIPTION: The Nashville District US Army Corps of Engineers is issuing Request for Proposal (RFP) W912P519R0001 for a firm-fixed price construction contract to improve the efficiency and reliability of excitation equipment located at up to eight (8) of the hydropower generation plants along the Cumberland River by replacing the existing excitation systems with new, fully static, digital excitation systems at up to eight (8) Hydropower Generation Plants. This will be a Full and Open procurement. In accordance with Federal Acquisition Regulation 19.1307, this project will require the HUBZone 10% price evaluation for a competitive acquisition for the award of a Single Award Indefinite Delivery/Indefinite Quantity, Firm-Fixed-Price construction contract. The Government anticipates recurring requirements (i.e., replacement of up to eight (8) excitation systems), but cannot predetermine, above a specified minimum, the precise quantities the Government will require during the contract period. The Single Award Task Order Contract (SATOC) will be awarded in an amount not to exceed $30M with a minimum guarantee of $25,000. The contract will be structured as a base (4 years) and three (3) options (2 years each). If all options are exercised, the total ordering period will be 10 years.
The SATOC will be acquired on an Unrestricted basis with award made to the responsible Offeror whose proposal is fair and reasonable and has been determined the best value to the Government, when past performance, technical, safety, small business and price factors are considered. The basis of award is best value trade-off; therefore, the Government has the right to accept other than the lowest offer. The right is also reserved to reject any and all offers and the Government make award without discussions.
The prototype project, which involves replacing excitation equipment at the Cordell Hull Power Plant located in Carthage, Tennessee, is anticipated to be the first task order awarded and is included in this acquisition for the purpose of evaluating the Offerors’ price reasonableness. The estimated magnitude of the prototype project is between $1,000,000 and $5,000,000.
As set forth in the technical plans and specifications, which are incorporated in the request for proposals, the scope of work requires the contractor to furnish all supervision, engineering, labor, materials, and equipment to perform the following work:
a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver F.O.B. destination three (3) complete static digital excitation systems.
b. Remove three (3) existing excitation systems.
c. Install, test, commission, and make ready for commercial operation three (3) excitation systems including, but not limited to: furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.
d. Conduct equipment model validation tests and prepare test reports suitable for use by SERC Reliability Corporation (SERC).
The scope of work is attached to the solicitation. The intended start date for this project is approximately 60 days after contract award.
NAICS CODE AND SBA SIZE STANDARD: 237130 and $39,500,000.00
TYPE OF SET-ASIDE: None (Full and Open)
ADDITIONAL INFORMATION: It is, and will continue to be, the responsibility of all potential offerors to monitor the Beta.sam.gov Contract Opportunities website for any amendments, updates, responses to industry questions/comments, etc. The Government will not be maintaining a mailing list.
POINT-OF-CONTACT: The Primary Contract Specialist for this solicitation is Rob Holdsworth, email: Robert.B.Holdsworth@usace.army.mil . Secondary Contract Specialist for this solicitation is Stacy Wiggins, email: Stacy.S.Wiggins@usace.army.mil. Any communication regarding this notice should be made in writing sent via email and must identify the Solicitation number, company name, address, email address, phone number including area code, and point of contact.
Place of Contract Performance for the Prototype Project:
Cordell Hull Power Plant
150 Corps Lane
Carthage, TN 37030
United States
VIRTUAL SITE VISIT: Due to the social distancing guidelines put forth by the Centers for Disease Control and Prevention (CDC) because of the COVID-19 situation, one (1) virtual site visit will be held for this project. The site visit will be held virtually via teleconference and is scheduled for 10:00am Central Time on Monday, June 16, 2020. Additional information in regard to the site visit is contained in the solicitation.
Update #3 ·
AMENDMENT 002 Posted June 13, 2020: Revised Solicitation to change the Virtual Site Visit Date to 1 July 2020 at 10:00 am central time and the deadline for questions to 8 July 2020 at 1:00 pm central time.
AMENDMENT 001 Posted June 10, 2020: Revised Solicitation to update the Virtual Site Visit Video Conference to 10:00AM central on Tuesday June 16, 2020
PROJECT DESCRIPTION: The Nashville District US Army Corps of Engineers is issuing Request for Proposal (RFP) W912P519R0001 for a firm-fixed price construction contract to improve the efficiency and reliability of excitation equipment located at up to eight (8) of the hydropower generation plants along the Cumberland River by replacing the existing excitation systems with new, fully static, digital excitation systems at up to eight (8) Hydropower Generation Plants. This will be a Full and Open procurement. In accordance with Federal Acquisition Regulation 19.1307, this project will require the HUBZone 10% price evaluation for a competitive acquisition for the award of a Single Award Indefinite Delivery/Indefinite Quantity, Firm-Fixed-Price construction contract. The Government anticipates recurring requirements (i.e., replacement of up to eight (8) excitation systems), but cannot predetermine, above a specified minimum, the precise quantities the Government will require during the contract period. The Single Award Task Order Contract (SATOC) will be awarded in an amount not to exceed $30M with a minimum guarantee of $25,000. The contract will be structured as a base (4 years) and three (3) options (2 years each). If all options are exercised, the total ordering period will be 10 years.
The SATOC will be acquired on an Unrestricted basis with award made to the responsible Offeror whose proposal is fair and reasonable and has been determined the best value to the Government, when past performance, technical, safety, small business and price factors are considered. The basis of award is best value trade-off; therefore, the Government has the right to accept other than the lowest offer. The right is also reserved to reject any and all offers and the Government make award without discussions.
The prototype project, which involves replacing excitation equipment at the Cordell Hull Power Plant located in Carthage, Tennessee, is anticipated to be the first task order awarded and is included in this acquisition for the purpose of evaluating the Offerors’ price reasonableness. The estimated magnitude of the prototype project is between $1,000,000 and $5,000,000.
As set forth in the technical plans and specifications, which are incorporated in the request for proposals, the scope of work requires the contractor to furnish all supervision, engineering, labor, materials, and equipment to perform the following work:
a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver F.O.B. destination three (3) complete static digital excitation systems.
b. Remove three (3) existing excitation systems.
c. Install, test, commission, and make ready for commercial operation three (3) excitation systems including, but not limited to: furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.
d. Conduct equipment model validation tests and prepare test reports suitable for use by SERC Reliability Corporation (SERC).
The scope of work is attached to the solicitation. The intended start date for this project is approximately 60 days after contract award.
NAICS CODE AND SBA SIZE STANDARD: 237130 and $39,500,000.00
TYPE OF SET-ASIDE: None (Full and Open)
ADDITIONAL INFORMATION: It is, and will continue to be, the responsibility of all potential offerors to monitor the Beta.sam.gov Contract Opportunities website for any amendments, updates, responses to industry questions/comments, etc. The Government will not be maintaining a mailing list.
POINT-OF-CONTACT: The Primary Contract Specialist for this solicitation is Rob Holdsworth, email: Robert.B.Holdsworth@usace.army.mil . Secondary Contract Specialist for this solicitation is Stacy Wiggins, email: Stacy.S.Wiggins@usace.army.mil. Any communication regarding this notice should be made in writing sent via email and must identify the Solicitation number, company name, address, email address, phone number including area code, and point of contact.
Place of Contract Performance for the Prototype Project:
Cordell Hull Power Plant
150 Corps Lane
Carthage, TN 37030
United States
VIRTUAL SITE VISIT: Due to the social distancing guidelines put forth by the Centers for Disease Control and Prevention (CDC) because of the COVID-19 situation, one (1) virtual site visit will be held for this project. The site visit will be held virtually via teleconference and is scheduled for 10:00am Central Time on Monday, June 16, 2020. Additional information in regard to the site visit is contained in the solicitation.
Update #2 ·
AMENDMENT 001 Posted June 10, 2020: Revised Solicitation to update the Virtual Site Visit Video Conference to 10:00AM central on Tuesday June 16, 2020
PROJECT DESCRIPTION: The Nashville District US Army Corps of Engineers is issuing Request for Proposal (RFP) W912P519R0001 for a firm-fixed price construction contract to improve the efficiency and reliability of excitation equipment located at up to eight (8) of the hydropower generation plants along the Cumberland River by replacing the existing excitation systems with new, fully static, digital excitation systems at up to eight (8) Hydropower Generation Plants. This will be a Full and Open procurement. In accordance with Federal Acquisition Regulation 19.1307, this project will require the HUBZone 10% price evaluation for a competitive acquisition for the award of a Single Award Indefinite Delivery/Indefinite Quantity, Firm-Fixed-Price construction contract. The Government anticipates recurring requirements (i.e., replacement of up to eight (8) excitation systems), but cannot predetermine, above a specified minimum, the precise quantities the Government will require during the contract period. The Single Award Task Order Contract (SATOC) will be awarded in an amount not to exceed $30M with a minimum guarantee of $25,000. The contract will be structured as a base (4 years) and three (3) options (2 years each). If all options are exercised, the total ordering period will be 10 years.
The SATOC will be acquired on an Unrestricted basis with award made to the responsible Offeror whose proposal is fair and reasonable and has been determined the best value to the Government, when past performance, technical, safety, small business and price factors are considered. The basis of award is best value trade-off; therefore, the Government has the right to accept other than the lowest offer. The right is also reserved to reject any and all offers and the Government make award without discussions.
The prototype project, which involves replacing excitation equipment at the Cordell Hull Power Plant located in Carthage, Tennessee, is anticipated to be the first task order awarded and is included in this acquisition for the purpose of evaluating the Offerors’ price reasonableness. The estimated magnitude of the prototype project is between $1,000,000 and $5,000,000.
As set forth in the technical plans and specifications, which are incorporated in the request for proposals, the scope of work requires the contractor to furnish all supervision, engineering, labor, materials, and equipment to perform the following work:
a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver F.O.B. destination three (3) complete static digital excitation systems.
b. Remove three (3) existing excitation systems.
c. Install, test, commission, and make ready for commercial operation three (3) excitation systems including, but not limited to: furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.
d. Conduct equipment model validation tests and prepare test reports suitable for use by SERC Reliability Corporation (SERC).
The scope of work is attached to the solicitation. The intended start date for this project is approximately 60 days after contract award.
NAICS CODE AND SBA SIZE STANDARD: 237130 and $39,500,000.00
TYPE OF SET-ASIDE: None (Full and Open)
ADDITIONAL INFORMATION: It is, and will continue to be, the responsibility of all potential offerors to monitor the Beta.sam.gov Contract Opportunities website for any amendments, updates, responses to industry questions/comments, etc. The Government will not be maintaining a mailing list.
POINT-OF-CONTACT: The Primary Contract Specialist for this solicitation is Rob Holdsworth, email: Robert.B.Holdsworth@usace.army.mil . Secondary Contract Specialist for this solicitation is Stacy Wiggins, email: Stacy.S.Wiggins@usace.army.mil. Any communication regarding this notice should be made in writing sent via email and must identify the Solicitation number, company name, address, email address, phone number including area code, and point of contact.
Place of Contract Performance for the Prototype Project:
Cordell Hull Power Plant
150 Corps Lane
Carthage, TN 37030
United States
VIRTUAL SITE VISIT: Due to the social distancing guidelines put forth by the Centers for Disease Control and Prevention (CDC) because of the COVID-19 situation, one (1) virtual site visit will be held for this project. The site visit will be held virtually via teleconference and is scheduled for 10:00am Central Time on Monday, June 16, 2020. Additional information in regard to the site visit is contained in the solicitation.
Update #1 ·
PROJECT DESCRIPTION: The Nashville District US Army Corps of Engineers is issuing Request for Proposal (RFP) W912P519R0001 for a firm-fixed price construction contract to improve the efficiency and reliability of excitation equipment located at up to eight (8) of the hydropower generation plants along the Cumberland River by replacing the existing excitation systems with new, fully static, digital excitation systems at up to eight (8) Hydropower Generation Plants. This will be a Full and Open procurement. In accordance with Federal Acquisition Regulation 19.1307, this project will require the HUBZone 10% price evaluation for a competitive acquisition for the award of a Single Award Indefinite Delivery/Indefinite Quantity, Firm-Fixed-Price construction contract. The Government anticipates recurring requirements (i.e., replacement of up to eight (8) excitation systems), but cannot predetermine, above a specified minimum, the precise quantities the Government will require during the contract period. The Single Award Task Order Contract (SATOC) will be awarded in an amount not to exceed $30M with a minimum guarantee of $25,000. The contract will be structured as a base (4 years) and three (3) options (2 years each). If all options are exercised, the total ordering period will be 10 years.
The SATOC will be acquired on an Unrestricted basis with award made to the responsible Offeror whose proposal is fair and reasonable and has been determined the best value to the Government, when past performance, technical, safety, small business and price factors are considered. The basis of award is best value trade-off; therefore, the Government has the right to accept other than the lowest offer. The right is also reserved to reject any and all offers and the Government make award without discussions.
The prototype project, which involves replacing excitation equipment at the Cordell Hull Power Plant located in Carthage, Tennessee, is anticipated to be the first task order awarded and is included in this acquisition for the purpose of evaluating the Offerors’ price reasonableness. The estimated magnitude of the prototype project is between $1,000,000 and $5,000,000.
As set forth in the technical plans and specifications, which are incorporated in the request for proposals, the scope of work requires the contractor to furnish all supervision, engineering, labor, materials, and equipment to perform the following work:
a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver F.O.B. destination three (3) complete static digital excitation systems.
b. Remove three (3) existing excitation systems.
c. Install, test, commission, and make ready for commercial operation three (3) excitation systems including, but not limited to: furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.
d. Conduct equipment model validation tests and prepare test reports suitable for use by SERC Reliability Corporation (SERC).
The scope of work is attached to the solicitation. The intended start date for this project is approximately 60 days after contract award.
NAICS CODE AND SBA SIZE STANDARD: 237130 and $39,500,000.00
TYPE OF SET-ASIDE: None (Full and Open)
ADDITIONAL INFORMATION: It is, and will continue to be, the responsibility of all potential offerors to monitor the Beta.sam.gov Contract Opportunities website for any amendments, updates, responses to industry questions/comments, etc. The Government will not be maintaining a mailing list.
POINT-OF-CONTACT: The Primary Contract Specialist for this solicitation is Rob Holdsworth, email: Robert.B.Holdsworth@usace.army.mil . Secondary Contract Specialist for this solicitation is Stacy Wiggins, email: Stacy.S.Wiggins@usace.army.mil. Any communication regarding this notice should be made in writing sent via email and must identify the Solicitation number, company name, address, email address, phone number including area code, and point of contact.
Place of Contract Performance for the Prototype Project:
Cordell Hull Power Plant
150 Corps Lane
Carthage, TN 37030
United States
VIRTUAL SITE VISIT: Due to the social distancing guidelines put forth by the Centers for Disease Control and Prevention (CDC) because of the COVID-19 situation, one (1) virtual site visit will be held for this project. The site visit will be held virtually via teleconference and is scheduled for 10:00am Central Time on Monday, June 16, 2020. Additional information in regard to the site visit is contained in the solicitation.
Files
Show all 23
Notice history
| Notice | Type | Posted |
|---|---|---|
| Excitation Rehabilitation Single Award Task Order Contract (SATOC) for Nashville District Power Plants | Award Notice | |
| This notice | Solicitation | |
| Excitation Rehabilitatio, Cordell Hull | Pre-Solicitation | |
| Excitation Rehabilitatio, Cordell Hull | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Tenkiller Hydropower Excitation System Replacement | ENDIST Tulsa | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity