This document outlines infection control precautions for the Upgrade Water Distribution System project at the Overton Brooks VA Medical Center in Shreveport, Louisiana. During construction, contractors must minimize dust, replace displaced ceiling tiles immediately, and place waste in covered containers. Upon completion, contractors must clean work areas by wiping surfaces, damp mopping floors, and removing waste in tightly covered containers. Infection control measures must be maintained until all work is finished. Exceptions require approval.
The related federal contract opportunity is solicitation number 667-22-4-1404-0033 for the Upgrade Water Distribution System project at the Main Hospital in Shreveport, Louisiana. Offerors should respond in accordance with the solicitation package, which has a 100% SDVOSB set-aside. All offerors must be registered in VIP and SAM at time of offer and award. The NAICS code is 236220 with a size standard of $39.5M. The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Overton Brooks VAMC Infection Control Precautions
Based on the Infection Control Risk Assessment of this construction/remodel project, the following activities are required.
PROJECT: Upgrade Water Distribution System 667-18-119
During Construction Project Upon Completion of Project
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace a ceiling tile displaced for visual inspection.
3. Project Specific: Replace ceiling tile or wall panel removed for dead leg removal.
4. Place any construction waste in a covered container.
1. Clean work area upon completion of task.
a. Wipe work surfaces with cleaner/disinfectant.
b. Damp mop floors to remove any visible debris from construction.
c. Remove and construction waste in tightly covered containers.
Maintain control measures until ALL Work is completed. Exceptions must be approved by Infection Prevention on a case by case basis.
Preliminary Approval Based of 35% Design Final Approval
X Vickie L. Moore MA, CIC, VHA-CM Infection Prevention Program Manager
2/9/2022
X Vickie L. Moore Vickie L. Moore MA, CIC, VHA-CM Infection Prevention Program Manager Signed by: VICKIE L. MOORE 193380