The file is a Pricing Sheet Excel template for a construction project, specifically a division summary for repairing Building 305. The spreadsheet includes cost breakdown categories across multiple construction divisions, including General Conditions, Site Construction, Wood & Plastics, Doors & Windows, Finishes, Special Construction, and Mechanical. The pricing sheet provides a comprehensive cost breakdown structure that captures labor, materials, subcontractor expenses, equipment, and other associated costs, with sections for net costs, overhead, profit, bonding, and total estimate.
The pricing sheet corresponds to the related federal contract opportunity (Solicitation W91QF4-25-B-0001) for installing 13 water bottle filling stations at the Presidio of Monterey, California. The project involves replacing existing water fountains with new commercial-grade units across 11 buildings, requiring removal of old units, installation of new plumbing and electrical connections, and compliance with various technical standards including ADA, ICC, ASME, and NSF requirements. The solicitation is set aside for small businesses, with a NAICS code of 238220 for Plumbing, Heating, and Air-Conditioning Contractors, and is being issued by the Department of the Army Materiel Command Mission and Installation Contracting Command.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
~tpl1f2e
| Division Summary with Totals Page | Repair Building 305 | |||||||
| Division Summary | ||||||||
| CSI | Division | Labor | Mat | Subs | Equip | Other | User | Grand |
| Total | Total | Total | Total | Total | Total | Total | ||
| 1 | General Conditions | |||||||
| 2 | Site Construction | |||||||
| 6 | Wood & Plastics | |||||||
| 8 | Doors & Windows | |||||||
| 9 | Finishes | |||||||
| 13 | Special Construction | |||||||
| 15 | Mechanical | |||||||
| Grand Total | ||||||||
| Totals Page | ||||||||
| Percent | Amount | Category | Hours | Job Cost Phase | ||||
| --- Base Estimate --- Totals | ||||||||
| Labor | ||||||||
| Material | ||||||||
| Subcontractor | ||||||||
| Equipment | ||||||||
| Other | ||||||||
| User |
| Net Costs |
| Overhead |
| Profit |
| Subtotal |
| Bond |
| Total --- Base Estimate --- |
Estimate Total