This solicitation seeks proposals for the Civil Engineering Building and Utilities Mechanical Program III (CE BUMP III) at Arnold Air Force Base. The Department of the Air Force Materiel Command Test Center is procuring mechanical installation, minor construction, infrastructure sustainment, maintenance and repair services for heating, ventilation and air conditioning, water, steam and fuel systems. Evaluation will be based on past performance, which is significantly more important than price. Proposals are due by June 20, 2023. Up to five multiple award indefinite delivery, indefinite quantity contracts will be awarded for a five year ordering period with a maximum value of $99 million.

This requirement is set aside exclusively for small businesses. The primary NAICS code is 238210 and PSC code R499. Evaluation will consider recency and relevancy of past performance on contracts over $100,000 for similar design-build and construction services. An initial seed project to repair and upgrade the fire suppression system in Building 579 is valued between $250,000-$500,000. Work will be performed at Arnold Air Force Base in Tennessee over a five year period.

Notice text

8 versions

Update #8 · Latest ·

Amendment 0005: The purpose this amendment is to:

a) Incorporate the clause at FAR 52.204-27, Prohibition on a ByteDance Covered Application into this solicitation.

b) Incorporate additional questions and answers.  Please see the attached questions and answers dated 15 June 2023.

Amendment 0004: The purpose this amendment is to:

a) Extend the proposal due date from 13 June 2023 at 2:00 pm central daylight time to 20 June 2023 2:00 pm central daylight time.

b) Upload additional questions and answers. New Q and A start at question and answer number 63. There are some questions that are still being answered and those will be answered in a subsequent amendment. See the attachment titled CE BUMP III Q and A 09 June 2023.

Procurement Integrated Enterprise Environment (PIEE) Solicitation Module link:  https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=FA910123RB007

Per Section L-2.3 Proposal Organization the Government requires proposal submissions be conducted via the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module, https://piee.eb.mil. No other proposal submission method is authorized.To initiate the proposal submission through PIEE, the Offeror must register as a proposal manager. Training on the solicitation module is available for proposal managers through PIEE. Subcontractors who have proprietary data and do not want to submit this data to the prime must submit it through PIEE. Subcontractors will register as a proposal manager and create a separate proposal submission from the Prime. Documents submitted by the Subcontractor directly to the Government must have the Prime Contractors team name and RFP number on the first page of the document. Pre-coordination is critical to submission of a complete and timely proposal.

Amendment 0003: The purpose of amendment 0003 is to provide the following:

1) Provide questions and answers. Please see the attached.

2) Provide the A6 SHE standards, APTU CO2 Photos 1 IRA-6867, and APTU CO2 Photos 2 IRA-6884. Please see the attached.

3) Provide the site visit roster. Please see the attached.

Please confirm receipt of amendment 0003 in writing. If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil.

Amendment 0002: The purpose of this Amendment is to

1) Incorporate Attachment 13 Questions and Answers related to the site visit and questions concerning clarifications to the Governments requirement.

2)  At present, the Government is reviewing an additional 50 questions (approximately) and will provide answers as soon as possible.

3) Please confirm receipt of this Amendment 0002 in writing.

4) If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil. Please see the attached.

Amendment 01: The purpose of amendment 01 is to clarify information found in FAR 52.237-27 and provide clarification on site visit information from the solicitation in the description of the sam.gov posting, add more information pertaining to the site visit, and to add a secondary point of contact.

It is the Governments intention to bring more attention to the requirements, time, and date of the site visit. The CE BUMP III site visit will be held on Monday, 22 May 2023 at 9:00 AM CDT (Ref: 52.236-27, Site Visit (Construction) - Alternate 1). Participants will meet at Pass and Registration, Main Gate, Building 111, Arnold AFB, Tennessee. Please arrive at least 3 Hours prior to the scheduled visit to allow the processing of visitors badges. A Government representative will provide further guidance upon arrival. Hard hats, safety glasses, and safety shoes are required for the site visit. Contractors are responsible for bringing their own personal protective equipment. All prospective Offerors are highly encouraged to attend this site visit and are advised that this will be held solely for the purpose of explaining the concepts involved in the Seed Project and the specifications, terms, and conditions of this solicitation. If attending, provide the full name of attendee(s), company name, citizenship, and telephone numbers to James B. Laney, Contract Specialist, at james.laney.3@us.af.mil and Robert A. Greene, Contracting Officer at robert.greene.17@us.af.mil no later than 18 May 2023.This is an request for proposal for the Civil Engineering Building and Utilities Mechanical Program III (CE BUMP III) at Arnold AFB. Please see ALL attachments for details and instructions.

Update #7 ·

Amendment 0005: The purpose this amendment is to:

a) Incorporate the clause at FAR 52.204-27, Prohibition on a ByteDance Covered Application into this solicitation. 

b) Incorporate additional questions and answers.  Please see the attached questions and answers dated 15 June 2023.

Amendment 0004: The purpose this amendment is to:

a) Extend the proposal due date from 13 June 2023 at 2:00 pm central daylight time to 20 June 2023 2:00 pm central daylight time.

b) Upload additional questions and answers. New Q&A start at question and answer number 63. There are some questions that are still being answered and those will be answered in a subsequent amendment. See the attachment titled "CE BUMP III Q and A 09 June 2023".

Procurement Integrated Enterprise Environment (PIEE) Solicitation Module link:  https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=FA910123RB007

Per Section L-2.3 Proposal Organization the Government requires proposal submissions be conducted via the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module, https://piee.eb.mil. No other proposal submission method is authorized.To initiate the proposal submission through PIEE, the Offeror must register as a proposal manager. Training on the solicitation module is available for proposal managers through PIEE. Subcontractors who have proprietary data and do not want to submit this data to the prime must submit it through PIEE. Subcontractors will register as a proposal manager and create a separate proposal submission from the Prime. Documents submitted by the Subcontractor directly to the Government must have the Prime Contractors team name and RFP number on the first page of the document. Pre-coordination is critical to submission of a complete and timely proposal.

Amendment 0003: The purpose of amendment 0003 is to provide the following:

1) Provide questions and answers. Please see the attached.

2) Provide the A6 SHE standards, APTU CO2 Photos 1 IRA-6867, and APTU CO2 Photos 2 IRA-6884. Please see the attached.

3) Provide the site visit roster. Please see the attached.

Please confirm receipt of amendment 0003 in writing. If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil.

Amendment 0002: The purpose of this Amendment is to

1) Incorporate Attachment 13 Questions and Answers related to the site visit and questions concerning clarifications to the Governments requirement.

2)  At present, the Government is reviewing an additional 50 questions (approximately) and will provide answers as soon as possible.

3) Please confirm receipt of this Amendment 0002 in writing.

4) If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil. Please see the attached.

Amendment 01: The purpose of amendment 01 is to clarify information found in FAR 52.237-27 and provide clarification on site visit information from the solicitation in the description of the sam.gov posting, add more information pertaining to the site visit, and to add a secondary point of contact.

It is the Governments intention to bring more attention to the requirements, time, and date of the site visit. The CE BUMP III site visit will be held on Monday, 22 May 2023 at 9:00 AM CDT (Ref: 52.236-27, Site Visit (Construction) - Alternate 1). Participants will meet at Pass and Registration, Main Gate, Building 111, Arnold AFB, Tennessee. Please arrive at least 3 Hours prior to the scheduled visit to allow the processing of visitors badges. A Government representative will provide further guidance upon arrival. Hard hats, safety glasses, and safety shoes are required for the site visit. Contractors are responsible for bringing their own personal protective equipment. All prospective Offerors are highly encouraged to attend this site visit and are advised that this will be held solely for the purpose of explaining the concepts involved in the Seed Project and the specifications, terms, and conditions of this solicitation. If attending, provide the full name of attendee(s), company name, citizenship, and telephone numbers to James B. Laney, Contract Specialist, at james.laney.3@us.af.mil and Robert A. Greene, Contracting Officer at robert.greene.17@us.af.mil no later than 18 May 2023.This is an request for proposal for the Civil Engineering Building and Utilities Mechanical Program III (CE BUMP III) at Arnold AFB. Please see ALL attachments for details and instructions.

Update #6 ·

Amendment 0004: The purpose this amendment is to:

a) Extend the proposal due date from 13 June 2023 at 2:00 pm central daylight time to 20 June 2023 2:00 pm central daylight time.

b) Upload additional questions and answers. New Q&A start at question and answer number 63. There are some questions that are still being answered and those will be answered in a subsequent amendment. See the attachment titled "CE BUMP III Q and A 09 June 2023".

Procurement Integrated Enterprise Environment (PIEE) Solicitation Module link:  https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=FA910123RB007

Per Section L-2.3 Proposal Organization the Government requires proposal submissions be conducted via the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module, https://piee.eb.mil. No other proposal submission method is authorized.To initiate the proposal submission through PIEE, the Offeror must register as a proposal manager. Training on the solicitation module is available for proposal managers through PIEE. Subcontractors who have proprietary data and do not want to submit this data to the prime must submit it through PIEE. Subcontractors will register as a proposal manager and create a separate proposal submission from the Prime. Documents submitted by the Subcontractor directly to the Government must have the Prime Contractors team name and RFP number on the first page of the document. Pre-coordination is critical to submission of a complete and timely proposal.

Amendment 0003: The purpose of amendment 0003 is to provide the following:

1) Provide questions and answers. Please see the attached.

2) Provide the A6 SHE standards, APTU CO2 Photos 1 IRA-6867, and APTU CO2 Photos 2 IRA-6884. Please see the attached.

3) Provide the site visit roster. Please see the attached.

Please confirm receipt of amendment 0003 in writing. If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil.

Amendment 0002: The purpose of this Amendment is to

1) Incorporate Attachment 13 Questions and Answers related to the site visit and questions concerning clarifications to the Governments requirement.

2)  At present, the Government is reviewing an additional 50 questions (approximately) and will provide answers as soon as possible.

3) Please confirm receipt of this Amendment 0002 in writing.

4) If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil. Please see the attached.

Amendment 01: The purpose of amendment 01 is to clarify information found in FAR 52.237-27 and provide clarification on site visit information from the solicitation in the description of the sam.gov posting, add more information pertaining to the site visit, and to add a secondary point of contact.

It is the Governments intention to bring more attention to the requirements, time, and date of the site visit. The CE BUMP III site visit will be held on Monday, 22 May 2023 at 9:00 AM CDT (Ref: 52.236-27, Site Visit (Construction) - Alternate 1). Participants will meet at Pass and Registration, Main Gate, Building 111, Arnold AFB, Tennessee. Please arrive at least 3 Hours prior to the scheduled visit to allow the processing of visitors badges. A Government representative will provide further guidance upon arrival. Hard hats, safety glasses, and safety shoes are required for the site visit. Contractors are responsible for bringing their own personal protective equipment. All prospective Offerors are highly encouraged to attend this site visit and are advised that this will be held solely for the purpose of explaining the concepts involved in the Seed Project and the specifications, terms, and conditions of this solicitation. If attending, provide the full name of attendee(s), company name, citizenship, and telephone numbers to James B. Laney, Contract Specialist, at james.laney.3@us.af.mil and Robert A. Greene, Contracting Officer at robert.greene.17@us.af.mil no later than 18 May 2023.This is an request for proposal for the Civil Engineering Building and Utilities Mechanical Program III (CE BUMP III) at Arnold AFB. Please see ALL attachments for details and instructions.

Update #5 ·

Procurement Integrated Enterprise Environment (PIEE) Solicitation Module link:  https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=FA910123RB007

Per Section L-2.3 Proposal Organization the Government requires proposal submissions be conducted via the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module, https://piee.eb.mil. No other proposal submission method is authorized.To initiate the proposal submission through PIEE, the Offeror must register as a proposal manager. Training on the solicitation module is available for proposal managers through PIEE. Subcontractors who have proprietary data and do not want to submit this data to the prime must submit it through PIEE. Subcontractors will register as a proposal manager and create a separate proposal submission from the Prime. Documents submitted by the Subcontractor directly to the Government must have the Prime Contractors team name and RFP number on the first page of the document. Pre-coordination is critical to submission of a complete and timely proposal.

Amendment 03: The purpose of amendment 0003 is to provide the following:

1) Provide questions and answers. Please see the attached.

2) Provide the A6 SHE standards, APTU CO2 Photos 1 IRA-6867, and APTU CO2 Photos 2 IRA-6884. Please see the attached.

3) Provide the site visit roster. Please see the attached.

Please confirm receipt of amendment 0003 in writing. If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil.

Amendment 02: The purpose of this Amendment is to

1) Incorporate Attachment 13 Questions and Answers related to the site visit and questions concerning clarifications to the Governments requirement.

2)  At present, the Government is reviewing an additional 50 questions (approximately) and will provide answers as soon as possible.

3) Please confirm receipt of this Amendment 0002 in writing.

4) If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil. Please see the attached.

Amendment 01: The purpose of amendment 01 is to clarify information found in FAR 52.237-27 and provide clarification on site visit information from the solicitation in the description of the sam.gov posting, add more information pertaining to the site visit, and to add a secondary point of contact.

It is the Governments intention to bring more attention to the requirements, time, and date of the site visit. The CE BUMP III site visit will be held on Monday, 22 May 2023 at 9:00 AM CDT (Ref: 52.236-27, Site Visit (Construction) - Alternate 1). Participants will meet at Pass and Registration, Main Gate, Building 111, Arnold AFB, Tennessee. Please arrive at least 3 Hours prior to the scheduled visit to allow the processing of visitors badges. A Government representative will provide further guidance upon arrival. Hard hats, safety glasses, and safety shoes are required for the site visit. Contractors are responsible for bringing their own personal protective equipment. All prospective Offerors are highly encouraged to attend this site visit and are advised that this will be held solely for the purpose of explaining the concepts involved in the Seed Project and the specifications, terms, and conditions of this solicitation. If attending, provide the full name of attendee(s), company name, citizenship, and telephone numbers to James B. Laney, Contract Specialist, at james.laney.3@us.af.mil and Robert A. Greene, Contracting Officer at robert.greene.17@us.af.mil no later than 18 May 2023.This is an request for proposal for the Civil Engineering Building and Utilities Mechanical Program III (CE BUMP III) at Arnold AFB. Please see ALL attachments for details and instructions.

Update #4 ·

Amendment 03:  

The purpose of amendment 0003 is to provide the following:

1) Provide questions and answers.  Please see the attached. 

2) Provide the A6 SHE standards, APTU CO2 Photos 1 IRA-6867, and APTU CO2 Photos 2 IRA-6884.  Please see the attached.

3) Provide the site visit roster.  Please see the attached.

Please confirm receipt of amendment 0003 in writing.  If you have any questions, please contact  Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil.

Amendment 02:  The purpose of this Amendment is to incorporate Attachment 13 "Questions and Answers" related to the site visit and questions concerning clarifications to the Government's requirement. 2. At present, the Government is reviewing an additional 50 questions (approximately) and will provide answers as soon as possible. 3. Please confirm receipt of this Amendment 0002 in writing. 4. If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil.  Please see the attached. 

Amendment 01:  The purpose of amendment 01 is to clarify information found in FAR 52.237-27 and provide clarification on site visit information from the solicitation in the description of the sam.gov posting, add more information pertaining to the site visit, and to add a secondary point of contact.   It is the Government's intention to bring more attention to the requirements, time, and date of the site visit.       

The CE BUMP III site visit will be held on Monday, 22 May 2023 at 9:00 AM CDT (Ref: 52.236-27, Site Visit (Construction) - Alternate 1). Participants will meet at Pass and Registration, Main Gate, Building 111, Arnold AFB, Tennessee. Please arrive at least 3 Hours prior to the scheduled visit to allow the processing of visitors badges. A Government representative will provide further guidance upon arrival. Hard hats, safety glasses, and safety shoes are required for the site visit. Contractors are responsible for bringing their own personal protective equipment. All prospective Offerors are highly encouraged to attend this site visit and are advised that this will be held solely for the purpose of explaining the concepts involved in the Seed Project and the specifications, terms, and conditions of this solicitation. If attending, provide the full name of attendee(s), company name, citizenship, and telephone numbers to James B. Laney, Contract Specialist, at james.laney.3@us.af.mil and Robert A. Greene, Contracting Officer at robert.greene.17@us.af.mil no later than 18 May 2023.

This is an request for proposal for the Civil Engineering Building and Utilities Mechanical Program III (CE BUMP III) at Arnold AFB.  Please see ALL attachments for details and instructions.  

Update #3 ·

Amendment 02:  The purpose of this Amendment is to incorporate Attachment 13 "Questions and Answers" related to the site visit and questions concerning clarifications to the Government's requirement. 2. At present, the Government is reviewing an additional 50 questions (approximately) and will provide answers as soon as possible. 3. Please confirm receipt of this Amendment 0002 in writing. 4. If you have any questions, please contact Contract Specialist Mr. James B. Laney at james.laney.3@us.af.mil and Contracting Officer Mr. Robert A. Greene at robert.greene.17@us.af.mil.  Please see the attached. 

Amendment 01:  The purpose of amendment 01 is to clarify information found in FAR 52.237-27 and provide clarification on site visit information from the solicitation in the description of the sam.gov posting, add more information pertaining to the site visit, and to add a secondary point of contact.   It is the Government's intention to bring more attention to the requirements, time, and date of the site visit.       

The CE BUMP III site visit will be held on Monday, 22 May 2023 at 9:00 AM CDT (Ref: 52.236-27, Site Visit (Construction) - Alternate 1). Participants will meet at Pass and Registration, Main Gate, Building 111, Arnold AFB, Tennessee. Please arrive at least 3 Hours prior to the scheduled visit to allow the processing of visitors badges. A Government representative will provide further guidance upon arrival. Hard hats, safety glasses, and safety shoes are required for the site visit. Contractors are responsible for bringing their own personal protective equipment. All prospective Offerors are highly encouraged to attend this site visit and are advised that this will be held solely for the purpose of explaining the concepts involved in the Seed Project and the specifications, terms, and conditions of this solicitation. If attending, provide the full name of attendee(s), company name, citizenship, and telephone numbers to James B. Laney, Contract Specialist, at james.laney.3@us.af.mil and Robert A. Greene, Contracting Officer at robert.greene.17@us.af.mil no later than 18 May 2023.

This is an request for proposal for the Civil Engineering Building and Utilities Mechanical Program III (CE BUMP III) at Arnold AFB.  Please see ALL attachments for details and instructions.  

Update #2 ·

Amendment 01:  The purpose of amendment 01 is to clarify information found in FAR 52.237-27 and provide clarification on site visit information from the solicitation in the description of the sam.gov posting, add more information pertaining to the site visit, and to add a secondary point of contact.   It is the Government's intention to bring more attention to the requirements, time, and date of the site visit.       

The CE BUMP III site visit will be held on Monday, 22 May 2023 at 9:00 AM CDT (Ref: 52.236-27, Site Visit (Construction) - Alternate 1). Participants will meet at Pass and Registration, Main Gate, Building 111, Arnold AFB, Tennessee. Please arrive at least 3 Hours prior to the scheduled visit to allow the processing of visitors badges. A Government representative will provide further guidance upon arrival. Hard hats, safety glasses, and safety shoes are required for the site visit. Contractors are responsible for bringing their own personal protective equipment. All prospective Offerors are highly encouraged to attend this site visit and are advised that this will be held solely for the purpose of explaining the concepts involved in the Seed Project and the specifications, terms, and conditions of this solicitation. If attending, provide the full name of attendee(s), company name, citizenship, and telephone numbers to James B. Laney, Contract Specialist, at james.laney.3@us.af.mil and Robert A. Greene, Contracting Officer at robert.greene.17@us.af.mil no later than 18 May 2023.

This is an request for proposal for the Civil Engineering Building and Utilities Mechanical Program III (CE BUMP III) at Arnold AFB.  Please see ALL attachments for details and instructions.  

Update #1 ·

This is an request for proposal for the Civil Engineering Building and Utilities Mechanical Program III (CE BUMP III) at Arnold AFB.  Please see ALL attachments for details and instructions.  

Files

Show all 25

Notice history

6 of 7 notices listed here. See the rest on GovTribe.

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity