1798 - Hanscom AFB Fire Suppression System Inspections
Closed Solicitation Posted
- Solicitation number
- 1798
- Agency
-
AFLCMC Hanscom AFB
Lifecycle Management Center, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 561990 All Other Support Services
- PSC
- J042 Maint/Repair/Rebuild Of Equip- Fire Fighting/Rescue/Safety Equip; Environ Protect Equip/Matls
- Place of performance
- Hanscom AFB, Massachusetts 01731, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Air Force Materiel Command Lifecycle Management Center at Hanscom Air Force Base seeks inspection, testing, and maintenance of fire suppression systems at two locations under a Total Small Business Set-Aside, with quotes due September 10 by 12:00 PM EST.
Place of performance includes Hanscom Air Force Base, MA and Sagamore Hill Observatory in Hamilton, MA. The contract covers wet pipe, dry pipe, and clean agent sprinkler systems; standpipe systems; post indicator valves; Very Early Smoke Detection Apparatus (VESDA); kitchen hood suppression systems; backflow preventers; and fire pumps. The NAICS code is 561990 (All Other Support Services) with a small business size standard of $16.5 million.
Key personnel qualifications require current Massachusetts certifications: fire protection system craftspeople, licensed fire sprinkler fitters, certified backflow prevention device testers, and licensed fire alarm technicians. All credentials must be provided within five business days of award. The contractor must maintain 24/7/365 emergency response capability with certified technicians arriving on-site within 60 minutes of dispatch notification to isolate hazards and commence repairs. Standard work hours are Monday through Friday, 7:00 a.m. to 3:00 p.m., excluding federal holidays; all work outside these hours requires contracting officer approval.
The contract consists of a one-year base period (September 18, 2026 through September 17, 2027) plus four one-year option periods through September 17, 2031, with no break in service. Inspection, testing, and maintenance tasks follow UFC 3-601-02 and include monthly fire pump maintenance, semiannual standpipe and backflow preventer inspections, and annual system inspections with additional multi-year intervals (2, 3, 5, 10, and 20 years). Backflow prevention device failures must be repaired within 10 working days and re-tested by a certified technician.
Evaluation is Lowest Price Technically Acceptable, weighing technical proposal and price. Quotes must not exceed 25 pages with completed bid schedules; pricing must not exceed two decimal places. A mandatory site visit is scheduled August 18 at 10:00 AM EST; pre-registration required by August 17. The solicitation has been amended twice; Amendment 2 eliminated the Q&A period and revised requirements; Amendment 3 provided Q&A clarifications on emergency response scope and pricing structure effective September 3.
Notice text
4 versions
Update #4 · Latest ·
Hanscom AFB facilities require fire suppression systems to be inspected, tested and maintained IAW the Performance Work Statement (PWS).
Locations will include Location 1 - Hanscom Air Force Base (HAFB) and Location 2 - Sagamore Hill Observatory, Hamilton, MA.
Amendment 1: Adding the Question and Answers along with an updated Wage Determination
Amendment 2: REVISED REQUIREMENTS- Please see the updated PWS and COMBO/Solicitation. There will not be a Q&A period. Quotes are due on 10 Sept 2026 by 12:00PM EST.
Amendment 3: Solicitation Update / Amendment Notice:
The Government is providing the following Questions and Answers (Q&As) for informational clarity and to ensure fair and open competition. These responses clarify the Government's intent and expectations regarding emergency response, mitigation scope, and pricing structure under Section 4.1 of the Performance Work Statement (PWS). Offerors shall prepare and submit their proposals in accordance with the clarifications provided herein.
Question 1:
Are we to include emergency services in our fixed price, or are we just agreeing to providing the service and will be paid for it as needed?
Government Response:
Maintaining 24/7/365 emergency response capability and readiness is inherent to the base Firm-Fixed-Price (FFP) contract requirement. Individual emergency call-outs and initial hazard mitigation are ordered and compensated as required under the applicable contract line-item structure.
Question 2:
What directionally constitutes an "emergency" that would need to be responded to at any time of the day/night/weekend/holiday that may not be able to wait until the next business day? For example, a small drip (leak) coming from a test valve, would that be a call we receive off hours? A major break in a pipe causing large amounts of water discharge would be an obvious emergency.
Government Response:
An "emergency" is strictly defined as an active hazard or critical system impairment that immediately threatens life safety, facility integrity, or mission continuity (e.g., active water discharge, major pipe rupture, complete loss of suppression pressure/agent, or uncontainable flow alarm). Routine maintenance, minor valve weeping/drips, or non-critical supervisory trouble alarms are not emergencies and will be handled during normal duty hours.
Question 3:
Can you confirm that emergency service calls are to be invoiced and paid upon completion based on the actual work performed?
Government Response:
Emergency call-outs cover the mandatory 60-minute physical arrival, diagnostic assessment, and immediate hazard containment/isolation to render the facility safe. Invoicing shall reflect completed dispatch and stabilization services in accordance with the established contract invoicing terms. Permanent corrective parts/repairs are excluded from the initial call-out.
Question 4:
Are repairs automatically authorized as part of the emergency service call, or do we need to diagnose the problem first, prepare an estimate, have estimate approved, then proceed with the repair?
Government Response:
Per PWS 4.1, the requirement upon 60-minute arrival is immediate hazard isolation and stabilization. Permanent repairs are NOT automatically authorized. Upon stabilizing the emergency, the Contractor shall submit a diagnostic assessment and cost proposal to the Contracting Officer and COR. Permanent corrective work shall only proceed upon written authorization from the Contracting Officer.
Quotes are due on 10 Sept 2026 by 12:00PM EST.
Update #3 ·
Hanscom AFB facilities require fire suppression systems to be inspected, tested and maintained IAW the Performance Work Statement (PWS).
Locations will include Location 1 - Hanscom Air Force Base (HAFB) and Location 2 - Sagamore Hill Observatory, Hamilton, MA.
Amendment 1: Adding the Question and Answers along with an updated Wage Determination
Amendment 2: REVISED REQUIREMENTS- Please see the updated PWS and COMBO/Solicitation. There will not be a Q&A period. Quotes are due on 10 Sept 2026 by 12:00PM EST.
Update #2 ·
Hanscom AFB facilities require fire suppression systems to be inspected, tested and maintained IAW the Performance Work Statement (PWS).
Locations will include Location 1 - Hanscom Air Force Base (HAFB) and Location 2 - Sagamore Hill Observatory, Hamilton, MA.
Amendment 1: Adding the Question and Answers along with an updated Wage Determination
Update #1 ·
Hanscom AFB facilities require fire suppression systems to be inspected, tested and maintained IAW the Performance Work Statement (PWS).
Locations will include Location 1 - Hanscom Air Force Base (HAFB) and Location 2 - Sagamore Hill Observatory, Hamilton, MA.
Files
Show all 13
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Fire Alarm/Suppression Inspection, Testing, and Maintenance | Air Force Research Laboratory | No set-aside | |
| Inspection of Fire Extinguishers and Suppression Systems for AMXG at Hill AFB, Utah | Air Force Sustainment Center | Total Small Business | |
| Hanscom Aero Club Automated Fuel Management System Replacement | AFLCMC Hanscom AFB | Total Small Business | |
| H342--CTX Annual Fire Extinguisher Inspection | Veterans Integrated Service Network 17 | Service-Disabled Veteran-Owned Small Business | |
| 2-STEP SEALED BID - TINKER AFB WWYK250019 Remove and Replace Fire Sprinkler in Plasma Booth Dust Collectors and Replace the Building F/A System, B3221 | Air Force Sustainment Center | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity