AF_3065_Contract_progress_report_LC.pdf

PDF 14 KB Posted

Attached to
Repair PV (Photovoltaic) System
Solicitation number
W9136419R8006
Issued by

About this file

AF3065 progress report (for informational purposes only, not required to be submitted with proposal)

View the file

Other files

File Type Posted
AF_3064_Progress_Schedule.xls XLS spreadsheet
W91363419R8006_Amendment002.pdf PDF
RFI_01_-_GEM_Energy_Answered_82319.pdf PDF
General_Requirements_-_Construction_Brief_PV_repair.pdf PDF
Preproposal_Conference_Briefing.pdf PDF
W9136419R8006_Preproposal_Conference_Attendance_List.pdf PDF
A0001_Final_82119.pdf PDF
PV_PH_5_E1.02.zip ZIP file
PH PH 5 E2.02.pdf PDF
PV PH5 E2.01 Partial Site Plan.pdf PDF
PH_PH_5_E2.02.zip ZIP file
180th_FW_Base_Map_Comm_(Solar_Field)_4-11-19.pdf PDF
PV_PH_5_E1.01.pdf PDF
PV_PH_5_E1.04_(1).pdf PDF
PV_PH_5_E0.01.pdf PDF
PV_PH_5_E0.02.pdf PDF
PV_PH_5_E1.02.pdf PDF
PV_PH_5_E3.02.pdf PDF
PV_PH_5_E0.03.pdf PDF
PV_PH_5_E1.03.pdf PDF
Existing_Solar_Communications_Riser.pdf PDF
PV_PH_5_E3.01_One_Line_Diagram.pdf PDF
W9136419R8006_Repair_Solar_Field_Solicitation_81219.pdf PDF
RFI_Template.doc DOC document
PV_PH_5_E1.06.pdf PDF
PV_PH_5_E2.03.pdf PDF
PV_PH_5_E1.05.pdf PDF
180th_FW_Base_Map_Electric_(Solar_Field)_4-11-19.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB NO. 0704-0188CONTRACT PROGRESS REPORT

Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to the Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (OMB No. 9000-0058), 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

PLEASE DO NOT RETURN YOUR FORM TO THE ABOVE ADDRESS. RETURN COMPLETED FORM TO : SAF/AQCO, 1060 Air Force Pentagon, Washington DC 20330-1060.

CONTRACTOR ADDRESS

REPORT NO. PERIOD COVERED

FROM:

PROJECT NO. CONTRACT NO. COMPLETION DATE

TO:

LINE

NO.

% OF

TOTAL JOB

% COMPLETED

THIS PERIOD

% COMPLETED

CUMULATIVE

WORK ELEMENT

TOTAL

REMARKS

At the Contracting Officer's discretion and according to the payments clause of the contract, the information provided on this form may be used for computing progress payments.

PROGRESS OR COMPLETION CERTIFICATE

I hereby certify that the contractor has satisfactorily completed the indicated percentage of the contract per contract specifications.

SUBMITTED BY OR FOR

CONTRACTOR BASE CIVIL ENGINEER

TYPE OR PRINT NAME AND TITLE SIGNATURE DATE

REVIEWED BY OR FOR CONTRACTING OFFICER

TYPE OR PRINT NAME AND TITLE SIGNATURE DATE

AF IMT 3065, 19960401, V1 PREVIOUS EDITION IS OBSOLETE.

File details come from the government source that posted it.