This amendment modifies a solicitation for the design-build of the Vandenberg Gate Complex at Hanscom Air Force Base. The amendment provides responses to four requests for information. The existing main entrance gate is not compliant with antiterrorism requirements and experiences traffic congestion. The project scope involves constructing a new access control facility to current standards and improve traffic flow. Offerors must supply fire alarm/mass notification panels that integrate with the base standard and communicate with a future Monaco system. Past performance questionnaires should be filled out by end users or customers. Offerors should submit projects demonstrating their own or proposed team members' work. The amendment does not change other terms and conditions of the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Cover_TOC.pdf | ||
| Part 4_PerformanceTechnicalSpecifications.pdf | ||
| District Design Manual.pdf | ||
| Part2_GeneralRequirements.pdf | ||
| W912WJ20R0001_Solicitation.pdf | ||
| Part5_Attachments.pdf | ||
| Part 3_ProjectProgams-14Apr2020.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment is issued to provide responses to Requests for Information (RFI). All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ20R0001
X 9B. DATED (SEE ITEM 11)
30-Apr-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Jun-2020
CODE
US ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA ROAD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ20R0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003 RFI
1. Are Past Performance Questionnaires required to be addressed to the end user of the project? For example, if the entity was a sub consultant on a project, can they request the evaluation from a Prime Contractor?
GOVERNMENT RESPONSE: PPQs should be filled out by the end-user/customer.
2. Part D. Proposal Submission Requirements, Item 4. Content Requirement, Factor I - Experience (on page 14 of the Solicitation PDF document) paragraph 5 states that "The description of the project should identify the design disciplines that were involved." Does this mean we should include all design disciplines involved on the project, or limit it to only the design disciplines that the preparer of the project sheet has been involved with?
GOVERNMENT RESPONSE: The intent of this requirement is for the offeror to identify all technical disciplinary activities that the Offeror, or the Offeror’s proposed team member, was responsible for during the execution of the project.
3. Can we submit a Factor 1 project from a sub consultant to the DOR? This sub consultant is serving as a
Technical Advisor to the design-build team. The Factor 1 project would show a project in which the sub consultant served in a similar capacity.
GOVERNMENT RESPONSE: The Offeror should submit projects that demonstrate work conducted by the Offeror, or Offeror’s proposed team member(s).
4. The solicitation calls for fire alarm to be provided where none exist and with the exception of five buildings with a Simplex system and another five buildings with a Monaco fire alarm system. All reporting to a central communication Monaco transmission system. Would the government accept a competitive alternate to?
1. The building fire alarm systems
2. The base communication and mass notification system
GOVERNMENT RESPONSE: Refer to Part4_Performance Technical Specifications, D401001 Fire Alarm Distribution, pg 93 of 172. "The Contractor must supply fire alarm/mass notification panels that fully integrate with the existing base standard while providing future capability to communicate with the future Monaco System."