AZ FLAP SR261(1) Eagar to Crescent Lake- QnA-11222022.pdf

PDF 123 KB Posted

Attached to
AZ FLAP SR261(1), Eagar to Crescent Lake
Solicitation number
6982AF22B000018
Issued by

About this file

This document contains questions and answers regarding a federal contract opportunity to rehabilitate 11.4 miles of Arizona State Route 261 between Eagar and Crescent Lake. Work includes pulverization and paving of the existing asphalt roadway, installing new and lining existing drainage culverts, and adding guardrail. Significant quantities include 33,000 tons of asphalt, 11.42 miles of full depth reclamation, 1,000 cubic yards of riprap, 1,600 linear feet of pipe culvert, 600 linear feet of culvert lining, and 3,500 linear feet of guardrail. The Department of Transportation Federal Highway Administration is the contracting agency. No pre-bid meeting is scheduled.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for AZ FLAP SR261(1), Eagar to Crescent Lake

November 22, 2022

Questions Answers 1 Will there be a pre-bid/pre-proposal meeting for this project and if so when and where will this take place?

No pre-bid is scheduled for the project.

2 There are several locations on the plans that show culvert locations in bold but only call for these to be cleaned and not have a new culvert installed such as at sta 600+73. Is this correct?

Culverts identified to be cleaned will be cleaned under the 60704-0000 CLEANING CULVERT IN PLACE pay item. There will not be a new culvert installed at these locations

3 There is a culvert shown at approximately sta 605+00 that does not indicated what work is being performed please clarify this culvert location scope of work.

Refer to plan sheet C21, where work for this culvert is described. See also Drainage Summary Sheet B07.

4 Please confirm that no drainage culvert improvements are being performed under driveway/road turnouts/aprons as none are currently shown.

Culvert improvements proposed under driveways are show on the Plan Sheets and Drainage Summary Sheets.