About this opportunity

This solicitation seeks construction services for the Crooked Creek Lake Boat Ramp Road Erosion Repair Project 2021 to be administered by the U.S. Army Corps of Engineers Pittsburgh District. The scope of work includes repairs to existing drainage features, erosion control measures, pavement replacement and rehabilitation, and guiderail replacement along Boat Ramp Road adjacent to Crooked Creek Lake in Armstrong County, Pennsylvania. The base contract and seven awardable options involve improvements to surface drainage, embankment buttressing, culvert cleaning and lining, catch basin installation, asphalt milling and overlay, and parking lot resurfacing. Bids are due by July 13, 2021.

The set-aside is for total small business. The NAICS code is 237110 and PSC code is C211. The estimated value is between $1,000,000 and $5,000,000. Brentzel Excavation LLC submitted the lowest bid of $1,032,986.76 for the base scope. All work must be completed within 365 calendar days of the notice to proceed and the contractor must maintain at least one travel lane at all times. The place of performance is Ford City, Pennsylvania.

Notice text

5 versions

Update #5 · Latest ·

The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the repair of several erosion issues and implementation of preventative measures in defense against future erosion issues at Crooked Creek Lake Boat Ramp Road, Ford City, Armstrong County, PA.  The contract has been divided into a base and seven (7) awardable options and generally includes improvements to surface drainage measures to reduce the likelihood of future erosion, buttressing the Boat Ramp Road embankment in an area of significant erosion, and pavement replacement/rehabilitation at various locations along Boat Ramp Road adjacent to Crooked Creek Lake.  The major features of the requirements are identified below:

The base contract scope of work specifically includes the removal, replacement, and modifications to existing site drainage features including riprap lined channels, culverts, and catch basins. Earthwork including excavation and disposal of excess materials. Toe bench excavation and riprap buttress construction. Existing culvert cleaning, televising, and slip lining. Full-depth pavement replacement and subdrainage installation. Asphalt milling and overlay.

And, the removal and replacement of guiderail.

There will be seven (7) awardable options. The scope of work for the awardable options specifically includes the cleaning, televising, point grouting repair, and slip lining of two existing culverts ranging from 24-inches to 36-inches in diameter and 70 feet to 90 feet in length. Fine grading of an approximate 0.2 acre flat camp area to promote positive drainage to existing and proposed surface drainage features. Asphalt milling and overlaying additional portions of Boat Ramp Road. And, the resurfacing of existing parking lots contiguous with Boat Ramp Road.

The work is to be performed at various locations throughout the length of Boat Ramp Road. Boat Ramp Road provides access for recreationists and for several residents that live in dwellings situated along the adjacent, privately owned Rummel Road.  Since Boat Ramp Road provides the only means of access, appropriate traffic control measures and construction sequencing are necessary to maintain at least one open travel lane at all times during contract duration. 

Surplus, excavated soils are planned to be disposed of on-site at a designated excess material stockpile.  Other excavated materials (exceeding the capacity of the designated excess material stockpile), concrete rubble, and other construction waste material will be disposed of at a commercially permitted facility licensed to accept the waste or recycled if applicable.

The work shall be completed within 365 calendar days after written Notice to Proceed. The estimated cost of the proposed work is between $1,000,000.00 and $5,000,000.00.

____________________________________

Posted Site Visit Sign-in Sheet. 

____________________________________

AMENDMENT 0001 

The purpose of this Amendment is to:
1) Answer questions arising f rom the Solicitation and/or Site Visit
2) Provide revised Specifications Sections 01 22 00.00 08; 01 35 00.00 08; and 33 01 99 and;
3) Provide Specification Attachment - Short-term Repair Construction Photos July 2020

________________________________________

AMENDMENT 0002

The purpose of this Amendment is to answer a question arising from the Solicitation and/or Site Visit.

__________________________________________

Bid Opening Results Posted.

Update #4 ·

The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the repair of several erosion issues and implementation of preventative measures in defense against future erosion issues at Crooked Creek Lake Boat Ramp Road, Ford City, Armstrong County, PA.  The contract has been divided into a base and seven (7) awardable options and generally includes improvements to surface drainage measures to reduce the likelihood of future erosion, buttressing the Boat Ramp Road embankment in an area of significant erosion, and pavement replacement/rehabilitation at various locations along Boat Ramp Road adjacent to Crooked Creek Lake.  The major features of the requirements are identified below:

The base contract scope of work specifically includes the removal, replacement, and modifications to existing site drainage features including riprap lined channels, culverts, and catch basins. Earthwork including excavation and disposal of excess materials. Toe bench excavation and riprap buttress construction. Existing culvert cleaning, televising, and slip lining. Full-depth pavement replacement and subdrainage installation. Asphalt milling and overlay.

And, the removal and replacement of guiderail.

There will be seven (7) awardable options. The scope of work for the awardable options specifically includes the cleaning, televising, point grouting repair, and slip lining of two existing culverts ranging from 24-inches to 36-inches in diameter and 70 feet to 90 feet in length. Fine grading of an approximate 0.2 acre flat camp area to promote positive drainage to existing and proposed surface drainage features. Asphalt milling and overlaying additional portions of Boat Ramp Road. And, the resurfacing of existing parking lots contiguous with Boat Ramp Road.

The work is to be performed at various locations throughout the length of Boat Ramp Road. Boat Ramp Road provides access for recreationists and for several residents that live in dwellings situated along the adjacent, privately owned Rummel Road.  Since Boat Ramp Road provides the only means of access, appropriate traffic control measures and construction sequencing are necessary to maintain at least one open travel lane at all times during contract duration. 

Surplus, excavated soils are planned to be disposed of on-site at a designated excess material stockpile.  Other excavated materials (exceeding the capacity of the designated excess material stockpile), concrete rubble, and other construction waste material will be disposed of at a commercially permitted facility licensed to accept the waste or recycled if applicable.

The work shall be completed within 365 calendar days after written Notice to Proceed. The estimated cost of the proposed work is between $1,000,000.00 and $5,000,000.00.

____________________________________

Posted Site Visit Sign-in Sheet. 

____________________________________

AMENDMENT 0001 

The purpose of this Amendment is to:
1) Answer questions arising f rom the Solicitation and/or Site Visit
2) Provide revised Specifications Sections 01 22 00.00 08; 01 35 00.00 08; and 33 01 99 and;
3) Provide Specification Attachment - Short-term Repair Construction Photos July 2020

________________________________________

AMENDMENT 0002

The purpose of this Amendment is to answer a question arising from the Solicitation and/or Site Visit.

Update #3 ·

The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the repair of several erosion issues and implementation of preventative measures in defense against future erosion issues at Crooked Creek Lake Boat Ramp Road, Ford City, Armstrong County, PA.  The contract has been divided into a base and seven (7) awardable options and generally includes improvements to surface drainage measures to reduce the likelihood of future erosion, buttressing the Boat Ramp Road embankment in an area of significant erosion, and pavement replacement/rehabilitation at various locations along Boat Ramp Road adjacent to Crooked Creek Lake.  The major features of the requirements are identified below:

The base contract scope of work specifically includes the removal, replacement, and modifications to existing site drainage features including riprap lined channels, culverts, and catch basins. Earthwork including excavation and disposal of excess materials. Toe bench excavation and riprap buttress construction. Existing culvert cleaning, televising, and slip lining. Full-depth pavement replacement and subdrainage installation. Asphalt milling and overlay.

And, the removal and replacement of guiderail.

There will be seven (7) awardable options. The scope of work for the awardable options specifically includes the cleaning, televising, point grouting repair, and slip lining of two existing culverts ranging from 24-inches to 36-inches in diameter and 70 feet to 90 feet in length. Fine grading of an approximate 0.2 acre flat camp area to promote positive drainage to existing and proposed surface drainage features. Asphalt milling and overlaying additional portions of Boat Ramp Road. And, the resurfacing of existing parking lots contiguous with Boat Ramp Road.

The work is to be performed at various locations throughout the length of Boat Ramp Road. Boat Ramp Road provides access for recreationists and for several residents that live in dwellings situated along the adjacent, privately owned Rummel Road.  Since Boat Ramp Road provides the only means of access, appropriate traffic control measures and construction sequencing are necessary to maintain at least one open travel lane at all times during contract duration. 

Surplus, excavated soils are planned to be disposed of on-site at a designated excess material stockpile.  Other excavated materials (exceeding the capacity of the designated excess material stockpile), concrete rubble, and other construction waste material will be disposed of at a commercially permitted facility licensed to accept the waste or recycled if applicable.

The work shall be completed within 365 calendar days after written Notice to Proceed. The estimated cost of the proposed work is between $1,000,000.00 and $5,000,000.00.

____________________________________

Posted Site Visit Sign-in Sheet. 

____________________________________

AMENDMENT 0001 

The purpose of this Amendment is to:
1) Answ er questions arising f rom the Solicitation and/or Site Visit
2) Provide revised Specifications Sections 01 22 00.00 08; 01 35 00.00 08; and 33 01 99 and;
3) Provide Specification Attachment - Short-term Repair Construction Photos July 2020

Update #2 ·

The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the repair of several erosion issues and implementation of preventative measures in defense against future erosion issues at Crooked Creek Lake Boat Ramp Road, Ford City, Armstrong County, PA.  The contract has been divided into a base and seven (7) awardable options and generally includes improvements to surface drainage measures to reduce the likelihood of future erosion, buttressing the Boat Ramp Road embankment in an area of significant erosion, and pavement replacement/rehabilitation at various locations along Boat Ramp Road adjacent to Crooked Creek Lake.  The major features of the requirements are identified below:

The base contract scope of work specifically includes the removal, replacement, and modifications to existing site drainage features including riprap lined channels, culverts, and catch basins. Earthwork including excavation and disposal of excess materials. Toe bench excavation and riprap buttress construction. Existing culvert cleaning, televising, and slip lining. Full-depth pavement replacement and subdrainage installation. Asphalt milling and overlay.

And, the removal and replacement of guiderail.

There will be seven (7) awardable options. The scope of work for the awardable options specifically includes the cleaning, televising, point grouting repair, and slip lining of two existing culverts ranging from 24-inches to 36-inches in diameter and 70 feet to 90 feet in length. Fine grading of an approximate 0.2 acre flat camp area to promote positive drainage to existing and proposed surface drainage features. Asphalt milling and overlaying additional portions of Boat Ramp Road. And, the resurfacing of existing parking lots contiguous with Boat Ramp Road.

The work is to be performed at various locations throughout the length of Boat Ramp Road. Boat Ramp Road provides access for recreationists and for several residents that live in dwellings situated along the adjacent, privately owned Rummel Road.  Since Boat Ramp Road provides the only means of access, appropriate traffic control measures and construction sequencing are necessary to maintain at least one open travel lane at all times during contract duration. 

Surplus, excavated soils are planned to be disposed of on-site at a designated excess material stockpile.  Other excavated materials (exceeding the capacity of the designated excess material stockpile), concrete rubble, and other construction waste material will be disposed of at a commercially permitted facility licensed to accept the waste or recycled if applicable.

The work shall be completed within 365 calendar days after written Notice to Proceed. The estimated cost of the proposed work is between $1,000,000.00 and $5,000,000.00.

____________________________________

Posted Site Visit Sign-in Sheet. 

Update #1 ·

The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the repair of several erosion issues and implementation of preventative measures in defense against future erosion issues at Crooked Creek Lake Boat Ramp Road, Ford City, Armstrong County, PA.  The contract has been divided into a base and seven (7) awardable options and generally includes improvements to surface drainage measures to reduce the likelihood of future erosion, buttressing the Boat Ramp Road embankment in an area of significant erosion, and pavement replacement/rehabilitation at various locations along Boat Ramp Road adjacent to Crooked Creek Lake.  The major features of the requirements are identified below:

The base contract scope of work specifically includes the removal, replacement, and modifications to existing site drainage features including riprap lined channels, culverts, and catch basins. Earthwork including excavation and disposal of excess materials. Toe bench excavation and riprap buttress construction. Existing culvert cleaning, televising, and slip lining. Full-depth pavement replacement and subdrainage installation. Asphalt milling and overlay.

And, the removal and replacement of guiderail.

There will be seven (7) awardable options. The scope of work for the awardable options specifically includes the cleaning, televising, point grouting repair, and slip lining of two existing culverts ranging from 24-inches to 36-inches in diameter and 70 feet to 90 feet in length. Fine grading of an approximate 0.2 acre flat camp area to promote positive drainage to existing and proposed surface drainage features. Asphalt milling and overlaying additional portions of Boat Ramp Road. And, the resurfacing of existing parking lots contiguous with Boat Ramp Road.

The work is to be performed at various locations throughout the length of Boat Ramp Road. Boat Ramp Road provides access for recreationists and for several residents that live in dwellings situated along the adjacent, privately owned Rummel Road.  Since Boat Ramp Road provides the only means of access, appropriate traffic control measures and construction sequencing are necessary to maintain at least one open travel lane at all times during contract duration. 

Surplus, excavated soils are planned to be disposed of on-site at a designated excess material stockpile.  Other excavated materials (exceeding the capacity of the designated excess material stockpile), concrete rubble, and other construction waste material will be disposed of at a commercially permitted facility licensed to accept the waste or recycled if applicable.

The work shall be completed within 365 calendar days after written Notice to Proceed. The estimated cost of the proposed work is between $1,000,000.00 and $5,000,000.00.

Files

Show all 12

Notice history

Notice Type Posted
Crooked Creek Lake Boat Ramp Road Erosion Repair Project 2021 Award Award Notice
This notice Latest solicitation Solicitation
Crooked Creek Lake Boat Ramp Road Erosion Repair Project 2021 Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Borough of Millvale, Pennsylvania, Local Protection Project (LPP) PL84-99 Rehabilitation Borough of Millvale, City of Pittsburgh, Allegheny County, Pennsylvania 15223 · NAICS 237990 ENDIST Pittsburgh Total Small Business
Canonsburg-Houston, Pennsylvania, Local Protection Project (LPP) PL84-99 Rehabilitation Canonsburg-Houston, Strabane, Washington County, Pennsylvania 15317 · NAICS 237990 ENDIST Pittsburgh Total Small Business
Pittsburgh facility 079 MEP parking lot erosion control 7100 Leech Farm Rd, Pittsburgh, PA 15206 15206 ENDIST Philadelphia No set-aside
Asphalt Services at Carr Creek Lake NAICS 237310 ENDIST Louisville No set-aside
JP Murtha Float Mooring Bitts Retrofit JP Murtha Locks and DamMonongahela River BasinGibsonton Road, Monessen, PA 15062 15062 · NAICS 237990 ENDIST Pittsburgh No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors