About this opportunity

The U.S. Army Corps of Engineers Engineering District Portland is soliciting offers for the Bonneville Lock and Dam Navigation Lock 1 Bridge Replacement under solicitation W9127N26BA024, with offers due October 29, 2026, as extended by Amendment 0005. The set-aside is Total Small Business, and the W071 ENDIST Portland KO Contracting Division is administering the fixed-price construction contract.

Work is performed at Bonneville Lock and Dam in Cascade Locks, Oregon 97014. The scope replaces the existing bridge with a single-span steel girder bridge with a concrete deck, 34'4" out-to-out, with two 11'0" travel lanes, two 2'0" shoulders, a 5'0" sidewalk, and four built-up steel plate girders. The new bridge sits on an alignment immediately downstream and must fit between the existing bridge and a Bonneville Power Administration transmission tower. The north abutment is a concrete stub with spread footing anchored into rock, and the south abutment is supported by drilled shafts. Partial demolition mitigates seismic hazards, and lead and asbestos removal is required.

Construction is phased to keep critical vehicular access open throughout the project, and two-lane access across the navigation channel must be maintained. Under Amendment 0007, full or partial closures require 48 hours' Government approval notice, and barge crane lifts occur near a high-voltage power line. In-water work is limited to the 2029 and 2030 work window years under Incidental Harassment Authorization marine mammal protections, and no IHA-governed in-water work is allowed beyond the permitted years. The contract performance period is 1,295 calendar days from Notice to Proceed, superseding the original 930 days.

Ground anchor and jet grouting work require pre-qualification before performance. Ground anchor qualifications require three years of permanent installation experience, and jet grouting requires three years of experience with at least 5,000 cubic yards in gridded treatment patterns and five years of personnel experience. Field testing and concrete work must comply with the Oregon Department of Transportation Manual of Field Test Procedures. Contractors must populate an IL-4 Construction Management Platform within seven calendar days of Notice to Proceed and keep user logins active at least every 35 days.

The Government estimate is $25.7 million across six mandatory CLINs, with structural work the largest at $18.8 million. The Standard Form 1419 abstract attached to the notice lists six offers, including Northbank Civil and Marine, LLC at $18.75 million, Derian, Inc at $25.47 million, Stellar J Corporation at $25.01 million, and Xenturis, LLC at $25.7 million. Two offers submitted no bids.

Notice text

8 versions

Update #8 · Latest ·

*** 20 October 2026 - Amendment W9127N26BA0240006 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment affects changes to the Block 14 (Description of Amendment/Modification):

CHANGE IN SOLICITATION SPECIFICATIONS:

Solicitation Specifications, Section 01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS

Paragraph 1.18.4 Traffic Control Plan (TCP) edited.

CHANGE IN SOLICITATION ATTACHMENTS:

Attachment A16 BN NL Bridge As Builts_combined drawings edited.

                                                       (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 14 October 2026 - Amendment W9127N26BA0240006 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment affects changes to the Block 14 (Description of Amendment/Modification):

Solicitation Specifications, Section 01 45 00.00 25 QUALITY CONTROL

Paragraph 3.8.1 GOVERNING FIELD TESTING STANDARDS AND FREQUENCIES added.

Solicitation Specifications, Section 03 30 00.00 99 CAST-IN-PLACE REINFORCED CONCRETE

Paragraph 3.13.1 GENERAL added.

Remove drawing C-104 and replace with C-104 - MARK 1 - AMD-0006 – UPDATE TO DEMOLITION NOTES.

Remove drawing C-106 and replace with C-106 - MARK 1 - AMD-0006 – UPDATE TO PAVING AREA AND NOTES, MARK 2 - AMD-0006 – UPDATE TO DEFINE FENCING AND GATE.

Remove drawing C-102 and replace with C-102 – MARK 1 - AMD-0006 – UPDATE TO DEMOLITION NOTES.

                                                       (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 01 October 2026 - Amendment W9127N26BA0240005 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification):

The Solicitation Period is extended by 21 calendar days which changes the Solicitation Closing Date from October 8, 2026, to October 29, 2026.

Solicitation Specifications, Section 01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS, Paragraph 1.18.4 Traffic Control Plan (TCP) edited.

Solicitation Specifications, Section 01 45 00.25 25 CONSTRUCTION MANAGEMENT PLATFORM (CMP), Technical Section added in its entirety.

                                                             (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 18 September 2026 - Amendment W9127N26BA0240004 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification):

Solicitation Specifications, Section 31 68 13.00 99 – GROUND ANCHORS, Part 1 GENERAL, Paragraph 1.5.2 Qualifications are changed as detailed in the SUMMARY OF CHANGES.

Solicitation Specifications, Section 31 73 20.00 99 – JET GROUTING, Part 1 GENERAL, Paragraph 1.7.1 Qualifications are changed as detailed in the SUMMARY OF CHANGES.

Solicitation Specifications, Section 00 73 00 – Supplementary Conditions, Paragraph L. - COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984), the Period of Performance is amended as detailed in the SUMMARY OF CHANGES. 

This will allow for work to occur during the 2029 and 2030 In Water Work Window years. Environmental permits remain unchanged by this amendment. Marine Mammal protections as listed in the specification, and as governed by the IHA, included with the Attachments, remain in effect for the permitted years. No in water work, that is governed by IHA, will be allowed beyond the IHA permit years allowed.

                                                            (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 09 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification): Solicitation Specifications, Section 01 57 19.00 25 - TEMPORARY ENVIRONMENTAL CONTROLS, Part 3 EXECUTION, Paragraph 3.4.3 PROFESSIONAL ARCHAEOLOGICAL MONITOR.

                                                            (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 03 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment effects changes to block 13 of Standard Form 1442, the Solicitation Specifications, Section 00 21 13 – Instruction to Bidders, and Section 00 21 00 – Instructions.  Additionally, it extends the solicitation period and provides for an additional site visit.

The Solicitation Period is extended by 20 calendar days which changes the Solicitation Closing Date from September 18, 2026, to October 8, 2026.

Site Visit Registration. Send an email to Michael R. Carl via email at michael.r.carl@usace.army.mil and Courney R. Hollins at courtney.r.hollins@usace.army.mil by COB Wednesday, 09 September 2026, to register for the site visit and provide first name, last name, and company/organization name. Site visit attendees must be U.S. citizens and possess a REAL ID to access the site.

Acceptable forms of proof of citizenship for anyone born outside the USA are:

US Birth Certificate: Must be certified & issued by either a US State or the US State Department.

US Passport Undamaged: Issued by the US Dept of State, without limitation, does not need to be current, is/was valid for 10 years for adults and 5 years for children under 16.

US Passport Card Undamaged: Issued by the US Dept of State, without limitation, does not need to be current.

US Certificate of Citizenship: Issued by US Citizenship and Immigration Service.

Consular Report of Birth Abroad: Issued by the US State Department.

US Naturalization Certificate: Issued by US Citizenship and Immigration Service.

Enhanced Driver’s License: from Michigan, Minnesota, New York, Vermont, or Washington.

Acceptable ID:

Real ID driver’s license.

Enhanced driver’s license.

Federal Identification Cards PIC/CAC/PIV/Etc.

Transportation Worker Identification Card (TWIC).

United States Passport or United States Passport Card.

Driver’s license issued by the Department of State.

*** 27 August 2026 - Amendment W9127N26BA0240001 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment inserts additional Government Furnished Information (GFI) as an attachment to the solicitation.  The file “Power Line Layout” is provided for the Contractor’s information.  The Government shall not be responsible for any interpretation of, or conclusion drawn, from the data or information by the Contractor.  Information provided should be field verified by the Contractor.  If there is a discrepancy between the solicitation plan set and the GFI, the solicitation plan set takes precedence.

The project consists of replacing the existing bridge with a new fixed bridge on a new alignment and to provide for partial demolition of the existing bridge.


The new fixed bridge will be a single-span steel girder bridge with a concrete deck. The bridge width will be 34’4½” out-to-out, with two 11’0” travel lanes, two 2’0” shoulders, a 5’0” sidewalk, and the superstructure will consist of four (4) built-up steel plate girders. The replacement bridge alignment is located immediately downstream of the existing bridge and, at its northern terminus, will fit entirely between the existing bridge and the Bonneville Power Administration transmission tower which is located to the south. Approach roadways will also be constructed to tie into the existing roadway alignment. The new fixed bridge will be located over the existing navigation channel and will provide an under clearance that is larger than is currently present under the existing bridge. The north abutment will be a concrete stub abutment with spread footing anchored into rock. The south abutment will be a concrete abutment that is supported by drilled shafts. To mitigate seismic hazards, portions of the existing bridge will be removed as part of the bridge construction requirement. The existing bridge provides for critical vehicular access to the Bonneville project that must remain open for the entirety of the construction project. This will likely require the contractor to construct the project in phases. In
addition, lead and asbestos removal will be required as part of this requirement. Working within environmental and seasonal restrictions and barge crane lifting will be required in close proximity to a high voltage power line will also be necessary during performance of the required work.

Update #7 ·

*** 14 October 2026 - Amendment W9127N26BA0240006 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment affects changes to the Block 14 (Description of Amendment/Modification):

Solicitation Specifications, Section 01 45 00.00 25 QUALITY CONTROL

Paragraph 3.8.1 GOVERNING FIELD TESTING STANDARDS AND FREQUENCIES added.

Solicitation Specifications, Section 03 30 00.00 99 CAST-IN-PLACE REINFORCED CONCRETE

Paragraph 3.13.1 GENERAL added.

Remove drawing C-104 and replace with C-104 - MARK 1 - AMD-0006 – UPDATE TO DEMOLITION NOTES.

Remove drawing C-106 and replace with C-106 - MARK 1 - AMD-0006 – UPDATE TO PAVING AREA AND NOTES, MARK 2 - AMD-0006 – UPDATE TO DEFINE FENCING AND GATE.

Remove drawing C-102 and replace with C-102 – MARK 1 - AMD-0006 – UPDATE TO DEMOLITION NOTES.

                                                       (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 01 October 2026 - Amendment W9127N26BA0240005 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification):

The Solicitation Period is extended by 21 calendar days which changes the Solicitation Closing Date from October 8, 2026, to October 29, 2026.

Solicitation Specifications, Section 01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS, Paragraph 1.18.4 Traffic Control Plan (TCP) edited.

Solicitation Specifications, Section 01 45 00.25 25 CONSTRUCTION MANAGEMENT PLATFORM (CMP), Technical Section added in its entirety.

                                                             (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 18 September 2026 - Amendment W9127N26BA0240004 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification):

Solicitation Specifications, Section 31 68 13.00 99 – GROUND ANCHORS, Part 1 GENERAL, Paragraph 1.5.2 Qualifications are changed as detailed in the SUMMARY OF CHANGES.

Solicitation Specifications, Section 31 73 20.00 99 – JET GROUTING, Part 1 GENERAL, Paragraph 1.7.1 Qualifications are changed as detailed in the SUMMARY OF CHANGES.

Solicitation Specifications, Section 00 73 00 – Supplementary Conditions, Paragraph L. - COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984), the Period of Performance is amended as detailed in the SUMMARY OF CHANGES. 

This will allow for work to occur during the 2029 and 2030 In Water Work Window years. Environmental permits remain unchanged by this amendment. Marine Mammal protections as listed in the specification, and as governed by the IHA, included with the Attachments, remain in effect for the permitted years. No in water work, that is governed by IHA, will be allowed beyond the IHA permit years allowed.

                                                            (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 09 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification): Solicitation Specifications, Section 01 57 19.00 25 - TEMPORARY ENVIRONMENTAL CONTROLS, Part 3 EXECUTION, Paragraph 3.4.3 PROFESSIONAL ARCHAEOLOGICAL MONITOR.

                                                            (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 03 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment effects changes to block 13 of Standard Form 1442, the Solicitation Specifications, Section 00 21 13 – Instruction to Bidders, and Section 00 21 00 – Instructions.  Additionally, it extends the solicitation period and provides for an additional site visit.

The Solicitation Period is extended by 20 calendar days which changes the Solicitation Closing Date from September 18, 2026, to October 8, 2026.

Site Visit Registration. Send an email to Michael R. Carl via email at michael.r.carl@usace.army.mil and Courney R. Hollins at courtney.r.hollins@usace.army.mil by COB Wednesday, 09 September 2026, to register for the site visit and provide first name, last name, and company/organization name. Site visit attendees must be U.S. citizens and possess a REAL ID to access the site.

Acceptable forms of proof of citizenship for anyone born outside the USA are:

US Birth Certificate: Must be certified & issued by either a US State or the US State Department.

US Passport Undamaged: Issued by the US Dept of State, without limitation, does not need to be current, is/was valid for 10 years for adults and 5 years for children under 16.

US Passport Card Undamaged: Issued by the US Dept of State, without limitation, does not need to be current.

US Certificate of Citizenship: Issued by US Citizenship and Immigration Service.

Consular Report of Birth Abroad: Issued by the US State Department.

US Naturalization Certificate: Issued by US Citizenship and Immigration Service.

Enhanced Driver’s License: from Michigan, Minnesota, New York, Vermont, or Washington.

Acceptable ID:

Real ID driver’s license.

Enhanced driver’s license.

Federal Identification Cards PIC/CAC/PIV/Etc.

Transportation Worker Identification Card (TWIC).

United States Passport or United States Passport Card.

Driver’s license issued by the Department of State.

*** 27 August 2026 - Amendment W9127N26BA0240001 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment inserts additional Government Furnished Information (GFI) as an attachment to the solicitation.  The file “Power Line Layout” is provided for the Contractor’s information.  The Government shall not be responsible for any interpretation of, or conclusion drawn, from the data or information by the Contractor.  Information provided should be field verified by the Contractor.  If there is a discrepancy between the solicitation plan set and the GFI, the solicitation plan set takes precedence.

The project consists of replacing the existing bridge with a new fixed bridge on a new alignment and to provide for partial demolition of the existing bridge.


The new fixed bridge will be a single-span steel girder bridge with a concrete deck. The bridge width will be 34’4½” out-to-out, with two 11’0” travel lanes, two 2’0” shoulders, a 5’0” sidewalk, and the superstructure will consist of four (4) built-up steel plate girders. The replacement bridge alignment is located immediately downstream of the existing bridge and, at its northern terminus, will fit entirely between the existing bridge and the Bonneville Power Administration transmission tower which is located to the south. Approach roadways will also be constructed to tie into the existing roadway alignment. The new fixed bridge will be located over the existing navigation channel and will provide an under clearance that is larger than is currently present under the existing bridge. The north abutment will be a concrete stub abutment with spread footing anchored into rock. The south abutment will be a concrete abutment that is supported by drilled shafts. To mitigate seismic hazards, portions of the existing bridge will be removed as part of the bridge construction requirement. The existing bridge provides for critical vehicular access to the Bonneville project that must remain open for the entirety of the construction project. This will likely require the contractor to construct the project in phases. In
addition, lead and asbestos removal will be required as part of this requirement. Working within environmental and seasonal restrictions and barge crane lifting will be required in close proximity to a high voltage power line will also be necessary during performance of the required work.

Update #6 ·

*** 01 October 2026 - Amendment W9127N26BA0240005 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification):

The Solicitation Period is extended by 21 calendar days which changes the Solicitation Closing Date from October 8, 2026, to October 29, 2026.

Solicitation Specifications, Section 01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS, Paragraph 1.18.4 Traffic Control Plan (TCP) edited.

Solicitation Specifications, Section 01 45 00.25 25 CONSTRUCTION MANAGEMENT PLATFORM (CMP), Technical Section added in its entirety.

                                                             (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 18 September 2026 - Amendment W9127N26BA0240004 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification):

Solicitation Specifications, Section 31 68 13.00 99 – GROUND ANCHORS, Part 1 GENERAL, Paragraph 1.5.2 Qualifications are changed as detailed in the SUMMARY OF CHANGES.

Solicitation Specifications, Section 31 73 20.00 99 – JET GROUTING, Part 1 GENERAL, Paragraph 1.7.1 Qualifications are changed as detailed in the SUMMARY OF CHANGES.

Solicitation Specifications, Section 00 73 00 – Supplementary Conditions, Paragraph L. - COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984), the Period of Performance is amended as detailed in the SUMMARY OF CHANGES. 

This will allow for work to occur during the 2029 and 2030 In Water Work Window years. Environmental permits remain unchanged by this amendment. Marine Mammal protections as listed in the specification, and as governed by the IHA, included with the Attachments, remain in effect for the permitted years. No in water work, that is governed by IHA, will be allowed beyond the IHA permit years allowed.

                                                            (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 09 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification): Solicitation Specifications, Section 01 57 19.00 25 - TEMPORARY ENVIRONMENTAL CONTROLS, Part 3 EXECUTION, Paragraph 3.4.3 PROFESSIONAL ARCHAEOLOGICAL MONITOR.

                                                            (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 03 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment effects changes to block 13 of Standard Form 1442, the Solicitation Specifications, Section 00 21 13 – Instruction to Bidders, and Section 00 21 00 – Instructions.  Additionally, it extends the solicitation period and provides for an additional site visit.

The Solicitation Period is extended by 20 calendar days which changes the Solicitation Closing Date from September 18, 2026, to October 8, 2026.

Site Visit Registration. Send an email to Michael R. Carl via email at michael.r.carl@usace.army.mil and Courney R. Hollins at courtney.r.hollins@usace.army.mil by COB Wednesday, 09 September 2026, to register for the site visit and provide first name, last name, and company/organization name. Site visit attendees must be U.S. citizens and possess a REAL ID to access the site.

Acceptable forms of proof of citizenship for anyone born outside the USA are:

US Birth Certificate: Must be certified & issued by either a US State or the US State Department.

US Passport Undamaged: Issued by the US Dept of State, without limitation, does not need to be current, is/was valid for 10 years for adults and 5 years for children under 16.

US Passport Card Undamaged: Issued by the US Dept of State, without limitation, does not need to be current.

US Certificate of Citizenship: Issued by US Citizenship and Immigration Service.

Consular Report of Birth Abroad: Issued by the US State Department.

US Naturalization Certificate: Issued by US Citizenship and Immigration Service.

Enhanced Driver’s License: from Michigan, Minnesota, New York, Vermont, or Washington.

Acceptable ID:

Real ID driver’s license.

Enhanced driver’s license.

Federal Identification Cards PIC/CAC/PIV/Etc.

Transportation Worker Identification Card (TWIC).

United States Passport or United States Passport Card.

Driver’s license issued by the Department of State.

*** 27 August 2026 - Amendment W9127N26BA0240001 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment inserts additional Government Furnished Information (GFI) as an attachment to the solicitation.  The file “Power Line Layout” is provided for the Contractor’s information.  The Government shall not be responsible for any interpretation of, or conclusion drawn, from the data or information by the Contractor.  Information provided should be field verified by the Contractor.  If there is a discrepancy between the solicitation plan set and the GFI, the solicitation plan set takes precedence.

The project consists of replacing the existing bridge with a new fixed bridge on a new alignment and to provide for partial demolition of the existing bridge.


The new fixed bridge will be a single-span steel girder bridge with a concrete deck. The bridge width will be 34’4½” out-to-out, with two 11’0” travel lanes, two 2’0” shoulders, a 5’0” sidewalk, and the superstructure will consist of four (4) built-up steel plate girders. The replacement bridge alignment is located immediately downstream of the existing bridge and, at its northern terminus, will fit entirely between the existing bridge and the Bonneville Power Administration transmission tower which is located to the south. Approach roadways will also be constructed to tie into the existing roadway alignment. The new fixed bridge will be located over the existing navigation channel and will provide an under clearance that is larger than is currently present under the existing bridge. The north abutment will be a concrete stub abutment with spread footing anchored into rock. The south abutment will be a concrete abutment that is supported by drilled shafts. To mitigate seismic hazards, portions of the existing bridge will be removed as part of the bridge construction requirement. The existing bridge provides for critical vehicular access to the Bonneville project that must remain open for the entirety of the construction project. This will likely require the contractor to construct the project in phases. In
addition, lead and asbestos removal will be required as part of this requirement. Working within environmental and seasonal restrictions and barge crane lifting will be required in close proximity to a high voltage power line will also be necessary during performance of the required work.

Update #5 ·

*** 18 September 2026 - Amendment W9127N26BA0240004 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification):

Solicitation Specifications, Section 31 68 13.00 99 – GROUND ANCHORS, Part 1 GENERAL, Paragraph 1.5.2 Qualifications are changed as detailed in the SUMMARY OF CHANGES.

Solicitation Specifications, Section 31 73 20.00 99 – JET GROUTING, Part 1 GENERAL, Paragraph 1.7.1 Qualifications are changed as detailed in the SUMMARY OF CHANGES.

Solicitation Specifications, Section 00 73 00 – Supplementary Conditions, Paragraph L. - COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984), the Period of Performance is amended as detailed in the SUMMARY OF CHANGES. 

This will allow for work to occur during the 2029 and 2030 In Water Work Window years. Environmental permits remain unchanged by this amendment. Marine Mammal protections as listed in the specification, and as governed by the IHA, included with the Attachments, remain in effect for the permitted years. No in water work, that is governed by IHA, will be allowed beyond the IHA permit years allowed.

                                                            (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 09 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement ***

This amendment effects changes to the Block 14 (Description of Amendment/Modification): Solicitation Specifications, Section 01 57 19.00 25 - TEMPORARY ENVIRONMENTAL CONTROLS, Part 3 EXECUTION, Paragraph 3.4.3 PROFESSIONAL ARCHAEOLOGICAL MONITOR.

                                                            (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 03 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment effects changes to block 13 of Standard Form 1442, the Solicitation Specifications, Section 00 21 13 – Instruction to Bidders, and Section 00 21 00 – Instructions.  Additionally, it extends the solicitation period and provides for an additional site visit.

The Solicitation Period is extended by 20 calendar days which changes the Solicitation Closing Date from September 18, 2026, to October 8, 2026.

Site Visit Registration. Send an email to Michael R. Carl via email at michael.r.carl@usace.army.mil and Courney R. Hollins at courtney.r.hollins@usace.army.mil by COB Wednesday, 09 September 2026, to register for the site visit and provide first name, last name, and company/organization name. Site visit attendees must be U.S. citizens and possess a REAL ID to access the site.

Acceptable forms of proof of citizenship for anyone born outside the USA are:

US Birth Certificate: Must be certified & issued by either a US State or the US State Department.

US Passport Undamaged: Issued by the US Dept of State, without limitation, does not need to be current, is/was valid for 10 years for adults and 5 years for children under 16.

US Passport Card Undamaged: Issued by the US Dept of State, without limitation, does not need to be current.

US Certificate of Citizenship: Issued by US Citizenship and Immigration Service.

Consular Report of Birth Abroad: Issued by the US State Department.

US Naturalization Certificate: Issued by US Citizenship and Immigration Service.

Enhanced Driver’s License: from Michigan, Minnesota, New York, Vermont, or Washington.

Acceptable ID:

Real ID driver’s license.

Enhanced driver’s license.

Federal Identification Cards PIC/CAC/PIV/Etc.

Transportation Worker Identification Card (TWIC).

United States Passport or United States Passport Card.

Driver’s license issued by the Department of State.

*** 27 August 2026 - Amendment W9127N26BA0240001 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment inserts additional Government Furnished Information (GFI) as an attachment to the solicitation.  The file “Power Line Layout” is provided for the Contractor’s information.  The Government shall not be responsible for any interpretation of, or conclusion drawn, from the data or information by the Contractor.  Information provided should be field verified by the Contractor.  If there is a discrepancy between the solicitation plan set and the GFI, the solicitation plan set takes precedence.

The project consists of replacing the existing bridge with a new fixed bridge on a new alignment and to provide for partial demolition of the existing bridge.


The new fixed bridge will be a single-span steel girder bridge with a concrete deck. The bridge width will be 34’4½” out-to-out, with two 11’0” travel lanes, two 2’0” shoulders, a 5’0” sidewalk, and the superstructure will consist of four (4) built-up steel plate girders. The replacement bridge alignment is located immediately downstream of the existing bridge and, at its northern terminus, will fit entirely between the existing bridge and the Bonneville Power Administration transmission tower which is located to the south. Approach roadways will also be constructed to tie into the existing roadway alignment. The new fixed bridge will be located over the existing navigation channel and will provide an under clearance that is larger than is currently present under the existing bridge. The north abutment will be a concrete stub abutment with spread footing anchored into rock. The south abutment will be a concrete abutment that is supported by drilled shafts. To mitigate seismic hazards, portions of the existing bridge will be removed as part of the bridge construction requirement. The existing bridge provides for critical vehicular access to the Bonneville project that must remain open for the entirety of the construction project. This will likely require the contractor to construct the project in phases. In
addition, lead and asbestos removal will be required as part of this requirement. Working within environmental and seasonal restrictions and barge crane lifting will be required in close proximity to a high voltage power line will also be necessary during performance of the required work.

Update #4 ·

*** 09 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment effects changes to the Block 14 (Description of Amendment/Modification): Solicitation Specifications, Section 01 57 19.00 25 - TEMPORARY ENVIRONMENTAL CONTROLS, Part 3 EXECUTION, Paragraph 3.4.3 PROFESSIONAL ARCHAEOLOGICAL MONITOR.

                                                            (SEE ATTACHED AMENDMENT FOR CHANGES)

*** 03 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment effects changes to block 13 of Standard Form 1442, the Solicitation Specifications, Section 00 21 13 – Instruction to Bidders, and Section 00 21 00 – Instructions.  Additionally, it extends the solicitation period and provides for an additional site visit.

The Solicitation Period is extended by 20 calendar days which changes the Solicitation Closing Date from September 18, 2026, to October 8, 2026.

Site Visit Registration. Send an email to Michael R. Carl via email at michael.r.carl@usace.army.mil and Courney R. Hollins at courtney.r.hollins@usace.army.mil by COB Wednesday, 09 September 2026, to register for the site visit and provide first name, last name, and company/organization name. Site visit attendees must be U.S. citizens and possess a REAL ID to access the site.

Acceptable forms of proof of citizenship for anyone born outside the USA are:

US Birth Certificate: Must be certified & issued by either a US State or the US State Department.

US Passport Undamaged: Issued by the US Dept of State, without limitation, does not need to be current, is/was valid for 10 years for adults and 5 years for children under 16.

US Passport Card Undamaged: Issued by the US Dept of State, without limitation, does not need to be current.

US Certificate of Citizenship: Issued by US Citizenship and Immigration Service.

Consular Report of Birth Abroad: Issued by the US State Department.

US Naturalization Certificate: Issued by US Citizenship and Immigration Service.

Enhanced Driver’s License: from Michigan, Minnesota, New York, Vermont, or Washington.

Acceptable ID:

Real ID driver’s license.

Enhanced driver’s license.

Federal Identification Cards PIC/CAC/PIV/Etc.

Transportation Worker Identification Card (TWIC).

United States Passport or United States Passport Card.

Driver’s license issued by the Department of State.

*** 27 August 2026 - Amendment W9127N26BA0240001 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment inserts additional Government Furnished Information (GFI) as an attachment to the solicitation.  The file “Power Line Layout” is provided for the Contractor’s information.  The Government shall not be responsible for any interpretation of, or conclusion drawn, from the data or information by the Contractor.  Information provided should be field verified by the Contractor.  If there is a discrepancy between the solicitation plan set and the GFI, the solicitation plan set takes precedence.

The project consists of replacing the existing bridge with a new fixed bridge on a new alignment and to provide for partial demolition of the existing bridge.


The new fixed bridge will be a single-span steel girder bridge with a concrete deck. The bridge width will be 34’4½” out-to-out, with two 11’0” travel lanes, two 2’0” shoulders, a 5’0” sidewalk, and the superstructure will consist of four (4) built-up steel plate girders. The replacement bridge alignment is located immediately downstream of the existing bridge and, at its northern terminus, will fit entirely between the existing bridge and the Bonneville Power Administration transmission tower which is located to the south. Approach roadways will also be constructed to tie into the existing roadway alignment. The new fixed bridge will be located over the existing navigation channel and will provide an under clearance that is larger than is currently present under the existing bridge. The north abutment will be a concrete stub abutment with spread footing anchored into rock. The south abutment will be a concrete abutment that is supported by drilled shafts. To mitigate seismic hazards, portions of the existing bridge will be removed as part of the bridge construction requirement. The existing bridge provides for critical vehicular access to the Bonneville project that must remain open for the entirety of the construction project. This will likely require the contractor to construct the project in phases. In
addition, lead and asbestos removal will be required as part of this requirement. Working within environmental and seasonal restrictions and barge crane lifting will be required in close proximity to a high voltage power line will also be necessary during performance of the required work.

Update #3 ·

*** 03 September 2026 - Amendment W9127N26BA0240002 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment effects changes to block 13 of Standard Form 1442, the Solicitation Specifications, Section 00 21 13 – Instruction to Bidders, and Section 00 21 00 – Instructions.  Additionally, it extends the solicitation period and provides for an additional site visit.

The Solicitation Period is extended by 20 calendar days which changes the Solicitation Closing Date from September 18, 2026, to October 8, 2026.

Site Visit Registration. Send an email to Michael R. Carl via email at michael.r.carl@usace.army.mil and Courney R. Hollins at courtney.r.hollins@usace.army.mil by COB Wednesday, 09 September 2026, to register for the site visit and provide first name, last name, and company/organization name. Site visit attendees must be U.S. citizens and possess a REAL ID to access the site.

Acceptable forms of proof of citizenship for anyone born outside the USA are:

US Birth Certificate: Must be certified & issued by either a US State or the US State Department.

US Passport Undamaged: Issued by the US Dept of State, without limitation, does not need to be current, is/was valid for 10 years for adults and 5 years for children under 16.

US Passport Card Undamaged: Issued by the US Dept of State, without limitation, does not need to be current.

US Certificate of Citizenship: Issued by US Citizenship and Immigration Service.

Consular Report of Birth Abroad: Issued by the US State Department.

US Naturalization Certificate: Issued by US Citizenship and Immigration Service.

Enhanced Driver’s License: from Michigan, Minnesota, New York, Vermont, or Washington.

Acceptable ID:

Real ID driver’s license.

Enhanced driver’s license.

Federal Identification Cards PIC/CAC/PIV/Etc.

Transportation Worker Identification Card (TWIC).

United States Passport or United States Passport Card.

Driver’s license issued by the Department of State.

*** 27 August 2026 - Amendment W9127N26BA0240001 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment inserts additional Government Furnished Information (GFI) as an attachment to the solicitation.  The file “Power Line Layout” is provided for the Contractor’s information.  The Government shall not be responsible for any interpretation of, or conclusion drawn, from the data or information by the Contractor.  Information provided should be field verified by the Contractor.  If there is a discrepancy between the solicitation plan set and the GFI, the solicitation plan set takes precedence.

The project consists of replacing the existing bridge with a new fixed bridge on a new alignment and to provide for partial demolition of the existing bridge.


The new fixed bridge will be a single-span steel girder bridge with a concrete deck. The bridge width will be 34’4½” out-to-out, with two 11’0” travel lanes, two 2’0” shoulders, a 5’0” sidewalk, and the superstructure will consist of four (4) built-up steel plate girders. The replacement bridge alignment is located immediately downstream of the existing bridge and, at its northern terminus, will fit entirely between the existing bridge and the Bonneville Power Administration transmission tower which is located to the south. Approach roadways will also be constructed to tie into the existing roadway alignment. The new fixed bridge will be located over the existing navigation channel and will provide an under clearance that is larger than is currently present under the existing bridge. The north abutment will be a concrete stub abutment with spread footing anchored into rock. The south abutment will be a concrete abutment that is supported by drilled shafts. To mitigate seismic hazards, portions of the existing bridge will be removed as part of the bridge construction requirement. The existing bridge provides for critical vehicular access to the Bonneville project that must remain open for the entirety of the construction project. This will likely require the contractor to construct the project in phases. In
addition, lead and asbestos removal will be required as part of this requirement. Working within environmental and seasonal restrictions and barge crane lifting will be required in close proximity to a high voltage power line will also be necessary during performance of the required work.

Update #2 ·

*** 27 August 2026 - Amendment W9127N26BA0240001 Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement***

This amendment inserts additional Government Furnished Information (GFI) as an attachment to the solicitation.  The file “Power Line Layout” is provided for the Contractor’s information.  The Government shall not be responsible for any interpretation of, or conclusion drawn, from the data or information by the Contractor.  Information provided should be field verified by the Contractor.  If there is a discrepancy between the solicitation plan set and the GFI, the solicitation plan set takes precedence.

The project consists of replacing the existing bridge with a new fixed bridge on a new alignment and to provide for partial demolition of the existing bridge.


The new fixed bridge will be a single-span steel girder bridge with a concrete deck. The bridge width will be 34’4½” out-to-out, with two 11’0” travel lanes, two 2’0” shoulders, a 5’0” sidewalk, and the superstructure will consist of four (4) built-up steel plate girders. The replacement bridge alignment is located immediately downstream of the existing bridge and, at its northern terminus, will fit entirely between the existing bridge and the Bonneville Power Administration transmission tower which is located to the south. Approach roadways will also be constructed to tie into the existing roadway alignment. The new fixed bridge will be located over the existing navigation channel and will provide an under clearance that is larger than is currently present under the existing bridge. The north abutment will be a concrete stub abutment with spread footing anchored into rock. The south abutment will be a concrete abutment that is supported by drilled shafts. To mitigate seismic hazards, portions of the existing bridge will be removed as part of the bridge construction requirement. The existing bridge provides for critical vehicular access to the Bonneville project that must remain open for the entirety of the construction project. This will likely require the contractor to construct the project in phases. In
addition, lead and asbestos removal will be required as part of this requirement. Working within environmental and seasonal restrictions and barge crane lifting will be required in close proximity to a high voltage power line will also be necessary during performance of the required work.

Update #1 ·

The project consists of replacing the existing bridge with a new fixed bridge on a new alignment and to provide for partial demolition of the existing bridge.


The new fixed bridge will be a single-span steel girder bridge with a concrete deck. The bridge width will be 34’4½” out-to-out, with two 11’0” travel lanes, two 2’0” shoulders, a 5’0” sidewalk, and the superstructure will consist of four (4) built-up steel plate girders. The replacement bridge alignment is located immediately downstream of the existing bridge and, at its northern terminus, will fit entirely between the existing bridge and the Bonneville Power Administration transmission tower which is located to the south. Approach roadways will also be constructed to tie into the existing roadway alignment. The new fixed bridge will be located over the existing navigation channel and will provide an under clearance that is larger than is currently present under the existing bridge. The north abutment will be a concrete stub abutment with spread footing anchored into rock. The south abutment will be a concrete abutment that is supported by drilled shafts. To mitigate seismic hazards, portions of the existing bridge will be removed as part of the bridge construction requirement. The existing bridge provides for critical vehicular access to the Bonneville project that must remain open for the entirety of the construction project. This will likely require the contractor to construct the project in phases. In
addition, lead and asbestos removal will be required as part of this requirement. Working within environmental and seasonal restrictions and barge crane lifting will be required in close proximity to a high voltage power line will also be necessary during performance of the required work.

Files

Show all 13

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Bonneville Lock and Dam - Navigation Lock 1 Bridge Replacement Pre-Solicitation
Bonneville Old Navigation Lock (NL1) Swing Bridge Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Bonneville Powerhouse II Unwatering Pump Replacement United States · NAICS 237990 ENDIST Portland Total Small Business
John day DAM navigation lock tainter valve (TV) repairs TV3 and TV4 Location and Access Details. Oregon Side Physical Access, Near Rufus, OR 97050 accessible via I-84, Exit 109. Washington Side (Closest Town), Goldendale, WA 98620 approximately 20 miles north across the river. River Location, Mile 216.6 on the Columbia River, joining Sherman County, Oregon, and Klickitat County, Washington. 98628 · NAICS 237990 ENDIST Portland No set-aside
W9127N27BA005 Foster Spillway Gate Nut Replacements and Re-Tensioning Foster Dam, Linn County, Oregon 93745 · NAICS 237990 ENDIST Portland Total Small Business
Navigation lock tainter valve (TV) repair, TV1 The Dalles Dam (Washington side), Lyle, WA 98635. 98635 · NAICS 237990 ENDIST Portland No set-aside
John day DAM unit 10 packing box replacement John Day Dam, Sherman County, Oregonthe John Day Dam On The Columbia River Between Sherman County, Oregon, And Klickitat County, Washington. Rufus, Oregon 97050, United States · NAICS 237990 ENDIST Portland No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors