About this opportunity

The General Services Administration is procuring Construction Manager as Constructor (CMc) services for the expansion and modernization of the Land Port of Entry at Coburn Gore, Maine through a two-step competitive solicitation process. The project involves designing and constructing a new fully functional border crossing facility to replace the existing 1932 historic inspection station, with objectives including maintaining full operational capabilities during construction, ensuring site security and utility continuity, and preserving the site's historic character while meeting U.S. Customs and Border Protection operational requirements. The evaluation will utilize a best-value trade-off process prioritizing non-price technical factors, including experience on similar projects (30%), management and technical approach (25%), key personnel qualifications (20%), past performance (20%), and small business participation (5%). The procurement follows GSA Design Excellence and Operational Excellence guidelines, CBP's 2023 Design Standards, and sustainability requirements from the Inflation Reduction Act. However, according to the most recent amendment dated August 11, 2025, this solicitation has been cancelled.

This procurement does not utilize any set-aside designations and is open to full and open competition under NAICS code 236220 with a small business size standard of $45 million average annual receipts. No current incumbents or contractors are identified in the solicitation documents. The estimated total construction cost ranges between $90 million and $100 million, with the contract structured as a firm-fixed-price design phase followed by an optional construction phase at a Guaranteed Maximum Price. The project timeline originally anticipated design phase services commencing in Fall/Winter 2025, with construction phase work expected to begin in Summer 2026 and last approximately 32 months. The place of performance is the 3.6-acre U.S. Inspection Station located at 6092 Arnold Trail in Coburn Gore, Maine, which is designated within the National Register of Historic Places and represents one of several extant examples of border crossing stations constructed between 1930-1943.

Notice text

3 versions

Update #3 · Latest ·

The General Services Administration (GSA) intends to construct a new fully functional Land Port of Entry (LPOE) at Coburn Gore, Maine.  The government will utilize the "Construction Manager as Constructor (CMc)", also known as "Construction Manager at Risk" or "Guaranteed Maximum Price (GMP),” delivery method.  The GSA intends to issue a 2-Step CMc solicitation.  The CMc project delivery method includes requirements for the Design Phase Services and the Options(s) for Construction Services at a Guaranteed Maximum Price (GMP).  The project shall adhere to the GSA Design Excellence and Operational Excellence guidelines, the GSA Core Building Standards.   

The proposed expansion and modernization of the Land Port of Entry (LPOE) complex located at 6092 Arnold Trail in Coburn Gore, Maine, was designed to strengthen supply chains, improve operational capabilities and facility infrastructure, spur economic growth, and bolster the country’s security. This LPOE is designated within the National Register of Historic Places (NRHP) and was originally constructed in 1932. The 3.6-acre U.S. Inspection Station – Coburn Gore, Maine was entered into the National Register of Historic Places (NRHP) on 9/10/14. Important in the history of border security in the United States, Coburn Gore LPOE is one of several extant examples of a wave of border crossing stations constructed between 1930 – 1943, as further detailed in the related 2014 Multiple Property Listing for U.S. Border Inspection Stations 1930 – 1943. The deficiencies at the LPOE fall into two broad categories: 1) limited capacity and facilities for port operations; and 2) the condition of the existing buildings. Thus, the expansion and modernization of the LPOE would provide a port that is functional, accessible, and equitable for U.S. Customs and Border Protection (CBP) to more efficiently carry out its agency mission and their operations and interactions with the public. Upon completion, the LPOE is anticipated to address these deficiencies and facilitate the efficient functioning of CBP operations while adhering to their POR, 2023 Design Standards, and the GSA Core Building Standards.

The main goals for this project include the following:

  1. Maintain full operations and current throughputs for all Port agencies throughout Construction.
  2. Maintain accessibility throughout the site during construction implementation.
  3. Maintain site security throughout construction.
  4. Ensure continuous availability of utilities (power, phone/data, water, sewer, and stormwater) and emergency power during phased construction.
  5.  Deliver Design and Construction Excellence that meets CBP’s POR, CBP 2023 Design Standards, and GSA’s Core Building Standards.
  6. Address significant problems and issues with each existing facility and its surrounding parcel.
  7. Maintain Coburn Gore’s significant historic character.
  8. Provide an upgraded port that is functional and accessible for each customer agency, their operations, and their interactions with the public.
  9. Perform design and construction efficiently and effectively using current technology tools for design, reviews, inspections, and project management processes.
  10. Provide the best value to GSA, their customer agencies, the community, and the American taxpayer.

The design phase services shall be performed at a firm-fixed-price and the optional construction services shall be performed at a Guaranteed Maximum Price (GMP).  This solicitation will be executed pursuant to Federal Acquisition Regulation (FAR) Subpart 15.101-1, Best value continuum, Trade-Off process and FAR Subpart 15.202, Advisory multi-step process.  Pursuant to FAR Clause 52.215-1 Instructions to Offerors-Competitive Acquisition, the Government intends to evaluate proposals and award contracts without discussions with offerors (except clarifications as described in FAR 15.306(a)), although it reserves the right to open discussions should it be determined to be in its best interests.  It is the government’s intention to award a contract to the offeror whose proposal conforms to the RFP requirements and is considered to be the most advantageous to the government, price and technical factors considered.  Competitive proposals shall be evaluated and assessed based on the factors specified in this solicitation.  For this solicitation, the combined weight of the non-price factors is significantly more important than the Total Evaluated Price.

One (1) award will be made from this two-step (2-Step) CMc solicitation.

This procurement will be solicited as full and open competition.

The North American Industry Classification System (NAICS) code for this acquisition is 236220 (Commercial and Institutional Building Construction).  The small business size standard is $45 million average annual receipts.

Competitive proposals shall be evaluated based on the factors specified in the solicitation.  This procurement will follow the advisory multistep process in accordance with FAR 15.202.  It is anticipated that the non-price technical factors will be broken down by phase, as follows:

Phase 1:

1. Experience in Providing Design Phase Services and Construction Phase Services on Similar Projects (30%)

2.   Management and Technical Approach (Design Phase Services and Construction Phase Services) (25%)

3. Qualifications and Experience of Key Personnel (20%)

4. Past Performance in Providing Design Phase Services and Construction Phase Services on Similar Projects provided under Factor #1 (20%)

Phase 2:

5.     Small Business Participation (5%)

6.     Price

Upon completion of the evaluation of Phase I proposals, an advisory shortlist will be developed. All offerors will be notified as to whether their firm was included on or excluded from the advisory shortlist.  The Advisory Shortlist will not be made public.  It shall be noted that exclusion from the advisory shortlist shall not preclude offerors from submitting a Phase II proposal.

Important Notes: (1) A bid guarantee will be required ninety (90) calendar days prior to the exercise of the GMP Option for Construction Services.  The Contractor shall furnish required performance and payment bonds within fourteen (14) calendar days of exercise of the GMP Option. (2) In accordance with FAR 30.101, Cost Accounting Standards, the Contractor must demonstrate their compliance with Cost Accounting Standards. Award shall not be made to any contractor that is not CAS compliant.

The estimated total construction cost for the project is between $90M and $100M.

Award is anticipated to be made for design phase services, with the GMP Construction Option(s) to be available for award at a later date as needed.

Design phase services are anticipated to commence upon award of the contract on or about Fall/Winter 2025.  The Optional Construction Phase Work is anticipated to be awarded on or about Summer 2026, with a performance period for the Design Phase of approximately date of award through Summer 2026, and a period of approximately 32 months for the Construction Phase.

A pre-proposal conference is expected to be held approximately 2 weeks from the issue date of the Phase 1 solicitation.  Additional details will be provided with the solicitation.  Small businesses are highly encouraged to attend.  Prior notification of attendance to this conference is mandatory. 

To ensure that you receive all information regarding this solicitation, please register to receive updates at www.SAM.gov, follow the procedures for notification registration.

Interested Parties/How to Offer:  The Solicitation will only be available electronically.  The Phase 1 solicitation will be available on 04/08/2025, with proposals due 06/24/2025 at 2:00PM EST.  The solicitation can only be obtained by accessing SAM.gov, a secure website designed to safeguard sensitive but unclassified (SBU) acquisition material. Potential offerors will be responsible for downloading the solicitation and for monitoring the website for possible amendments and/or additional information.  Potential offerors must be registered in SAM.gov.  Inquiries concerning the project should be directed to the following email addresses: james.adamo@gsa.gov; michele.valenza@gsa.gov; and caitlyn.egan@gsa.gov, and reference the solicitation number in the subject line.

