Base Period

ATTACHMENT 2 - SCHEDULE OF SERVICES

Solicitation W91QVN-17-R-0091 Telecommunications Infrastructure Support Services (TISS), USFK-Wide

Base Period: 1 September 2017 - 31 August 2018
CLINCLIN
TYPESERVICES DESCRIPTIONQtyUnitUnit PriceAmount
0001FFPCOPPER CABLE
Install, Splice, Terminate, and Test - Copper Cable (25 to 1200 PR).40,000FT

(Linear Foot)

0002FFPGROUND ROD
Install Ground Rod to Include Grounding of Cable / Terminal.100EA
0003FFPPET HOUSING
Install Protected Entrance Terminal (PET) Housing for Copper Cable.50EA
0004FFPSPLICE CASE FOR COPPER CABLE
Install Splice Case for Copper Cable.50EA
0005FFP¾ INCH, FIRE-RETARDANT PLYWOOD BACKBOARD
Provide Contractor Furnished Material (CFM) and Install ¾ Inch, Fire-Retardant Plywood Backboard.40EA
0006FFPFIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - Fiber Optic Cable in Duct (2 to 144 Fiber Cores).160,000FT

(Linear Foot)

0007FFPLEAF FIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - LEAF Fiber Optic Cable in Duct (12 to 96 Fiber Cores).800,000FT

(Linear Foot)

0008FFPTERMINATION PANEL
Install Fiber Optic - Termination Panel (Wall Mount or Rack).100EA
0009FFPSPLICE ENCLOSURE KIT
Install Fiber Optic Cable - Splice Enclosure Kit (12 to 144 Cores).100EA
0010FFPENCASED BURIED (EB)-20 CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Encased Buried (EB)-20 Conduit Where Vehicular Traffic (i.e., Automotive, Railway) is Present.

Duct Installation to Include Excavation, Backfill, Restoration of Paved and Concrete Surfaces, Concrete Encasing, Spacers, Markers and Warning Tape(Paved Area). 5,000 FT (Linear Foot)

0011 FFP RIGID NONMETALLIC CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Rigid Nonmetallic Conduit Schedule 40 PVC Conduit.

Duct Installation to Include Excavation, Backfill, Markers and Warning Tape. 20,000 FT (Linear Foot)

0012FFPSUB / MULTI / MESH INNERDUCT
Install Sub-Duct / Innerduct / Multi-Duct / Fabric-Mesh Innerduct.10,000FT

(Linear Foot)

0013FFPCORE DRILL ½ TO 4 INCH HOLE
Core Drill ½ to 4 Inch Hole.1,000EA
0014FFP2 INCH TO 4 INCH BUILDING ENTRANCE CONDUIT
Provide Contractor Furnished Material (CFM) and Install 2 to 4 Inch Building Entrance Conduit.50EA
0015FFPMULTIDIRECTIONAL HANDHOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional 1220 x 1220 x 1220 Milimeter Handhole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.25EA
0016FFPMULTIDIRECTIONAL MAINTENANCE HOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional W1850mm by L3700 x H2150 Milimeter Maintenance Hole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.5EA
0017FFPCAT 6 LAN CABLE
Install, Terminate, and Test CAT 6 LAN Cable.500,000FT

(Linear Foot)

0018FFPCAT 6 WALL OUTLET BOX
Install CAT 6 Wall Outlet Box.500EA
0019FFPNON-METALLIC RACEWAY
Install of Non-Metallic Raceway.30,000FT

(Linear Foot)

0020FFP6 TO 12 INCH METAL CABLE LADDER RACK
Install and Bonding of 6 to 12 Inch Metal Cable Ladder Rack.10FT

(Linear Foot)

0021FFPEQUIPMENT RACK
Install Equipment Rack.10EA
0022FFPSTRAND AND GUY WIRES FOR AERIAL CABLE
Provide Contractor Furnished Material (CFM) and Install Strand and Guy Wires for Aerial Cable.50,000FT

(Linear Foot)

0023FFPCABLE ON STRAND USING LASHING MACHINE
Install Cable on Strand Using Lashing Machine to Include Splicing, Termination, and Testing of Cable.65,000FT

(Linear Foot)

0024FFPSPLICE CASE ON STRAND
Install Splice Case on Strand.20EA
0025FFP½ TO 2 INCH EMT CONDUIT INSIDE
Installation of ½ to 2 Inch Electrical Metallic Tubing (EMT) Conduit Inside of Building.35,000FT

(Linear Foot)

0026FFPPULL OR DROP BOX FOR PDS
Install Pull or Drop Box for Protected Distribution System (PDS).10EA
0027FFPGIP 4 INCH CONDUIT WITH COUPLINGS INSIDE
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Inside of Building.100FT

(Linear Foot)

0028FFPGIP 4 INCH CONDUIT WITH COUPLINGS BURIED
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Buried at a Minimum of 1 Meter Below the Surface, Encased Within a Minimum of 20 Centimeters of Concrete On All Sides.200FT

(Linear Foot)

0029FFPDEINSTALL CABLE IN CONDUITS
Deinstall Cable in Conduits.1,000,000FT

(Linear Foot)

0030FFPCIS TYPE 25 MILIMETER X 4 EACH
Provide Contractor Furnished Material (CFM) and Install Combined Innerduct System (CIS) Type 25 Milimeter x 4 Each (Black, Yellow, Red, Green).6,000FT

(Linear Foot)

0031FFPOUTSIDE PULL-BOX
Install Outside Pull-Box (Various Sizes).40EA
0032FFPPULLING WIRE IN DUCTS
Provide Contractor Furnished Material (CFM) and Install Pulling Wire in Ducts.1,000,000FT

(Linear Foot)

0033FFPACCOUNTING FOR CONTRACT SERVICES
Contractor Manpower Reporting (CMR) Must be Reported by 31 October of Each Calendar Year During the Life of the Contract.1JOB
0034INFOESTIMATED COST FOR WAR HAZARD LOSSES

Estimated Cost for War Hazard Losses is Zero ($0.00).

Total Amount for Base Period

1st Option Period

ATTACHMENT 2 - SCHEDULE OF SERVICES

Solicitation W91QVN-17-R-0091 Telecommunications Infrastructure Support Services (TISS), USFK-Wide

1st Option Period: 1 September 2018 - 31 August 2019
CLINCLIN
TYPESERVICES DESCRIPTIONQtyUnitUnit PriceAmount
1001FFPCOPPER CABLE
Install, Splice, Terminate, and Test - Copper Cable (25 to 1200 PR).40,000FT

(Linear Foot)

1002FFPGROUND ROD
Install Ground Rod to Include Grounding of Cable / Terminal.100EA
1003FFPPET HOUSING
Install Protected Entrance Terminal (PET) Housing for Copper Cable.50EA
1004FFPSPLICE CASE FOR COPPER CABLE
Install Splice Case for Copper Cable.50EA
1005FFP¾ INCH, FIRE-RETARDANT PLYWOOD BACKBOARD
Provide Contractor Furnished Material (CFM) and Install ¾ Inch, Fire-Retardant Plywood Backboard.40EA
1006FFPFIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - Fiber Optic Cable in Duct (2 to 144 Fiber Cores).160,000FT

(Linear Foot)

1007FFPLEAF FIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - LEAF Fiber Optic Cable in Duct (12 to 96 Fiber Cores).800,000FT

(Linear Foot)

1008FFPTERMINATION PANEL
Install Fiber Optic - Termination Panel (Wall Mount or Rack).100EA
1009FFPSPLICE ENCLOSURE KIT
Install Fiber Optic Cable - Splice Enclosure Kit (12 to 144 Cores).100EA
1010FFPENCASED BURIED (EB)-20 CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Encased Buried (EB)-20 Conduit Where Vehicular Traffic (i.e., Automotive, Railway) is Present.

Duct Installation to Include Excavation, Backfill, Restoration of Paved and Concrete Surfaces, Concrete Encasing, Spacers, Markers and Warning Tape(Paved Area). 5,000 FT (Linear Foot)

1011 FFP RIGID NONMETALLIC CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Rigid Nonmetallic Conduit Schedule 40 PVC Conduit.

Duct Installation to Include Excavation, Backfill, Markers and Warning Tape. 20,000 FT (Linear Foot)

1012FFPSUB / MULTI / MESH INNERDUCT
Install Sub-Duct / Innerduct / Multi-Duct / Fabric-Mesh Innerduct.10,000FT

(Linear Foot)

1013FFPCORE DRILL ½ TO 4 INCH HOLE
Core Drill ½ to 4 Inch Hole.1,000EA
1014FFP2 INCH TO 4 INCH BUILDING ENTRANCE CONDUIT
Provide Contractor Furnished Material (CFM) and Install 2 to 4 Inch Building Entrance Conduit.50EA
1015FFPMULTIDIRECTIONAL HANDHOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional 1220 x 1220 x 1220 Milimeter Handhole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.25EA
1016FFPMULTIDIRECTIONAL MAINTENANCE HOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional W1850mm by L3700 x H2150 Milimeter Maintenance Hole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.5EA
1017FFPCAT 6 LAN CABLE
Install, Terminate, and Test CAT 6 LAN Cable.400,000FT

(Linear Foot)

1018FFPCAT 6 WALL OUTLET BOX
Install CAT 6 Wall Outlet Box.400EA
1019FFPNON-METALLIC RACEWAY
Install of Non-Metallic Raceway.24,000FT

(Linear Foot)

1020FFP6 TO 12 INCH METAL CABLE LADDER RACK
Install and Bonding of 6 to 12 Inch Metal Cable Ladder Rack.10FT

(Linear Foot)

1021FFPEQUIPMENT RACK
Install Equipment Rack.10EA
1022FFPSTRAND AND GUY WIRES FOR AERIAL CABLE
Provide Contractor Furnished Material (CFM) and Install Strand and Guy Wires for Aerial Cable.50,000FT

(Linear Foot)

1023FFPCABLE ON STRAND USING LASHING MACHINE
Install Cable on Strand Using Lashing Machine to Include Splicing, Termination, and Testing of Cable.65,000FT

(Linear Foot)

1024FFPSPLICE CASE ON STRAND
Install Splice Case on Strand.20EA
1025FFP½ TO 2 INCH EMT CONDUIT INSIDE
Installation of ½ to 2 Inch Electrical Metallic Tubing (EMT) Conduit Inside of Building.30,000FT

(Linear Foot)

1026FFPPULL OR DROP BOX FOR PDS
Install Pull or Drop Box for Protected Distribution System (PDS).10EA
1027FFPGIP 4 INCH CONDUIT WITH COUPLINGS INSIDE
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Inside of Building.80FT

(Linear Foot)

1028FFPGIP 4 INCH CONDUIT WITH COUPLINGS BURIED
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Buried at a Minimum of 1 Meter Below the Surface, Encased Within a Minimum of 20 Centimeters of Concrete On All Sides.160FT

(Linear Foot)

1029FFPDEINSTALL CABLE IN CONDUITS
Deinstall Cable in Conduits.800,000FT

(Linear Foot)

1030FFPCIS TYPE 25 MILIMETER X 4 EACH
Provide Contractor Furnished Material (CFM) and Install Combined Innerduct System (CIS) Type 25 Milimeter x 4 Each (Black, Yellow, Red, Green).5,000FT

(Linear Foot)

1031FFPOUTSIDE PULL-BOX
Install Outside Pull-Box (Various Sizes).35EA
1032FFPPULLING WIRE IN DUCTS
Provide Contractor Furnished Material (CFM) and Install Pulling Wire in Ducts.800,000FT

(Linear Foot)

1033FFPACCOUNTING FOR CONTRACT SERVICES
Contractor Manpower Reporting (CMR) Must be Reported by 31 October of Each Calendar Year During the Life of the Contract.1JOB
1034INFOESTIMATED COST FOR WAR HAZARD LOSSES

Total Amount for 1st Option Period

2nd Option Period

ATTACHMENT 2 - SCHEDULE OF SERVICES

Solicitation W91QVN-17-R-0091 Telecommunications Infrastructure Support Services (TISS), USFK-Wide

2nd Option Period: 1 September 2019 - 31 August 2020
CLINCLIN
TYPESERVICES DESCRIPTIONQtyUnitUnit PriceAmount
2001FFPCOPPER CABLE
Install, Splice, Terminate, and Test - Copper Cable (25 to 1200 PR).40,000FT

(Linear Foot)

2002FFPGROUND ROD
Install Ground Rod to Include Grounding of Cable / Terminal.100EA
2003FFPPET HOUSING
Install Protected Entrance Terminal (PET) Housing for Copper Cable.50EA
2004FFPSPLICE CASE FOR COPPER CABLE
Install Splice Case for Copper Cable.50EA
2005FFP¾ INCH, FIRE-RETARDANT PLYWOOD BACKBOARD
Provide Contractor Furnished Material (CFM) and Install ¾ Inch, Fire-Retardant Plywood Backboard.40EA
2006FFPFIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - Fiber Optic Cable in Duct (2 to 144 Fiber Cores).160,000FT

(Linear Foot)

2007FFPLEAF FIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - LEAF Fiber Optic Cable in Duct (12 to 96 Fiber Cores).800,000FT

(Linear Foot)

2008FFPTERMINATION PANEL
Install Fiber Optic - Termination Panel (Wall Mount or Rack).100EA
2009FFPSPLICE ENCLOSURE KIT
Install Fiber Optic Cable - Splice Enclosure Kit (12 to 144 Cores).100EA
2010FFPENCASED BURIED (EB)-20 CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Encased Buried (EB)-20 Conduit Where Vehicular Traffic (i.e., Automotive, Railway) is Present.

Duct Installation to Include Excavation, Backfill, Restoration of Paved and Concrete Surfaces, Concrete Encasing, Spacers, Markers and Warning Tape(Paved Area). 5,000 FT (Linear Foot)

2011 FFP RIGID NONMETALLIC CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Rigid Nonmetallic Conduit Schedule 40 PVC Conduit.

Duct Installation to Include Excavation, Backfill, Markers and Warning Tape. 20,000 FT (Linear Foot)

2012FFPSUB / MULTI / MESH INNERDUCT
Install Sub-Duct / Innerduct / Multi-Duct / Fabric-Mesh Innerduct.10,000FT

(Linear Foot)

2013FFPCORE DRILL ½ TO 4 INCH HOLE
Core Drill ½ to 4 Inch Hole.1,000EA
2014FFP2 INCH TO 4 INCH BUILDING ENTRANCE CONDUIT
Provide Contractor Furnished Material (CFM) and Install 2 to 4 Inch Building Entrance Conduit.50EA
2015FFPMULTIDIRECTIONAL HANDHOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional 1220 x 1220 x 1220 Milimeter Handhole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.25EA
2016FFPMULTIDIRECTIONAL MAINTENANCE HOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional W1850mm by L3700 x H2150 Milimeter Maintenance Hole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.5EA
2017FFPCAT 6 LAN CABLE
Install, Terminate, and Test CAT 6 LAN Cable.300,000FT

(Linear Foot)

2018FFPCAT 6 WALL OUTLET BOX
Install CAT 6 Wall Outlet Box.300EA
2019FFPNON-METALLIC RACEWAY
Install of Non-Metallic Raceway.18,000FT

(Linear Foot)

2020FFP6 TO 12 INCH METAL CABLE LADDER RACK
Install and Bonding of 6 to 12 Inch Metal Cable Ladder Rack.10FT

(Linear Foot)

2021FFPEQUIPMENT RACK
Install Equipment Rack.10EA
2022FFPSTRAND AND GUY WIRES FOR AERIAL CABLE
Provide Contractor Furnished Material (CFM) and Install Strand and Guy Wires for Aerial Cable.50,000FT

(Linear Foot)

2023FFPCABLE ON STRAND USING LASHING MACHINE
Install Cable on Strand Using Lashing Machine to Include Splicing, Termination, and Testing of Cable.65,000FT

(Linear Foot)

2024FFPSPLICE CASE ON STRAND
Install Splice Case on Strand.20EA
2025FFP½ TO 2 INCH EMT CONDUIT INSIDE
Installation of ½ to 2 Inch Electrical Metallic Tubing (EMT) Conduit Inside of Building.25,000FT

(Linear Foot)

2026FFPPULL OR DROP BOX FOR PDS
Install Pull or Drop Box for Protected Distribution System (PDS).10EA
2027FFPGIP 4 INCH CONDUIT WITH COUPLINGS INSIDE
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Inside of Building.60FT

(Linear Foot)

2028FFPGIP 4 INCH CONDUIT WITH COUPLINGS BURIED
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Buried at a Minimum of 1 Meter Below the Surface, Encased Within a Minimum of 20 Centimeters of Concrete On All Sides.120FT

(Linear Foot)

2029FFPDEINSTALL CABLE IN CONDUITS
Deinstall Cable in Conduits.600,000FT

(Linear Foot)

2030FFPCIS TYPE 25 MILIMETER X 4 EACH
Provide Contractor Furnished Material (CFM) and Install Combined Innerduct System (CIS) Type 25 Milimeter x 4 Each (Black, Yellow, Red, Green).4,000FT

(Linear Foot)

2031FFPOUTSIDE PULL-BOX
Install Outside Pull-Box (Various Sizes).30EA
2032FFPPULLING WIRE IN DUCTS
Provide Contractor Furnished Material (CFM) and Install Pulling Wire in Ducts.600,000FT

(Linear Foot)

2033FFPACCOUNTING FOR CONTRACT SERVICES
Contractor Manpower Reporting (CMR) Must be Reported by 31 October of Each Calendar Year During the Life of the Contract.1JOB
2034INFOESTIMATED COST FOR WAR HAZARD LOSSES

Total Amount for 2nd Option Period

3rd Option Period

ATTACHMENT 2 - SCHEDULE OF SERVICES

Solicitation W91QVN-17-R-0091 Telecommunications Infrastructure Support Services (TISS), USFK-Wide

3rd Option Period: 1 September 2020 - 31 August 2021
CLINCLIN
TYPESERVICES DESCRIPTIONQtyUnitUnit PriceAmount
3001FFPCOPPER CABLE
Install, Splice, Terminate, and Test - Copper Cable (25 to 1200 PR).40,000FT

(Linear Foot)

3002FFPGROUND ROD
Install Ground Rod to Include Grounding of Cable / Terminal.100EA
3003FFPPET HOUSING
Install Protected Entrance Terminal (PET) Housing for Copper Cable.50EA
3004FFPSPLICE CASE FOR COPPER CABLE
Install Splice Case for Copper Cable.50EA
3005FFP¾ INCH, FIRE-RETARDANT PLYWOOD BACKBOARD
Provide Contractor Furnished Material (CFM) and Install ¾ Inch, Fire-Retardant Plywood Backboard.40EA
3006FFPFIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - Fiber Optic Cable in Duct (2 to 144 Fiber Cores).160,000FT

(Linear Foot)

3007FFPLEAF FIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - LEAF Fiber Optic Cable in Duct (12 to 96 Fiber Cores).800,000FT

(Linear Foot)

3008FFPTERMINATION PANEL
Install Fiber Optic - Termination Panel (Wall Mount or Rack).100EA
3009FFPSPLICE ENCLOSURE KIT
Install Fiber Optic Cable - Splice Enclosure Kit (12 to 144 Cores).100EA
3010FFPENCASED BURIED (EB)-20 CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Encased Buried (EB)-20 Conduit Where Vehicular Traffic (i.e., Automotive, Railway) is Present.

Duct Installation to Include Excavation, Backfill, Restoration of Paved and Concrete Surfaces, Concrete Encasing, Spacers, Markers and Warning Tape(Paved Area). 5,000 FT (Linear Foot)

3011 FFP RIGID NONMETALLIC CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Rigid Nonmetallic Conduit Schedule 40 PVC Conduit.

Duct Installation to Include Excavation, Backfill, Markers and Warning Tape. 20,000 FT (Linear Foot)

3012FFPSUB / MULTI / MESH INNERDUCT
Install Sub-Duct / Innerduct / Multi-Duct / Fabric-Mesh Innerduct.10,000FT

(Linear Foot)

3013FFPCORE DRILL ½ TO 4 INCH HOLE
Core Drill ½ to 4 Inch Hole.1,000EA
3014FFP2 INCH TO 4 INCH BUILDING ENTRANCE CONDUIT
Provide Contractor Furnished Material (CFM) and Install 2 to 4 Inch Building Entrance Conduit.50EA
3015FFPMULTIDIRECTIONAL HANDHOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional 1220 x 1220 x 1220 Milimeter Handhole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.25EA
3016FFPMULTIDIRECTIONAL MAINTENANCE HOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional W1850mm by L3700 x H2150 Milimeter Maintenance Hole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.5EA
3017FFPCAT 6 LAN CABLE
Install, Terminate, and Test CAT 6 LAN Cable.200,000FT

(Linear Foot)

3018FFPCAT 6 WALL OUTLET BOX
Install CAT 6 Wall Outlet Box.200EA
3019FFPNON-METALLIC RACEWAY
Install of Non-Metallic Raceway.12,000FT

(Linear Foot)

3020FFP6 TO 12 INCH METAL CABLE LADDER RACK
Install and Bonding of 6 to 12 Inch Metal Cable Ladder Rack.10FT

(Linear Foot)

3021FFPEQUIPMENT RACK
Install Equipment Rack.10EA
3022FFPSTRAND AND GUY WIRES FOR AERIAL CABLE
Provide Contractor Furnished Material (CFM) and Install Strand and Guy Wires for Aerial Cable.50,000FT

(Linear Foot)

3023FFPCABLE ON STRAND USING LASHING MACHINE
Install Cable on Strand Using Lashing Machine to Include Splicing, Termination, and Testing of Cable.65,000FT

(Linear Foot)

3024FFPSPLICE CASE ON STRAND
Install Splice Case on Strand.20EA
3025FFP½ TO 2 INCH EMT CONDUIT INSIDE
Installation of ½ to 2 Inch Electrical Metallic Tubing (EMT) Conduit Inside of Building.20,000FT

(Linear Foot)

3026FFPPULL OR DROP BOX FOR PDS
Install Pull or Drop Box for Protected Distribution System (PDS).10EA
3027FFPGIP 4 INCH CONDUIT WITH COUPLINGS INSIDE
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Inside of Building.40FT

(Linear Foot)

3028FFPGIP 4 INCH CONDUIT WITH COUPLINGS BURIED
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Buried at a Minimum of 1 Meter Below the Surface, Encased Within a Minimum of 20 Centimeters of Concrete On All Sides.80FT

(Linear Foot)

3029FFPDEINSTALL CABLE IN CONDUITS
Deinstall Cable in Conduits.400,000FT

(Linear Foot)

3030FFPCIS TYPE 25 MILIMETER X 4 EACH
Provide Contractor Furnished Material (CFM) and Install Combined Innerduct System (CIS) Type 25 Milimeter x 4 Each (Black, Yellow, Red, Green).3,000FT

(Linear Foot)

3031FFPOUTSIDE PULL-BOX
Install Outside Pull-Box (Various Sizes).25EA
3032FFPPULLING WIRE IN DUCTS
Provide Contractor Furnished Material (CFM) and Install Pulling Wire in Ducts.400,000FT

(Linear Foot)

3033FFPACCOUNTING FOR CONTRACT SERVICES
Contractor Manpower Reporting (CMR) Must be Reported by 31 October of Each Calendar Year During the Life of the Contract.1JOB
3034INFOESTIMATED COST FOR WAR HAZARD LOSSES

Total Amount for 3rd Option Period

4th Option Period

ATTACHMENT 2 - SCHEDULE OF SERVICES

Solicitation W91QVN-17-R-0091 Telecommunications Infrastructure Support Services (TISS), USFK-Wide

4th Option Period: 1 September 2021 - 31 August 2022
CLINCLIN
TYPESERVICES DESCRIPTIONQtyUnitUnit PriceAmount
4001FFPCOPPER CABLE
Install, Splice, Terminate, and Test - Copper Cable (25 to 1200 PR).40,000FT

(Linear Foot)

4002FFPGROUND ROD
Install Ground Rod to Include Grounding of Cable / Terminal.100EA
4003FFPPET HOUSING
Install Protected Entrance Terminal (PET) Housing for Copper Cable.50EA
4004FFPSPLICE CASE FOR COPPER CABLE
Install Splice Case for Copper Cable.50EA
4005FFP¾ INCH, FIRE-RETARDANT PLYWOOD BACKBOARD
Provide Contractor Furnished Material (CFM) and Install ¾ Inch, Fire-Retardant Plywood Backboard.40EA
4006FFPFIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - Fiber Optic Cable in Duct (2 to 144 Fiber Cores).160,000FT

(Linear Foot)

4007FFPLEAF FIBER OPTIC CABLE IN DUCT
Install, Terminate, Splice, and Test - LEAF Fiber Optic Cable in Duct (12 to 96 Fiber Cores).800,000FT

(Linear Foot)

4008FFPTERMINATION PANEL
Install Fiber Optic - Termination Panel (Wall Mount or Rack).100EA
4009FFPSPLICE ENCLOSURE KIT
Install Fiber Optic Cable - Splice Enclosure Kit (12 to 144 Cores).100EA
4010FFPENCASED BURIED (EB)-20 CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Encased Buried (EB)-20 Conduit Where Vehicular Traffic (i.e., Automotive, Railway) is Present.

Duct Installation to Include Excavation, Backfill, Restoration of Paved and Concrete Surfaces, Concrete Encasing, Spacers, Markers and Warning Tape(Paved Area). 5,000 FT (Linear Foot)

4011 FFP RIGID NONMETALLIC CONDUIT

Provide Contractor Furnished Material (CFM) and Install 4 Inch (1 to 4 Ducts) Rigid Nonmetallic Conduit Schedule 40 PVC Conduit.

Duct Installation to Include Excavation, Backfill, Markers and Warning Tape. 20,000 FT (Linear Foot)

4012FFPSUB / MULTI / MESH INNERDUCT
Install Sub-Duct / Innerduct / Multi-Duct / Fabric-Mesh Innerduct.10,000FT

(Linear Foot)

4013FFPCORE DRILL ½ TO 4 INCH HOLE
Core Drill ½ to 4 Inch Hole.1,000EA
4014FFP2 INCH TO 4 INCH BUILDING ENTRANCE CONDUIT
Provide Contractor Furnished Material (CFM) and Install 2 to 4 Inch Building Entrance Conduit.50EA
4015FFPMULTIDIRECTIONAL HANDHOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional 1220 x 1220 x 1220 Milimeter Handhole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.25EA
4016FFPMULTIDIRECTIONAL MAINTENANCE HOLE
Provide Contractor Furnished Material (CFM) and Install Multidirectional W1850mm by L3700 x H2150 Milimeter Maintenance Hole to Include Excavation, Restoration, Backfill, Plugging Ducts, All Hardware and Grounding Installation.5EA
4017FFPCAT 6 LAN CABLE
Install, Terminate, and Test CAT 6 LAN Cable.100,000FT

(Linear Foot)

4018FFPCAT 6 WALL OUTLET BOX
Install CAT 6 Wall Outlet Box.100EA
4019FFPNON-METALLIC RACEWAY
Install of Non-Metallic Raceway.6,000FT

(Linear Foot)

4020FFP6 TO 12 INCH METAL CABLE LADDER RACK
Install and Bonding of 6 to 12 Inch Metal Cable Ladder Rack.10FT

(Linear Foot)

4021FFPEQUIPMENT RACK
Install Equipment Rack.10EA
4022FFPSTRAND AND GUY WIRES FOR AERIAL CABLE
Provide Contractor Furnished Material (CFM) and Install Strand and Guy Wires for Aerial Cable.50,000FT

(Linear Foot)

4023FFPCABLE ON STRAND USING LASHING MACHINE
Install Cable on Strand Using Lashing Machine to Include Splicing, Termination, and Testing of Cable.65,000FT

(Linear Foot)

4024FFPSPLICE CASE ON STRAND
Install Splice Case on Strand.20EA
4025FFP½ TO 2 INCH EMT CONDUIT INSIDE
Installation of ½ to 2 Inch Electrical Metallic Tubing (EMT) Conduit Inside of Building.15,000FT

(Linear Foot)

4026FFPPULL OR DROP BOX FOR PDS
Install Pull or Drop Box for Protected Distribution System (PDS).10EA
4027FFPGIP 4 INCH CONDUIT WITH COUPLINGS INSIDE
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Inside of Building.40FT

(Linear Foot)

4028FFPGIP 4 INCH CONDUIT WITH COUPLINGS BURIED
Provide Contractor Furnished Material (CFM) and Install Galvanized (GIP) 4 Inch Conduit with Couplings Buried at a Minimum of 1 Meter Below the Surface, Encased Within a Minimum of 20 Centimeters of Concrete On All Sides.80FT

(Linear Foot)

4029FFPDEINSTALL CABLE IN CONDUITS
Deinstall Cable in Conduits.200,000FT

(Linear Foot)

4030FFPCIS TYPE 25 MILIMETER X 4 EACH
Provide Contractor Furnished Material (CFM) and Install Combined Innerduct System (CIS) Type 25 Milimeter x 4 Each (Black, Yellow, Red, Green).2,000FT

(Linear Foot)

4031FFPOUTSIDE PULL-BOX
Install Outside Pull-Box (Various Sizes).20EA
4032FFPPULLING WIRE IN DUCTS
Provide Contractor Furnished Material (CFM) and Install Pulling Wire in Ducts.200,000FT

(Linear Foot)

4033FFPACCOUNTING FOR CONTRACT SERVICES
Contractor Manpower Reporting (CMR) Must be Reported by 31 October of Each Calendar Year During the Life of the Contract.1JOB
4034INFOESTIMATED COST FOR WAR HAZARD LOSSES

Total Amount for 4th Option Period