This document is a Solicitation Amendment for the Coburn Gore Land Port of Entry (LPOE) Construction Manager as Constructor (CMc) New Construction project. The amendment (Number 0001) modifies the original solicitation 47PB0024R0068 with several key changes: the proposal due date remains May 27, 2025 at 2:00 PM EST, FAR Clause 52.222-21 is removed, points of contact for Jacobs Technology Inc. are updated to John Ososkie and Michael Alvarez, IRA requirements are updated, and evaluation factors have been modified. A new requirement mandates that joint ventures must be registered in SAM as a separate entity before submitting a proposal.

The solicitation is for a GSA project to construct a new fully functional Land Port of Entry in Coburn Gore, Maine, using a two-step Construction Manager at Risk delivery method. The project is estimated to cost between $90M and $100M, with design phase services anticipated to commence in Fall/Winter 2025 and construction phase work expected to be awarded in Summer 2026. The project aims to address operational deficiencies, improve facility infrastructure, and maintain the site's historic character. The procurement will follow a best value trade-off process, with non-price technical factors significantly more important than total evaluated price. Small businesses are encouraged to participate, and the NAICS code is 236220 with a $45 million average annual receipts size standard.

View the file

Other files

File Type Posted
Solicitation Amendment 47PB0024R0068_0005.pdf PDF
C. Phase I Agreement Document - Two-Step CMc Updated 2025 06 12.pdf PDF
B. Phase I Solicitation Document - Two-Step CMc Updated 2025 06 12.pdf PDF
Solicitation Amendment 47PB0024R0068_0004 2025 06 12.pdf PDF
Solicitation Amendment 47PB0024R0068_0003 2025 05 29.pdf PDF
Solicitation Amendment 47PB0024R0068_0002 2025 05 21.pdf PDF
B. Phase I Solicitation Document - Two-Step CMc Amendment 01 Update 2025 05 02.pdf PDF
C. Phase I Agreement Document - Two-Step CMc Amendment 01 Update 2025 05 02.pdf PDF
Phase I Pre-Proposal Conference Final Slides 2025 04 22.pdf PDF
Coburn Gore Phase I Pre-Proposal Conference Attendance 2025 04 22.pdf PDF
10. PBS Core Building Standards Memorandum 2025 02 24.pdf PDF
11. GSA Commissioning Guide September 2020.pdf PDF
G. CBP Non-Disclosure Agreement Form.pdf PDF
D. Coburn Gore Offeror Representations and Certifications 2025 04 07.pdf PDF
C. Phase I Agreement Document - Two-Step CMc 2025 04 07.pdf PDF
1. Coburn Gore LPOE CMc SOW Final 2025 03 27.pdf PDF
3. Coburn Gore AE SOW_FINAL 2024 08 06.pdf PDF
A. RFP 47PB0024R0068 SF1442 2025 04 08.pdf PDF
E. Past Performance Questionnaire 2025 04 07.pdf PDF
5. Colby Coburn Gore Three-Phase Final Report 2022 12 22.pdf PDF
4. Coburn Gore LPOE - CMa w CxP SOW 2023 10 12.pdf PDF
B. Phase I Solicitation Document - Two-Step CMc 2025 04 07.pdf PDF
2. Coburn Gore Three phase SOW Final 2025 04 04.pdf PDF
6. P-120 Public Buildings Service Cost and Schedule Management Policy Requirements, October 2022.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

Description of Modification Continuation Page

Amendment 01 - The Solicitation 47PB0024R0068, Coburn Gore LPOE CMc New Construction, is hereby amended as follows:

1. The proposal due date remains the same on May 27, 2025 at 2:00PM EST.

2. FAR Clause 52.222-21 Prohibition of Segregated Facilities (APR 15) is removed from Section IV.C. of the Phase I Agreement Document.

3. A note has been added to Section IV.B. of the Phase I Agreement Document.

4. A note has been added in Section IV.B.(12) FAR 52.244-5, which reads âApplicable to GMP Construction Services (Not Firm-Fixed Price Design Phase Servicesâ

5. The Point of Contact for Jacobs Technology Inc. is changed to John Ososkie and Michael Alvarez in Section II.E.6 of The Phase I Solicitation Document.

6. The IRA requirements included on the Cover Page and Section II.D.3 of the Phase I Solicitation Document, and Sections II.B., III.K.2, and III.O. of the Phase I Agreement Document have been updated.

7. The Evaluation Factors in Sections II.C., VII.A., and VII.F. of the Phase I Solicitation Document have been changed.

8. Section II.F. of the Phase I Solicitation Document has been changed to add paragraph (5) which states the following: (5) Joint Ventures must be registered in SAM as a separate entity before submitting a proposal for this solicitation.

9. The following responses to RFI questions are incorporated into the Solicitation:

Q: For the purposes of this solicitation RFP, will information pertaining to parent company, affiliates, divisions, subsidiaries, or other related entities be considered for past performance evaluation when submitted by the business entity of the offeror?

A: For the purposes of this solicitation, offerors may be able to use information pertaining to a parent company or related entities, as long as the relationship between them will be disclosed.

10. Attached to this Amendment you will find updated copies of the Phase I Solicitation and Agreement documents.

These revised copies replace the original documents in their entirety.

All other information provided in the Solicitation remains the same.

NOTE: Offerors are reminded to acknowledge receipt of this amendment by one of the methods cited in Block 11.

47PB0024R0068/0001

topmostSubform[0]:
Page2[0]:
TextField1[5]:
TextField1[2]:
TextField1[1]:
TextField1[4]:
TextField1[3]:
TextField1[0]:
Page1[0]:
Code[0]: 1PQ
Copies[0]: 1
CheckBox9[0]: 1
Code[2]: 1PQC
NameandTitleOfficer[0]: James Adamo, Director, Acquisition Management Division
Is[0]: Off
CheckBox10[0]: Off
NameandAddress[0]:
DateSigned[1]:
Pages[0]: 3
AmendmentNo[0]: 0001
Dated10B[0]:
ModificationNo[0]:
AdministeredBy[0]: Acquisition Management Division (1PQ) Contract Operations Branch (1PQC), GSA/PBS

10 Causeway Street, Rm 1100 Boston, MA 02222-1077 USA

FacilityCode[0]:
CheckBox13B[0]: Off
CheckBox13D[0]: Off
ReqNumber[0]: EQ1PC-24-0025
Dated9B[0]: 4/8/2025
C13[0]:
Description[0]:

[See Description of Modification Continuation Page]

NotExtended[0]: 1
Code[1]:
AmendmentNo[1]: 47PB0024R0068
ContractIDCode[0]:
DateSigned[0]:
CheckBox11[0]: 1
Page[0]: 1
AccountingData[0]:
CopiesReturned[0]:
CheckBox13A[0]: Off
IsNot[0]: Off
EffectiveDate[0]: 5/2/2025
A13[0]:
ProjectNo[0]:
CheckBox13C[0]: Off
Extended[0]: Off
D13[0]:
IssuedBy[0]: Acquisition Management Division (1PQ) GSA/PBS

10 CAUSEWAY ST., RM 1100

BOSTON, MA 02222-1077 USA

NameandTitleSigner[0]: