AZ FLAP SR261(1), Eagar to Crescent Lake
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 6982AF22B000018
- Agency
- Federal Highway Administration Department of Transportation
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Springerville, Arizona 85938, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks bids for the rehabilitation of 11.4 miles of Arizona State Route 261 between Eagar and Crescent Lake. The project involves pulverization and paving of the existing roadway, installation of new culverts ranging from 24 to 48 inches in diameter, lining of large 60 to 66 inch culverts, and new guardrail. Significant quantities include 33,000 tons of asphalt, 11.42 miles of full depth reclamation, 1,000 cubic yards of riprap, 1,600 linear feet of pipe culvert, 600 linear feet of culvert lining, and 3,500 linear feet of guardrail. The Department of Transportation Federal Highway Administration issued the solicitation, with sealed bids due by January 5, 2023. Evaluation will be based on responsiveness, responsibility, and lowest price.
The solicitation has no set-aside designation. Significant NAICS codes include 237110 (Water and Sewer Line and Related Structures Construction) and 237310 (Highway, Street, and Bridge Construction). No incumbent is identified. The engineer's estimate was $10.6 million. Work is to be completed on 11.4 miles of State Route 261 between Eagar and Crescent Lake in Apache County, Arizona.
Notice text
2 versions
Update #2 · Latest ·
This project consists of the rehabilitation (3R) of approximately 11.4 miles of Arizona State Route 261 between the Town of Eagar and the intersection of State Route 273 in Apache County, Arizona. The figure below provides a visual summary of the project location.
This project consists of pulverization and paving of approximately 11.4 miles of existing asphalt paved roadway. Work also includes drainage improvements (new pipe culverts ranging from 24-inch to 48-inch diameter), lining of large diameter culverts (60-inch to 66-inch) and new guardrail installation.
APPROXIMATE QUANTITIES for major work items:
- 33,000 tons of asphalt concrete pavement, gyratory mix,
- 11.42 miles of full depth reclamation,
- 1,000 cubic yards of riprap,
- 1,600 linear feet of pipe culvert,
- 600 linear feet of culvert lining, and
- 3,500 linear feet of guardrail.
Update #1 ·
This project consists of the rehabilitation (3R) of approximately 11.4 miles of Arizona State Route 261 between the Town of Eagar and the intersection of State Route 273 in Apache County, Arizona. The figure below provides a visual summary of the project location.
This project consists of pulverization and paving of approximately 11.4 miles of existing asphalt paved roadway. Work also includes drainage improvements (new pipe culverts ranging from 24-inch to 48-inch diameter), lining of large diameter culverts (60-inch to 66-inch) and new guardrail installation.
SIGNIFICANT QUANTITIES
- 33,000 tons of asphalt concrete pavement, gyratory mix,
- 11.42 miles of full depth reclamation,
- 1,000 cubic yards of riprap,
- 1,600 linear feet of pipe culvert,
- 600 linear feet of culvert lining, and
- 3,500 linear feet of guardrail.
Attachments
Show all 16
Notice history
| Notice | Type | Posted |
|---|---|---|
| AZ FLAP SR261(1), Eagar to Crescent Lake | Award Notice | |
| AZ FLAP SR261(1), Eagar to Crescent Lake | Solicitation | |
| AZ FLAP SR261(1), Eagar to Crescent Lake | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity