This document includes an infection control risk assessment and requirements for a water distribution system upgrade project at the Overton Brooks VA Medical Center in Shreveport, Louisiana. The assessment outlines control measures to contain dust and isolate the HVAC system during construction such as providing dust mitigation, sealing unused doors and air vents, placing dust mats, and containing waste. It also lists post-construction cleaning requirements including wiping surfaces, containing waste, wet mopping or vacuuming before leaving the work area, and scheduling a terminal clean.

The related federal contract opportunity is a 100% SDVOSB set-aside solicitation for Project 667-18-119 to upgrade the main hospital's water distribution system. Interested vendors must respond in accordance with the solicitation package, which is seeking these water system upgrade services from the Department of Veterans Affairs Veterans Health Administration VISN 16. The solicitation includes information on the NAICS code, size standard, and systems registration requirements for offerors.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VAMC Infection Control Precautions for Class II Projects

Based on the Infection Control Risk Assessment of this construction/remodel project, the following activities are required.

PROJECT: Upgrade Water Distribution System 667-18-119

During Construction Project Upon Completion of Project

C la ss I

I

1. Provide active means to reduce airborne dust from dispersing into atmosphere.

2. Water mist work surfaces to control dust while cutting.

3. Seal unused doors with duct tape.

4. Block off and seal air vents if the

HVAC system is removed or isolated.

5. Place dust mat at entrance and exit of work area

6. Remove or isolate HVAC system in areas where work is being performed if required to prevent contamination of adjacent areas.

7. Contain construction waste before transport in tightly covered containers.

1. Wipe work surfaces with cleaner/disinfectant.

2. Contain construction waste before transport in tightly covered containers.

3. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

4. Upon completion, restore HVAC system where work was performed.

5. Schedule EMS Terminal Clean once work is complete

Maintain control measures until ALL Work is completed. Exceptions must be approved by Infection Prevention on a case by case basis.

Preliminary Approved: Based on 35% Design Final

X Vickie L. Moore Infection Prevention Program Manager

2/9/2022

X Vickie L. Moore Vickie L. Moore MA, CIC, VHA-CM Infection Prevention Program Manager Signed by: VICKIE L. MOORE 193380