Update #2 ·

The General Services Administration (GSA) intends to construct a new fully functional Land Port of Entry (LPOE) at Coburn Gore, Maine.  The government will utilize the "Construction Manager as Constructor (CMc)", also known as "Construction Manager at Risk" or "Guaranteed Maximum Price (GMP),” delivery method.  The GSA intends to issue a 2-Step CMc solicitation.  The CMc project delivery method includes requirements for the Design Phase Services and the Options(s) for Construction Services at a Guaranteed Maximum Price (GMP).  The project shall adhere to the GSA Design Excellence and Operational Excellence guidelines, the GSA Core Building Standards.   

The proposed expansion and modernization of the Land Port of Entry (LPOE) complex located at 6092 Arnold Trail in Coburn Gore, Maine, was designed to strengthen supply chains, improve operational capabilities and facility infrastructure, spur economic growth, and bolster the country’s security. This LPOE is designated within the National Register of Historic Places (NRHP) and was originally constructed in 1932. The 3.6-acre U.S. Inspection Station – Coburn Gore, Maine was entered into the National Register of Historic Places (NRHP) on 9/10/14. Important in the history of border security in the United States, Coburn Gore LPOE is one of several extant examples of a wave of border crossing stations constructed between 1930 – 1943, as further detailed in the related 2014 Multiple Property Listing for U.S. Border Inspection Stations 1930 – 1943. The deficiencies at the LPOE fall into two broad categories: 1) limited capacity and facilities for port operations; and 2) the condition of the existing buildings. Thus, the expansion and modernization of the LPOE would provide a port that is functional, accessible, and equitable for U.S. Customs and Border Protection (CBP) to more efficiently carry out its agency mission and their operations and interactions with the public. Upon completion, the LPOE is anticipated to address these deficiencies and facilitate the efficient functioning of CBP operations while adhering to their POR, 2023 Design Standards, and the GSA Core Building Standards.

The main goals for this project include the following:

  1. Maintain full operations and current throughputs for all Port agencies throughout Construction.
  2. Maintain accessibility throughout the site during construction implementation.
  3. Maintain site security throughout construction.
  4. Ensure continuous availability of utilities (power, phone/data, water, sewer, and stormwater) and emergency power during phased construction.
  5.  Deliver Design and Construction Excellence that meets CBP’s POR, CBP 2023 Design Standards, and GSA’s Core Building Standards.
  6. Address significant problems and issues with each existing facility and its surrounding parcel.
  7. Maintain Coburn Gore’s significant historic character.
  8. Provide an upgraded port that is functional and accessible for each customer agency, their operations, and their interactions with the public.
  9. Perform design and construction efficiently and effectively using current technology tools for design, reviews, inspections, and project management processes.
  10. Provide the best value to GSA, their customer agencies, the community, and the American taxpayer.

The design phase services shall be performed at a firm-fixed-price and the optional construction services shall be performed at a Guaranteed Maximum Price (GMP).  This solicitation will be executed pursuant to Federal Acquisition Regulation (FAR) Subpart 15.101-1, Best value continuum, Trade-Off process and FAR Subpart 15.202, Advisory multi-step process.  Pursuant to FAR Clause 52.215-1 Instructions to Offerors-Competitive Acquisition, the Government intends to evaluate proposals and award contracts without discussions with offerors (except clarifications as described in FAR 15.306(a)), although it reserves the right to open discussions should it be determined to be in its best interests.  It is the government’s intention to award a contract to the offeror whose proposal conforms to the RFP requirements and is considered to be the most advantageous to the government, price and technical factors considered.  Competitive proposals shall be evaluated and assessed based on the factors specified in this solicitation.  For this solicitation, the combined weight of the non-price factors is significantly more important than the Total Evaluated Price.

One (1) award will be made from this two-step (2-Step) CMc solicitation.

This procurement will be solicited as full and open competition.

The North American Industry Classification System (NAICS) code for this acquisition is 236220 (Commercial and Institutional Building Construction).  The small business size standard is $45 million average annual receipts.

Competitive proposals shall be evaluated based on the factors specified in the solicitation.  This procurement will follow the advisory multistep process in accordance with FAR 15.202.  It is anticipated that the non-price technical factors will be broken down by phase, as follows:

Phase 1:

1. Experience in Providing Design Phase Services and Construction Phase Services on Similar Projects (30%)

2.   Management and Technical Approach (Design Phase Services and Construction Phase Services) (25%)

3. Qualifications and Experience of Key Personnel (20%)

4. Past Performance in Providing Design Phase Services and Construction Phase Services on Similar Projects provided under Factor #1 (20%)

Phase 2:

5.     Small Business Participation (5%)

6.     Price

Upon completion of the evaluation of Phase I proposals, an advisory shortlist will be developed. All offerors will be notified as to whether their firm was included on or excluded from the advisory shortlist.  The Advisory Shortlist will not be made public.  It shall be noted that exclusion from the advisory shortlist shall not preclude offerors from submitting a Phase II proposal.

Important Notes: (1) A bid guarantee will be required ninety (90) calendar days prior to the exercise of the GMP Option for Construction Services.  The Contractor shall furnish required performance and payment bonds within fourteen (14) calendar days of exercise of the GMP Option. (2) In accordance with FAR 30.101, Cost Accounting Standards, the Contractor must demonstrate their compliance with Cost Accounting Standards. Award shall not be made to any contractor that is not CAS compliant.

The estimated total construction cost for the project is between $90M and $100M.

Award is anticipated to be made for design phase services, with the GMP Construction Option(s) to be available for award at a later date as needed.

Design phase services are anticipated to commence upon award of the contract on or about Fall/Winter 2025.  The Optional Construction Phase Work is anticipated to be awarded on or about Summer 2026, with a performance period for the Design Phase of approximately date of award through Summer 2026, and a period of approximately 32 months for the Construction Phase.

A pre-proposal conference is expected to be held approximately 2 weeks from the issue date of the Phase 1 solicitation.  Additional details will be provided with the solicitation.  Small businesses are highly encouraged to attend.  Prior notification of attendance to this conference is mandatory. 

To ensure that you receive all information regarding this solicitation, please register to receive updates at www.SAM.gov, follow the procedures for notification registration.

Interested Parties/How to Offer:  The Solicitation will only be available electronically.  The Phase 1 solicitation will be available on 04/08/2025, with proposals due 06/17/2025 at 2:00PM EST.  The solicitation can only be obtained by accessing SAM.gov, a secure website designed to safeguard sensitive but unclassified (SBU) acquisition material. Potential offerors will be responsible for downloading the solicitation and for monitoring the website for possible amendments and/or additional information.  Potential offerors must be registered in SAM.gov.  Inquiries concerning the project should be directed to the following email addresses: james.adamo@gsa.gov; michele.valenza@gsa.gov; and caitlyn.egan@gsa.gov, and reference the solicitation number in the subject line.

Update #1 ·

The General Services Administration (GSA) intends to construct a new fully functional Land Port of Entry (LPOE) at Coburn Gore, Maine.  The government will utilize the "Construction Manager as Constructor (CMc)", also known as "Construction Manager at Risk" or "Guaranteed Maximum Price (GMP),” delivery method.  The GSA intends to issue a 2-Step CMc solicitation.  The CMc project delivery method includes requirements for the Design Phase Services and the Options(s) for Construction Services at a Guaranteed Maximum Price (GMP).  The project shall adhere to the GSA Design Excellence and Operational Excellence guidelines, the GSA Core Building Standards.   

The proposed expansion and modernization of the Land Port of Entry (LPOE) complex located at 6092 Arnold Trail in Coburn Gore, Maine, was designed to strengthen supply chains, improve operational capabilities and facility infrastructure, spur economic growth, and bolster the country’s security. This LPOE is designated within the National Register of Historic Places (NRHP) and was originally constructed in 1932. The 3.6-acre U.S. Inspection Station – Coburn Gore, Maine was entered into the National Register of Historic Places (NRHP) on 9/10/14. Important in the history of border security in the United States, Coburn Gore LPOE is one of several extant examples of a wave of border crossing stations constructed between 1930 – 1943, as further detailed in the related 2014 Multiple Property Listing for U.S. Border Inspection Stations 1930 – 1943. The deficiencies at the LPOE fall into two broad categories: 1) limited capacity and facilities for port operations; and 2) the condition of the existing buildings. Thus, the expansion and modernization of the LPOE would provide a port that is functional, accessible, and equitable for U.S. Customs and Border Protection (CBP) to more efficiently carry out its agency mission and their operations and interactions with the public. Upon completion, the LPOE is anticipated to address these deficiencies and facilitate the efficient functioning of CBP operations while adhering to their POR, 2023 Design Standards, and the GSA Core Building Standards.

The main goals for this project include the following:

  1. Maintain full operations and current throughputs for all Port agencies throughout Construction.
  2. Maintain accessibility throughout the site during construction implementation.
  3. Maintain site security throughout construction.
  4. Ensure continuous availability of utilities (power, phone/data, water, sewer, and stormwater) and emergency power during phased construction.
  5.  Deliver Design and Construction Excellence that meets CBP’s POR, CBP 2023 Design Standards, and GSA’s Core Building Standards.
  6. Address significant problems and issues with each existing facility and its surrounding parcel.
  7. Maintain Coburn Gore’s significant historic character.
  8. Provide an upgraded port that is functional and accessible for each customer agency, their operations, and their interactions with the public.
  9. Perform design and construction efficiently and effectively using current technology tools for design, reviews, inspections, and project management processes.
  10. Provide the best value to GSA, their customer agencies, the community, and the American taxpayer.

The design phase services shall be performed at a firm-fixed-price and the optional construction services shall be performed at a Guaranteed Maximum Price (GMP).  This solicitation will be executed pursuant to Federal Acquisition Regulation (FAR) Subpart 15.101-1, Best value continuum, Trade-Off process and FAR Subpart 15.202, Advisory multi-step process.  Pursuant to FAR Clause 52.215-1 Instructions to Offerors-Competitive Acquisition, the Government intends to evaluate proposals and award contracts without discussions with offerors (except clarifications as described in FAR 15.306(a)), although it reserves the right to open discussions should it be determined to be in its best interests.  It is the government’s intention to award a contract to the offeror whose proposal conforms to the RFP requirements and is considered to be the most advantageous to the government, price and technical factors considered.  Competitive proposals shall be evaluated and assessed based on the factors specified in this solicitation.  For this solicitation, the combined weight of the non-price factors is significantly more important than the Total Evaluated Price.

One (1) award will be made from this two-step (2-Step) CMc solicitation.

This procurement will be solicited as full and open competition.

The North American Industry Classification System (NAICS) code for this acquisition is 236220 (Commercial and Institutional Building Construction).  The small business size standard is $45 million average annual receipts.

Competitive proposals shall be evaluated based on the factors specified in the solicitation.  This procurement will follow the advisory multistep process in accordance with FAR 15.202.  It is anticipated that the non-price technical factors will be broken down by phase, as follows:

Phase 1:

1. Experience in Providing Design Phase Services and Construction Phase Services on Similar Projects (30%)

2.   Management and Technical Approach (Design Phase Services and Construction Phase Services) (25%)

3. Qualifications and Experience of Key Personnel (20%)

4. Past Performance in Providing Design Phase Services and Construction Phase Services on Similar Projects provided under Factor #1 (20%)

Phase 2:

5.     Small Business Participation (5%)

6.     Price

Upon completion of the evaluation of Phase I proposals, an advisory shortlist will be developed. All offerors will be notified as to whether their firm was included on or excluded from the advisory shortlist.  The Advisory Shortlist will not be made public.  It shall be noted that exclusion from the advisory shortlist shall not preclude offerors from submitting a Phase II proposal.

Important Notes: (1) A bid guarantee will be required ninety (90) calendar days prior to the exercise of the GMP Option for Construction Services.  The Contractor shall furnish required performance and payment bonds within fourteen (14) calendar days of exercise of the GMP Option. (2) In accordance with FAR 30.101, Cost Accounting Standards, the Contractor must demonstrate their compliance with Cost Accounting Standards. Award shall not be made to any contractor that is not CAS compliant.

The estimated total construction cost for the project is between $90M and $100M.

Award is anticipated to be made for design phase services, with the GMP Construction Option(s) to be available for award at a later date as needed.

Design phase services are anticipated to commence upon award of the contract on or about Fall/Winter 2025.  The Optional Construction Phase Work is anticipated to be awarded on or about Summer 2026, with a performance period for the Design Phase of approximately date of award through Summer 2026, and a period of approximately 32 months for the Construction Phase.

A pre-proposal conference is expected to be held approximately 2 weeks from the issue date of the Phase 1 solicitation.  Additional details will be provided with the solicitation.  Small businesses are highly encouraged to attend.  Prior notification of attendance to this conference is mandatory. 

To ensure that you receive all information regarding this solicitation, please register to receive updates at www.SAM.gov, follow the procedures for notification registration.

Interested Parties/How to Offer:  The Solicitation will only be available electronically.  The Phase 1 solicitation will be available on 04/08/2025, with proposals due 05/27/2025 at 2:00PM EST.  The solicitation can only be obtained by accessing SAM.gov, a secure website designed to safeguard sensitive but unclassified (SBU) acquisition material. Potential offerors will be responsible for downloading the solicitation and for monitoring the website for possible amendments and/or additional information.  Potential offerors must be registered in SAM.gov.  Inquiries concerning the project should be directed to the following email addresses: james.adamo@gsa.gov; michele.valenza@gsa.gov; and caitlyn.egan@gsa.gov, and reference the solicitation number in the subject line.

Files

File Type Posted
Solicitation Amendment 47PB0024R0068_0005.pdf PDF
Solicitation Amendment 47PB0024R0068_0004 2025 06 12.pdf PDF
B. Phase I Solicitation Document - Two-Step CMc Updated 2025 06 12.pdf PDF
C. Phase I Agreement Document - Two-Step CMc Updated 2025 06 12.pdf PDF
Solicitation Amendment 47PB0024R0068_0003 2025 05 29.pdf PDF
Solicitation Amendment 47PB0024R0068_0002 2025 05 21.pdf PDF
B. Phase I Solicitation Document - Two-Step CMc Amendment 01 Update 2025 05 02.pdf PDF
C. Phase I Agreement Document - Two-Step CMc Amendment 01 Update 2025 05 02.pdf PDF
Solicitation Amendment 47PB0024R0068_0001 2025 05 02.pdf PDF
Coburn Gore Phase I Pre-Proposal Conference Attendance 2025 04 22.pdf PDF
Phase I Pre-Proposal Conference Final Slides 2025 04 22.pdf PDF
1. Coburn Gore LPOE CMc SOW Final 2025 03 27.pdf PDF
5. Colby Coburn Gore Three-Phase Final Report 2022 12 22.pdf PDF
10. PBS Core Building Standards Memorandum 2025 02 24.pdf PDF
B. Phase I Solicitation Document - Two-Step CMc 2025 04 07.pdf PDF
2. Coburn Gore Three phase SOW Final 2025 04 04.pdf PDF
4. Coburn Gore LPOE - CMa w CxP SOW 2023 10 12.pdf PDF
6. P-120 Public Buildings Service Cost and Schedule Management Policy Requirements, October 2022.pdf PDF
A. RFP 47PB0024R0068 SF1442 2025 04 08.pdf PDF
C. Phase I Agreement Document - Two-Step CMc 2025 04 07.pdf PDF
D. Coburn Gore Offeror Representations and Certifications 2025 04 07.pdf PDF
E. Past Performance Questionnaire 2025 04 07.pdf PDF
G. CBP Non-Disclosure Agreement Form.pdf PDF
11. GSA Commissioning Guide September 2020.pdf PDF
3. Coburn Gore AE SOW_FINAL 2024 08 06.pdf PDF
Show all 25

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Coburn Gore LPOE CMc Pre-Solicitation Pre-Solicitation
Construction Manager as Constructor (CMc) or Construction Manager at Risk (CMr) New Land Port of Entry, Coburn Gore, Maine Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Upcoming Construction Opportunity: Land Port of Entry Highgate Springs, VT Highgate Springs, Vermont 05460, United States · NAICS 236220 — No set-aside
SOLICITATION NOTICE- Massena NY Virtual Law Enforcement Training Facility- Construction Massena, New York 13662, United States · NAICS 236220 — Total Small Business
Coburn Gore LPOE Art in Architecture Project Coburn Gore, Maine 04936, United States · NAICS 711510 — Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity