W912P519R0001 TSPECS RTA.pdf
PDF 4 MB Posted
- Attached to
- Excitation Rehabilitation Single Award Task Order Contract (SATOC) for Nashville District Power Plants
- Solicitation number
- W912P519R0001
About this file
This is a solicitation for a Single Award Task Order Contract (SATOC) to replace excitation equipment at up to eight hydropower generation plants along the Cumberland River. The Nashville District US Army Corps of Engineers seeks a firm-fixed price construction contract not to exceed $30 million over a potential 10-year period. The minimum guarantee is $25,000.
The scope of work includes designing, manufacturing, installing, testing and commissioning new digital excitation systems to replace existing equipment at the sites. The first task order will serve as a prototype project to replace excitation equipment at the Cordell Hull Power Plant in Carthage, Tennessee, with an estimated value between $1-5 million. The contractor must conduct equipment validation tests and submit reports. The acquisition is unrestricted and will be awarded based on best value considering past performance, technical, safety, small business and price factors. The prototype performance period begins approximately 60 days after contract award.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation # W912P519R0001
US Army Corps Of Engineers Nashville District
Excitation Replacement
Cordell Hull Power Plant Smith County, Tennessee
Technical Specifications RTA-Certified Final
January 2019
THIS PAGE INTENTIONALLY LEFT BLANK
FOR DUPLEX PRINTING
Excitation Replacement Cordell Hull W912P519R0001 Smith County, TN
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 11 10 STATEMENT OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES
01 35 70 CYBERSECURITY
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 95 00 FORMS AND ATTACHMENTS
DIVISION 02 - EXISTING CONDITIONS
02 82 13 ASBESTOS ABATEMENT
02 83 19 LEAD-BASED PAINT ABATEMENT
02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)
DIVISION 03 - CONCRETE
03 60 00 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND
MINOR EQUIPMENT FOUNDATIONS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 00 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT
DIVISION 26 - ELECTRICAL
26 05 00 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 13 MEDIUM-VOLTAGE CABLE
26 05 19 INSULATED WIRE AND CABLE
26 05 26 GROUNDING
26 25 00 BUS STRUCTURES
DIVISION 48 - ELECTRICAL POWER GENERATION
48 19 26 DIGITAL EXCITERS
48 70 01 NERC COMPLIANCE FOR HYDROGENERATORS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
1.2 LOCATION AND ACCESS
1.2.1 Location
1.2.2 Access to Site
1.3 COORDINATION CONFERENCES
1.4 PARTNERING
1.5 REFERENCES
1.6 SUBMITTALS
1.7 PROJECT SIGNS
1.7.1 General
1.7.2 Materials
1.7.3 Painting
1.7.4 Erection and Maintenance
1.8 CONTRACTOR'S STAGING AREA
1.9 DAILY CLEANUP AND DISPOSAL
1.10 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.11 EVALUATION OF CONTRACTOR PERFORMANCE
1.12 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.13 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Contractor Responsibilities
3.1.2 Interruptions of Utilities
-- End of Section Table of Contents --
SECTION 01 00 00 Page 1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
This section comprises an explanation of the general contract requirements needed to accomplish the work. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and drawings.
1.2 LOCATION AND ACCESS
1.2.1 Location
Cordell Hull Dam is located at river mile 313.50 on the Cumberland River in Carthage, Tennessee. The Cordell Hull Project is comprised of, from southwest to northeast, a southwestern Navigation Lock, 5 Spillway Gates, a Powerhouse, and an northeastern Embankment
1.2.2 Access to Site
Cordell Hull Project maintenance personnel must be on site at all times during the Contractor's work. Project personnel currently work Monday through Thursday, 10 hour day shifts 6:30 A.M. to 5:00 P.M. Contractor work will not be allowed on Federal Holidays.
1.3 COORDINATION CONFERENCES
Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this project. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to this construction. The Corps of Engineers and the Contractor will be represented at each of these meetings. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.
1.4 PARTNERING
In order to most effectively accomplish this contract, the Government urges the contractor to join the Government in establishing a cohesive and professional project management team. Through this "partnering" relationship both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project’s intended results are achieved, within budget and on schedule. This endeavor seeks an environment that nurtures team building, cooperation and trust between the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.
The first step in initiating the concept would be a joint project management team "partnering" conference attended by multiple officers from each organization representing management and the key jobsite staff of each
SECTION 01 00 00 Page 2 entity. The initial conference would be held within the first thirty (30) days following contract award. The Resident Engineer would chair the conference, establish its agenda and distribute minutes of the meeting. A professional facilitator acceptable to both parties would lead the participants of the session, through the steps of team building and the formation of a problem solving mechanism within the group. The conference duration would be no more than one day. Location of the conference would be offsite within a 60 mile radius of the jobsite at a facility which offers conference rooms and food service. All costs in connection with rented facilities and the facilitator would be shared equally by the Government and the Contractor. Each organization would pay other costs of its respective employees attending the conference.
Additional partnering sessions would be held no less than biannually.
Implementation of the partnering concept and philosophy would be an on-going process.
1.5 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 310-1-6a (2006) Sign Standards Manual, VOL 1
EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices
1.6 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
1.7 PROJECT SIGNS
1.7.1 General
Furnish and erect, within 15 days after issuance of the Notice to Proceed, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN at the location directed by the Contracting Officer. Letter signs on one side only and conform to EP 310-1-6a (Section 16), EP 310-1-6b, and to the details and colors shown on the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. Name the project as follows:
Cordell Hull Excitation System Replacement
1.7.2 Materials
Construct the sign with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material.
Screws shall be commercial quality and of sizes shown.
SECTION 01 00 00 Page 3
1.7.3 Painting
Apply one prime coat and two finish coats of exterior oil paint to signs and post before lettering. Apply letters and trim to one side only using one coat of enamel of color, style, and size shown.
1.7.4 Erection and Maintenance
Erect signs at the locations designated by the Contracting Officer. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs throughout the life of the contract. Maintain signs in good condition until completion of the contract. Remove signs from the site upon final acceptance of the contract work.
1.8 CONTRACTOR'S STAGING AREA
The Contractor will be assigned an area within or near the project site for use as a staging area. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner. Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.
1.9 DAILY CLEANUP AND DISPOSAL
Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.
1.10 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.
1.11 EVALUATION OF CONTRACTOR PERFORMANCE
The Contractor's performance will be evaluated in accordance with FAR Part
42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum. The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section
01 95 00 FORMS AND ATTACHMENTS.
The Contractor's review of the evaluation shall be completed electronically at the CPARS, http://www.cpars.gov. This website also includes guidance and the user's manual.
Upon contract award, the Contractor shall provide the Contracting Officer
SECTION 01 00 00 Page 4 with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.
1.12 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
a. U.S. Department of Labor Veterans employment: www.vets.gov/
b. Federal veteran employment information: www.fedshirevets.gov/index.aspx
c. Veterans’ Employment and Training Service (VETS):
http://www.dol.gov/vets/
d. Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/
e. U.S. Army Warrior Transition Command Employment Index:
http://www.wct.army.mil/modules/employers/index.html
f. Hiring Our Heroes initiative:
www.uschamberfoundation.org/hiring-our-heroes
g. Guide to Hiring Veterans:
www.whitehouse.gov/sites/default/files/docs/white_house_business_council_ -_guide_to_hiring_veterans_0.pdf
1.13 MEASUREMENT AND PAYMENT
No separate payment will be made for the work covered under this section.
The costs thereof shall be included in the item to which the work pertains.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Contractor Responsibilities
a. The Contractor shall be responsible for the availability of utilities for use on the project. Raw water is available with no charge at the site. The contractor shall supply any other utilities needed at his cost. The Contractor shall carefully conserve any utilities furnished without charge.
b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final
SECTION 01 00 00 Page 5 acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.
c. The Contractor is responsible for providing drinking water facilities for all personnel associated with this contract.
3.1.2 Interruptions of Utilities
a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.
b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) days prior to date of proposed interruption. The request shall give the following information:
(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)
(2) Size of line and location of shutoff.
(3) Buildings and services affected.
(4) Hours and date of shutoff.
(5) Estimated length of time services will be interrupted.
c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.
d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency.
e. Operation of valves on water mains will be by Government personnel.
Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event of emergency.
-- End of Section --
SECTION 01 00 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 10
STATEMENT OF WORK
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
1.2 SPECIFICATIONS
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 11 10 Page 1
SECTION 01 11 10
STATEMENT OF WORK
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
The scope of work for this contract consists of the Contractor furnishing all supervision, engineering, labor, materials, and equipment to perform the following work in strict accordance with the detailed requirements of these specifications:
a. Design, prepare drawings and data, manufacture, shop test, prepare and load for shipment, and deliver f.o.b. destination three complete digital static excitation systems for the Cordell Hull Power Plant.
b. Remove three existing excitation systems, to include all existing cabinets, Amplidyne motor-generator sets, and associated equipment as specified.
c. Install, test, commission, and make ready for commercial operation three excitation systems at Cordell Hull Power Plant, including floor repair as well as furnishing and installing wire, cable, bus, conduit, meters, switches, and all other required appurtenances.
d. Perform collector ring inspection and brush and brush holder replacement.
e. Perform optional collector ring refurbishment, if approved by Government.
f. Conduct equipment model validation tests and prepare test report suitable for use by SERC.
1.2 SPECIFICATIONS
Technical specifications listed below cover the detailed requirements for the equipment and services listed in the Bid Schedule:
SECTION TITLE
01 35 70 CYBERSECURITY
03 60 00.01 26 CONCRETE DEMOLITION AND REPAIR OF CONCRETE SURFACES
13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT
26 05 00.00 26 GENERAL ELECTRICAL WORK
26 05 13.00 26 MEDIUM-VOLTAGE CABLE
26 05 19.00 26 INSULATED WIRE AND CABLE
26 05 26.00 26 GROUNDING
26 25 00.00 26 BUS STRUCTURES
48 19 26.00 26 DIGITAL EXCITERS
48 70 01.00 26 NERC COMPLIANCE FOR HYDROGENERATORS
SECTION 01 11 10 Page 2
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 11 10 Page 3
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 MEASUREMENT
1.3 PAYMENT
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
In each instance, the contract price for a contract line item number (CLIN) will constitute full compensation as herein specified, as shown, or as otherwise approved. The contract price and payment will also constitute full compensation for all work incidental to completion of the CLIN, unless such work is otherwise specifically mentioned for separate payment under another CLIN. In the event any work is required by the specification sections or by the drawings and not specifically mentioned in the measurement and payment paragraphs separate or direct payment will not be made. All costs are therefore incidental to, and included in, the contract prices and payment for all CLINs listed in the price schedule.
1.2 MEASUREMENT
CLINs measured as a job will be measured for payment as a complete job in the locations indicated. This measurement includes all incidental work and materials such as fasteners, electrical materials, and O&M manuals that are necessary to make a complete job. Unless the CLIN paragraph makes a specific exception of any item, incidental items will not be measured under any other CLIN, even though there is another listing for the work or material.
1.3 PAYMENT
Payment for all work specified, shown, or incidental to complete the work will be made as follows:
CLIN 0001 Design, manufacture, test and deliver excitation systems and appurtenances (SECTION 48 19 26)
Payment will be made on a per unit basis under CLIN 0001. Payment shall be made for all materials, labor, equipment, and facilities needed to design, manufacture, test, submit design documents and deliver the excitation systems in accordance with specification section 48 19 26.
CLIN 0002 Disassemble and remove existing excitation systems (SECTION 48 19 26)
Payment will be made on a per unit basis under CLIN 0002. Payment shall be made for all materials, labor, and equipment needed to disassemble and remove the existing excitation systems in accordance with specification section 48 19 26.
CLIN 0003 Install, test, and commission excitation systems and appurtenances; modify existing powerhouse control panels; and deliver and install external wiring, cabling, conduits, and bus (SECTION 48 19 26)
Payment will be made on a per unit basis under CLIN 0003. Payment
SECTION 01 22 00 Page 2 shall be made for all materials, labor, and equipment needed to install and test the new excitation systems, including modifying existing panels and delivery and installations of external wiring, cabling, conduits, and bus in accordance with the specification section 48 19 26.
CLIN 0004 Mobilize and demobilize for installation work (SECTION 48 19 26)
Payment will be made on a job basis under CLIN 0004. Payment shall be made for all costs incurred prior to arriving onsite (mobilization) or immediately after departing the work site (demobilization). These costs include, but are not limited to, all preparatory work at the Contractors shop, labor costs associated with travel to and from the work site, and transportation costs.
CLIN 0005 Perform special factory tests (SECTION 48 19 26)
Payment will be made on a job basis under CLIN 0005. Payment shall be made for all materials, labor, and equipment needed to perform the special factory testing in accordance with specification Section 48 19 26.
CLIN 0006 Special tools and spare parts (SECTION 48 19 26)
Payment will be made on a job basis under CLIN 0006. Payment shall be made for providing and delivering to site all special tools and all spare parts in accordance with specification Section 48 19 26).
CLIN 0007 Concrete removal and repair (SECTION 03 60 00)
Payment will be made on a per unit basis under CLIN 0007. Payment shall be made for all materials, labor, and equipment needed for concrete work in accordance with specification Sections 03 60 00 and 48 19 26.
CLIN 0008 Training (SECTION 48 19 26)
Payment will be made on a job basis under CLIN 0008. Payment shall be made for all materials, labor, and equipment needed to conduct all training sessions required in accordance with specification section 48 19 26.
Asbestos Abatement Work (SECTION 02 82 13)
CLIN 0009A Asbestos Bulk Sampling of Materials (SECTION 02 82 13)
Asbestos bulk sampling will be paid for on a per-Job basis under CLIN 0009A, "Asbestos Bulk Sampling of Materials." This item shall include all costs for collecting, transporting, and analyzing the sample materials.
CLIN 0009B Disposal of Non-Friable Asbestos-Containing Materials
(SECTION 02 82 13)
SECTION 01 22 00 Page 3
Disposal of non-friable asbestos-containing materials will be paid for on a per-pound basis under CLIN 0009B, "Disposal of Non-Friable Asbestos-Containing Materials." Non-Friable Asbestos-Containing Materials (ACM) shall be disposed off as construction debris. Unless otherwise directed, trucks shall be weighed at the disposal site before and after disposal of the material and submission of weight certificates for payment.
Payment under this item is confined to activities once the ACM leaves the powerhouse.
CLIN 0009C Disposal of Friable Asbestos-Containing Materials (SECTION 02 82 13)
Disposal of friable asbestos-containing materials will be paid for on a per-pound basis under unit price Item "Disposal of Friable Asbestos-Containing Materials." Unless otherwise directed, trucks shall be weighed at the disposal site before and after disposal of the material and submission of weight certificates for payment.
Payment under this item is confined to activities once the ACM leaves the powerhouse.
CLIN 0009D Services of a Certified Asbestos Abatement Worker (SECTION 02 82 13)
Services of a certified asbestos abatement worker will be paid for on a per-manhour basis under CLIN 0009D, "Services of a Certified Asbestos Abatement Worker." This pay item also includes in the per-manhourly rate the full compensation cost for expendable supplies/materials incidental to the completion of the abatement activities, which are performed by the certified asbestos abatement worker.
CLIN 0009E Services of a Certified Asbestos Abatement Supervisor
(SECTION 02 82 13)
Services of a certified asbestos abatement worker will be paid for on a per-manhour basis under CLIN 0009E, "Services of a Certified Asbestos Abatement Worker." This pay item also includes in the per-manhourly rate the full compensation cost for expendable supplies/materials incidental to the completion of the abatement activities, which are performed by the certified asbestos abatement supervisor.
CLIN 0009F Services of Certified Air Monitoring Personnel (SECTION 02 82 13)
Services of certified air monitoring personnel will be paid for on a per-manhour basis under CLIN 0009F "Services of Certified Air Monitoring Personnel." This pay item also includes in the per-manhourly rate the full compensation cost for expendable supplies/materials incidental to the completion of the abatement activities, which are performed by the certified air monitoring personnel.
CLIN 0010 Model validation testing and reports (SECTION 48 70 01)
Payment will be made on a job basis under CLIN 0010. Payment shall be made for all materials, labor, and equipment needed to
SECTION 01 22 00 Page 4 perform model validation testing and reporting in accordance with specification section 48 70 01.00 26.
CLIN 0011 Convert applicable reference drawings into CADD format (Section 01 00 00)
Payment will be made on an per unit basis under CLIN 0011. Payment shall be made for all services, labor, and equipment needed to convert existing electronic reference drawing files in raster format to CADD format in accordance with Section 01 00 00 and HPMATOC Section 01 78 00.
CLIN 0012 Furnish and install new brushes and holders (SECTION 48 19 26)
Payment will be made on a per unit basis under CLIN 0012. Payment shall be made for providing and installing new brushes and holders for three units in accordance with specification Section 48 19 26.
CLIN 0013 Inspect and test existing collector ring assembly (SECTION 48 19 26)
Payment will be made on a per unit basis under CLIN 0013. Payment shall be made for all materials, labor, and equipment needed to effect the collector ring inspection and testing work in accordance with specification Section 48 19 26.
CLIN 0014 Performance and Payment Bonds
Payment will be made for the performance and payment bonds that are required as part of this contract. The Government will pay the actual cost of acceptable performance and payment bonds or the Contractor's bid price, whichever is less. The Contractor shall provide evidence of payment (paid invoice) from the bonding company or agency. If the actual cost of the bonds is less than the line item amount, the contract will be modified to adjust the line item accordingly. Adjustment(s) to the line item will also be made for any revisions to the actual bond costs associated with contract changes.
OPTIONAL ITEMS
CLIN 1001 Refurbish existing collector ring assembly (SECTION 48 19 26
Payment will be made on a per unit basis under CLIN 1001. Payment shall be made for all materials, labor, and equipment needed to effect the collector ring refurbishment work in accordance with specification Section 48 19 26.
PART 2 PRODUCTS
(NOT USED)
PART 3 EXECUTION
(NOT USED)
SECTION 01 22 00 Page 5
SECTION 01 22 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
3.3.2 Activity Durations
3.3.3 Design and Permit Activities
3.3.4 Procurement Activities
3.3.5 Closeout Activities
3.3.6 Mandatory Tasks
3.3.7 Government Activities
3.3.8 Standard Activity Coding Dictionary
3.3.8.1 Workers Per Day (WRKP)
3.3.8.2 Responsible Party Coding (RESP)
3.3.8.3 Area of Work Coding (AREA)
3.3.8.4 Modification Number (MODF)
3.3.8.5 Bid Item Coding (BIDI)
3.3.8.6 Phase of Work Coding (PHAS)
3.3.8.7 Category of Work Coding (CATW)
3.3.8.8 Feature of Work Coding (FOW)
3.3.9 Contract Milestones and Constraints
3.3.9.1 Project Start Date Milestone and Constraint
3.3.9.2 End Project Finish Milestone and Constraint
3.3.9.3 Interim Completion Dates and Constraints
3.3.9.3.1 Start Phase
3.3.9.3.2 End Phase
3.3.10 Calendars
3.3.11 Open Ended Logic
3.3.12 Default Progress Data Disallowed
3.3.13 Out-of-Sequence Progress
3.3.14 Added and Deleted Activities
SECTION 01 32 01 Page 1
3.3.15 Original Durations
3.3.16 Leads, Lags, and Start to Finish Relationships
3.3.17 Retained Logic
3.3.18 Percent Complete
3.3.19 Remaining Duration
3.3.20 Cost Loading of Closeout Activities
3.3.20.1 As-Built Drawings
3.3.20.2 O & M Manuals
3.3.21 Anticipated Adverse Weather
3.3.22 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
3.4.2 Initial Project Schedule Submission
3.4.2.1 Design Package Schedule Submission
3.4.3 Periodic Schedule Updates
3.5 SUBMISSION REQUIREMENTS
3.5.1 Narrative Report
3.5.2 Schedule Reports
3.5.2.1 Activity Report
3.5.2.2 Logic Report
3.5.2.3 Total Float Report
3.5.2.4 Earnings Report by CLIN
3.5.2.5 Schedule Log
3.5.3 Network Diagram
3.5.3.1 Continuous Flow
3.5.3.2 Project Milestone Dates
3.5.3.3 Critical Path
3.5.3.4 Banding
3.5.3.5 Cash Flow / Schedule Variance Control (SVC) Diagram
3.6 PERIODIC SCHEDULE UPDATE
3.6.1 Periodic Schedule Update Meetings
3.6.2 Update Submission Following Progress Meeting
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Time Impact Analysis (Prospective Analysis)
3.8.3 Forensic Schedule Analysis (Retrospective Analysis)
3.8.4 Fragmentary Network (Fragnet)
3.8.5 Time Extension
3.8.6 Impact to Early Completion Schedule
3.9 FAILURE TO ACHIEVE PROGRESS
3.9.1 Artificially Improving Progress
3.9.2 Failure to Perform
3.9.3 Recovery Schedule
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01 Page 2
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this
SECTION 01 32 01 Page 3 specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6 version 8.4.
2.1.2 Contractor Software
Scheduling software used by the contractor must be able to meet the requirements of this specification and be compatible with the software used by the government; Primavera P6 version 8.4
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development.
Subcontractors, Designers, and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule.
Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address
SECTION 01 32 01 Page 4 major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Design and Permit Activities
Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. Provide at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work.
Also include review and correction periods associated with each item.
3.3.4 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.5 Closeout Activities
Include activities associated with the closeout of the project that take place after the contractor is substantially complete. The contractor shall maintain at least 45 days of time, post substantial completion, to account for all closeout related activities. These activities may include, but are not limited to: Final Punchlist Corrections, Final Walk Through and Acceptance, Preparation of Submission of O&M and As-Builts.
3.3.6 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of features require design completion Submission, review and acceptance of design packages.
c. Submission of mechanical/electrical/information systems layout drawings.
d. Long procurement activities
e. Submission and approval of O & M manuals.
SECTION 01 32 01 Page 5
f. Submission and approval of as-built drawings.
g. Submission and approval of DD1354 data and installed equipment lists.
h. Submission and approval of testing and air balance (TAB).
i. Submission of TAB specialist design review report.
j. Submission and approval of fire protection specialist.
k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
l. Air and water balancing.
m. Building commissioning - Functional Performance Testing.
n. Controls testing plan submission.
o. Controls testing.
p. Performance Verification testing.
q. Other systems testing, if required.
r. Contractor's pre-final inspection.
s. Correction of punch list from Contractor's pre-final inspection.
t. Government's pre-final inspection.
u. Correction of punch list from Government's pre-final inspection.
v. Final inspection.
3.3.7 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals,acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.8 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site:
http://rms.usace.army.mil.
The SDEF format is as follows:
SECTION 01 32 01 Page 6
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.8.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.8.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.8.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities cannot have more than one Work Area Code.
SECTION 01 32 01 Page 7
3.3.8.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.8.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.8.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are design phase, procurement phase, and construction phase. Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.8.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to design, design submittal, design reviews, review conferences, permits, construction submittals,construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.8.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00 QUALITY CONTROL.
An activity can have only one Feature of Work Code.
3.3.9 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for
SECTION 01 32 01 Page 8 approval on a case by case basis.
3.3.9.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.9.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.9.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.9.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.3.9.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.10 Calendars
Schedule activities on a Calendar to which the activity logically belongs.
Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.
3.3.11 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End
SECTION 01 32 01 Page 9
Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.12 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.13 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.14 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.3.15 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.16 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
3.3.17 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
SECTION 01 32 01 Page 10
3.3.18 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.
3.3.19 Remaining Duration
Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
3.3.20 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3.20.1 As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, which ever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.
3.3.20.2 O & M Manuals
Cost load the "Submission and approval of O & M manuals" activity not less than $20,000. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.
3.3.21 Anticipated Adverse Weather
Paragraph applicable to contracts with clause entitled TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Reflect the number of anticipated adverse weather delays allocated to a weather sensitive activity in the activity's calendar.
3.3.22 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
SECTION 01 32 01 Page 11
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.4.1 Preliminary Project Schedule Submission
Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .