AZ FLAP SR261(1), Eagar to Crescent Lake
Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 6982AF22B000018
- Agency
- Federal Highway Administration Department of Transportation
- Responses due
- Not on record
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Arizona, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This notice seeks offers for the rehabilitation of approximately 11.4 miles of Arizona State Route 261 between Eagar and Crescent Lake. The Department of Transportation Federal Highway Administration will solicit full and open competition for the rehabilitation of the existing asphalt paved roadway. Work will include pulverization and paving of the roadway, drainage improvements such as new pipe culverts ranging from 24 to 48 inches in diameter, lining of large diameter culverts from 60 to 66 inches, and new guardrail installation. Evaluation will prioritize best value with consideration given to technical qualifications, past performance, and price. The anticipated schedule includes advertising in fall 2022, award in winter 2022, and construction from spring 2023 through fall 2023.
There is no set-aside designation. The estimated cost range is between $10 million and $20 million. Key work items include approximately 33,000 tons of asphalt concrete pavement, 11.42 miles of full depth reclamation, 1,000 cubic yards of riprap, 1,600 linear feet of pipe culvert, 600 linear feet of culvert lining, and 3,500 linear feet of guardrail.
Notice text
PROJECT NUMBER: AZ FLAP SR261(1)
PROJECT NAME: Eagar to Crescent Lake
PROJECT DESCRIPTION: This project consists of the rehabilitation (3R) of approximately 11.4 miles of Arizona State Route 261 between the Town of Eagar and the intersection of State Route 273 in Apache County, Arizona.
SCOPE OF THE WORK: This project consists of pulverization and paving of approximately 11.4 miles of existing asphalt paved roadway. Work also includes drainage improvements (new pipe culverts ranging from 24-inch to 48-inch diameter), lining of large diameter culverts (60-inch to 66-inch) and new guardrail installation.
PRINCIPAL WORK ITEMS:
Approximate quantities for major work items:
- 33,000 tons of asphalt concrete pavement, gyratory mix,
- 11.42 miles of full depth reclamation,
- 1,000 cubic yards of riprap,
- 1,600 linear feet of pipe culvert,
- 600 linear feet of culvert lining, and
- 3,500 linear feet of guardrail.
ANTICIPATED SCHEDULE:
Advertise: Fall 2022
Award: Winter 2022
Construction: Spring 2023 – Fall 2023
ESTIMATED COST RANGE: The anticipated cost range is between $10,000,000 and $20,000,000.
This will be solicited as full and open competition
Notice history
| Notice | Type | Posted |
|---|---|---|
| AZ FLAP SR261(1), Eagar to Crescent Lake | Award Notice | |
| AZ FLAP SR261(1), Eagar to Crescent Lake | Solicitation | |
| AZ FLAP SR261(1), Eagar to Crescent Lake | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity