REQUEST FOR INFORMATION
Solicitation Number: W912SV-18-B-6002
PROJECT TITLE: Underground Utilities
Date: 28 August 2018
RFI
NO.
DATE OF
SUBMISSION
DATE TO
REQUESTOR/TECH
POC
DATE
RESPONSE
RETURNED
RESPONSE TO RFI DATE
RETURNED
TO KTR
19 Jul 2018 N/A 19 Jul 2018 See answer below 19 Jul 2018
I am requesting access to the Plans for the above subject Project.
I have completed DD Form 2345 and FedEx mailed to the DLA this morning. However, I am concerned that the required DLA approvals will not be processed in order for me to obtain the plans via FBO.
SOW, plans, and specs have been sent via AMRDEC.
19 Jul 2018 N/A 19 Jul 2018 See answer below 19 Jul 2018
I am trying to download the rest of the Bid package and for some reason the FBO system isn’t able to verify our company MPIN number. I have verified it through SAM it is the correct number I am not sure why it wont work on the FBO site. Is there another way to get the drawings?
Or do you know what I need to do to verify the MPIN number is correct?
19 Jul 2018 N/A 19 Jul 2018 See answer below 19 Jul 2018
Are you the person who can grant access to the documents regarding this project on FBO?
Yes, along with SMSgt Kyle Kiepke and Ms. Kerry Wells.
19 Jul 2018 19 Jul 2018 24 Jul 2018 See answer below 13 Aug 2018
Can you confirm there are only 6 sheets of drawings for this project.
The SOW and notes on the plans insinuate that there is work for exterior lighting and there may be a lighting plan associated with the
Lighting Plan added and attached as “H01 Lighting Plan” project. We have not received a lighting plan in this package. Please advise.
25 Jul 2018 N/A 25 Jul 2018 See answer below 25 Jul 2018
Requesting all documentation regarding the above project for our
CEO…
31 Jul 2018 N/A 3 Aug 2018 See answer below 3 Aug 2018
Will you post the pre-bid visit attendance list on FBO?
Requested site visit documents are posted to FBO.
31 Jul 2018 N/A 2 Aug 2018 See answer below 2 Aug 2018
I believe you had mentioned that you might be able to send us the files direct through email. Any way you can do that for us?
31 Jul 2018 N/A 2 Aug 2018 See answer below 2 Aug 2018
We would like to get plans and specifications for Solicitation No.
W912SV18B6002.
1 Aug 2018 1 Aug 2018 3 Aug 2018 See answer below 13 Aug 2018
Lighting Plan-need scale for ductbank lengths (No scale on plans)
The first “x” from left to right is 100LF 2nd “x” is 200LF 3rd “x” is 400LF
1 Aug 2018 1 Aug 2018 22 Aug 2018 See answer below 22 Aug 2018
How do we address comm. cables on poles?
Please see SECTION 265700 and “Information Only” drawings
11 1 Aug 2018 See answer below
Is 3" conduit ductbank adequate for 3-4/0 and 1 -2/0 cable?
Primary Distribution Conduits between underground structures) – Use 6 inch concrete encased (155 mm). Verify with manufacturer and pertinent sections of the NEC as to conduit sizes. But provide minimum 6” conduit concrete encased.
Primary Distribution Conduits (on laterals) and Secondary Distribution Conduits – 4 in (103 mm). Secondary distribution conduits refer to the conduit routing from the distribution transformer to the service entrance panel. This requirement does not apply to street lighting circuits.
Use Type EB Schedule 40 PVC conduits (minimum thickness) for conduits installed in concrete encasement.
Provide at least 3 in (75 mm) of concrete encasement.
Also use Schedule 40 PVC conduit (minimum thickness) for conduits that are not installed in concrete encasement.
Bury conduit at a minimum depth of 18 in (450 mm) below grade. Conduits must be 24 in (600 mm) minimum depth under roads and pavement. Apply conductor ampacity derating when exceeding the NFPA 70 maximum burial depths.
Provide 3 in (75 mm) clearance between conduits utilizing interlocking plastic spacers.
Provide spare conduits such that at least 1/3 of the ductbank contains empty conduits.
Include pull wires (pull string or pull rope) in all spare ducts.
Provide a transition from Type EB conduit to Schedule 40 PVC conduit before emerging from underground.
6 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Please provide a scaled site plan or a required linear footage of trenching.
Graphic scale is depicted above in item no. 9. Please do the takeoff from the plan using that scale.
6 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Can you specify how many linear feet of ductbank is to be (4) conduits,
(2) conduits and (1) conduit per the typical trench details that were provided in the drawing set?
Three phase duct banks along IZZEA Street and Granville Ave shall be four (4) conduits. Other street areas can be two (2) conduits. Only use one (1) conduit on the transformer secondary sides.
Provide spare conduits such that at least 1/3 of the ductbank contains empty conduits with pull string.
6 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Is it acceptable to move the trenching into the grassed areas parallel to the street to limit the amount of pavement and concrete restoration to only the driveways and walkways?
Yes that is acceptable as long as accessibility to the underground primary is safe and in compliance with the intent of this Performance Work Statement. There are minimum distance requirements from hydrants, etc. when locating MH.
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
What is the scale on the prints?
Please see item no. 9 above
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
What are the sizes of the electrical services from the transformer to the buildings?
Electrical Contractor shall provide the maximum service to the building based on the size of the main distribution c/b serving the facility with appropriate guidance of articles from the National Electrical Code (NEC 2017). Following are the main distribution panel circuit breaker sizes for the different buildings:
Building 165 has an 800A Main c/b 156: 400A
155: 200A 604: 200A 162: 800A 169: 1600A 168: 800A 170: 1200A 197: 800A 159: 600A 149: 800A
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
How many conduits are required between manholes?
Four (4) includes spare conduits
On print # One Line Drawings what is box SC-1
SC-1 is a Sectionalizing Cabinet as depicted on the “Section Pad Details” drawing
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
We would like specifications on the transformers and S & C Switchgear.
Specifications for transformers is provided in Section 261200.
Specifications for 15kV Separable Connectors , Sectionalizing Termination Cabinets and Pad Mounted Switchgear is provided in Section 261201
How do we check for addendum for the project?
Addendums are posted as separate attachments with the solicitation documentation on FBO.
Are there any spare conduits required for this project?
Yes. There shall be at least one spare conduit of sufficient size in ALL underground duct.
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
No scale is shown on the drawings. Please provide a scale for estimating purposes.
Please see item no. 9 above for drawing scale.
23 9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Note 21 on the Site Plan references a Lighting Plan but no Lighting Plan was provided. Please provide Lighting Plan.
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Reference Grounding Detail at Pad Mounted Transformer (Detail D) on the Section Pad Details drawing. A note on the right side of the detail states to provide a 1/0 AWG bare copper ground @ "1000" feet off the edge of the fence. Please confirm this is required.
When performing the required grounding test, the grounding shall pass the “Fall of Potential” requirements. Please see item 35 below for “Fence Grounding”.
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Note 27 on the Site Plan drawing indicates a 36" x 36" x 36" closed bottom pullbox. There is no detail for a 36” x 36” x 36” pullbox but there is a precast handhole detail on the Section Pad Details drawing showing a 24" x 24" x 24" handhole. Is the pullbox to be the same as the handhole except for the larger dimensions?
Yes. But that depends on where it’s to be utilized, plus the NEC pertinent requirements.
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Please provide a detail for each of the pull boxes, handholes and manholes showing the grounding requirements.
There is some grounding detail information indicated on the “Typical Precast Manhole Detail” on “Manhole Detail Layout”. Plus see item no. 28 below
Materials and Special Requirements Ground Rods.
Ground rod composition, minimum spacing requirements and connections shall conform to requirements of IEEE C2 Section 9 except that minimum dimensions shall be 10 ft (3.0 m) in length and ¾ inch (19 mm) in diameter. Ground rods shall be copper-clad steel, solid copper, or stainless steel. Sectional ground rods are permitted.
All connections to ground rods below ground level shall be by exothermic weld connection. Accessible connections above ground level and in test wells can be accomplished by clamping.
Spacing for driving additional grounds must be a minimum of 10 ft (3.0 m). Bond these driven electrodes together with a minimum of 4 AWG soft drawn bare copper wire buried to a depth of at least 12 in (300 mm).
Pole–butt plates and wire wraps recognized by IEEE C2 Section 9 shall not be recognized as grounding electrodes.
Provide Ground Rings around all 15kV Sectionalizing Termination Cabinets and Pad Mounted Switchgear. Ground rings shall conform to the requirements of NFPA 70 Section 250.
Switchgear, and sectionalizing cabinets require a 4/0 bare copper ground ring with a minimum of four ground rods for three phase service. Single phase service installations can be modified to minimum 1/0 copper and two ground rods for the ground ring. Provide one Test well at each location.
Note: Bond each bollard to the ground ring.
• The service point for utilization of electric supply stations containing an overcurrent protection device shall be at the main breaker on the secondary side of the utilization electric supply station. This is the transition point from IEEE C2 to NFPA 70 grounding where the service main bonding jumper is located.
Is there a grounding requirement for protective bollards?
Yes. Bond (exothermically) each bollard to the ground ring.
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
The Typical Precast Electrical Manhole Detail on the Manhole and Other Details drawing shows a bare #6 AWG grounding conductor from a ground rod to a Cable Rack. The "Top View Precast Electrical Manhole Detail" on the same drawing indicates that the cable racks are non-metallic. Please verify the requirements for manhole grounding.
See Manhole Typical Grounding Detail below. This is only for the grounding aspect of the manhole.
Please verify requirements for grounding in vaults.
Please see response in item 26 and 28 above
Reference Electrical One Line Plan drawing. The fuse sizes in the pad mounted switchgears are not indicated. Please provide their sizes and indicate if spare fuses are required.
Contractor is to provide the proper fuse sizes based on submittals and field review of existing equipment and new equipment being provided. Spare fuses are to be provided for each fuse type
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018 Reference Electrical One Line Plan drawing. The sizes of the feeder conductors to the transformers are not indicated. Please provide sizes and quantities for each feeder.
Contractor shall provide the appropriate feeder and conduit sizes from the National Electrical Code (2017 NEC) based on maximum load percentages that the transformers can carry.
See item no. 16 above for main distribution panel circuit breaker sizes for the different buildings.
In the Solicitation documentation, Section 00100, under Description of Project on page 7 of 70, states “Provide (5) pad mounted separable connector cabinets and (9) pad mounted fusible switchgear units…”.
The Site Plan shows (1) pad mounted separable connector cabinet and
(7) pad mounted fusible switch gear units. Which is correct, the quantities shown on Site Plan or noted in the Description of the Project?
The exact no. shall be determined in the field as required.
Contractor has a responsibility to assist in determining the exact quantity. For purposes of bidding project assume the higher amounts are required.
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Does the Fence enclosed Pad Mounted Fusible Switchgear/Vault require bollards by each pad corner as shown on the drawing titled “Manhole and Other Details”?
yes
Please provide a specification for the bollard material. Shall the bollard material be hot dip galvanized schedule 80 pipe? (6” dia. x 8’L concrete filled as shown on the plans).
Yes bollard material shall be hot dip galvanized schedule 80 pipe? (6” dia. x 8’L (approx. 5 ft above grade) concrete filled as shown on the plans).
9 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Please provide a specification for the fence and gate, including materials, height of fence, and length of double leaf gate, enclosing the transformer/switchgear.
Provide 8 (eight) feet high chain link fencing. Exterior areas where fencing is to be located and that has easy accessibility with no individuals around daily, shall have a one foot barbed wire supplement at the top. Provide two (2) swing gates for ease of removal of pad mounted equipment. Width of gate(s) is dependent on size of equipment being furnished.
Chain Link Fencing Fabric Fencing fabric shall be minimum 9-gage wire mesh and mesh openings shall not be greater than 2-inches (51 mm) per side. Fence fabric material shall be galvanized steel, Provide PVC coated steel fabric in high visibility areas
Grounding Requirements for Chain Link Fences Metal fences for electrical equipment shall be grounded in accordance with IEEE C2 Section 9. Use exothermic welds (cadwelds). Where plastic coated fabric is used, remove plastic coating where it overlaps the post to be grounded and braze or bolt conductor to post.
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Regarding frame and covers for the Electrical Manhole, note 4 under the detail “Top View Precast Electrical Manhole Detail” on Drawing titled Manhole and Other Details, states the structure is “to be designed to accommodate Heavy 18 wheeled vehicle traffic”. Paragraph 2.2.7 under specification 260553 Manholes, Pull Boxes, Vaults for Electrical Systems states “Specify H20 highway loading for all locations”.
Please confirm the frame and covers for the Electrical Manhole shall be meet H20 loading and not other loading requirements listed under specification 260533 paragraphs 2.2.10, 2.2.11, and 2.2.12.
Electrical Manhole shall meet H20 loading
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Please confirm if the project superintendent can also act as the QC Manger and SSHO, or if each position needs to be individually provided.
The Quality Control Manager (QCM) and the Site Safety and Health Officer (SSHO) should be two separate individuals from the Project Superintendent. These are all independent and separate functions.
Please confirm is Federal, state, and local taxes should be included in proposals?
The Federal Government is tax exempt.
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Please confirm if Federal, state, or local permits will be required on this project?
This is on military property. No State or local permits are necessary. However, all federal jurisdictions apply to the project and will be inspected by qualified federal individuals.
40 10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Please confirm if there are any known hazardous materials on this project?
In the vicinity of Granville Ave crossing South Outer Road, near the existing running track, there used to be a steam treatment facility. The possibility exists that there is some underground piping from that former plant location (near existing water tower no. 3) crossing the roadway and located several feet down (min 4 feet). Some of that piping may have Asbestos Containing Materials (ACM). This is HM and shall be disposed of properly by the contractor. Contractor shall make every effort possible to avoid any existing piping in that area that may have ACM when performing underground primary work. There are no plans available that shows actual locations of the former steam generating facility. (SEE RFI NO. 66 below)
Site Plan Note 1 designates pad mounted switchgear to be “One (1) in four (4) out.”, this is not matched by the Electrical One Line Plan.
Please confirm the desired switchgear configuration?
Switchgear assignments in and out shall match approved submittals. For purposes of this project please follow one-line plan. This is a Performance Work Statement (PWS). A PWS expresses a required outcome for the project. The exact type of switchgear can and may vary from what is indicated.
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Please confirm if it is the governments intent to have all pad mount switchgear assemblies be the same / interchangeable?
All the same.
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Note 22 on Existing Removals Plan states to “….provide switchgear in place of existing cutouts…”. Please confirm if this indicating the need for an additional (SGR-8) pad mounted switchgear?
The existing pole mounted cutout is to be removed. A means of switching out those loads shall be provided.
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Can the government provide a revised Electrical One Line Plan that incorporates work / elements required by drawing notes but not currently shown? (i.e. Note 5 on Existing Removals Plan -refeed of existing OH primary from SGR-2)
Please rephrase specific question. Note No. 5 says: Pole R3 has pole mounted cutouts that are to remain and be refed from the underground primary via Switchgear no. 2 (SGR-2)).
45 10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Note 21 on Site Plan references a lighting plan. Will a lighting plan be provided?
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Specification 312000 Earth Moving, paragraph 2.1.1 states “Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations”. The detail “Typical Duct Bank Trench Detail” on drawing titled Manhole and Other Details, calls out “dense graded crushed stone subbase” for fill around the ductbank. Does all the excavate get removed and replaced with imported dense graded crushed stone subbase? If not, please provide a percentage or volume of material that shall be removed and replaced with imported material, dense graded crushed stone subbase.
Please provide as indicated : “50% shall be removed and replaced with imported material, dense graded crushed stone subbase.”
On drawing titled Manhole and Other Details, the “Typical Duct Bank Trench Detail” notes “existing concrete pavement to remain undisturbed, thickness varies. Not present in all areas”. For bidding purposes, please provide a percentage (i.e. 80% of the ductbank area) where the concrete exists and an average concrete thickness. Specify reinforcing steel, size and spacing, if any. If reinforcing steel is required in the new concrete specify if dowels need to be drilled and epoxied into adjoining concrete, bar size and spacing.
Yes, dowels need to be drilled and epoxied into adjoining concrete, bar size and spacing.
Provide all sizing based on the established standards for the application
80% is a reasonable amount
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
On drawing titled Manhole and Other Details, the “Typical Duct Bank Trench Detail” notes “New bituminous pavement thickness to match existing. Place in two (2) lifts.” Please provide an average depth of bituminous pavement.
8” minimum bituminous in two equal lifts.
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Specification Section 321216 paragraph 2.4.3.1 states “Provide mixes with a history of satisfactory performance in geographical area where Project is located at Joint Base Cape Cod”, and goes on to reference the specified mixes as follows:
2.4.3.2 Base Course: ODOT item 301
MADOT is correct
2.4.3.3 Surface Course: ODOT item 446
Should the above references be MADOT and not ODOT?
10 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
The drawings do not show rebar in the proposed/new ductbank. Please confirm there is no rebar in the proposed/new ductbank.
Appropriately sized rebar for the particular application shall be provided by the general contractor. See item no. 47 above
13 Aug 2018 13 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
What is the minimum 28 day concrete compressive strength of the proposed concrete ductbank?
3,000psi at 28 days
13 Aug 2018 14 Aug 2018 15 Aug 2018 See answer below 15 Aug 2018
Please confirm the required concrete mix for the concrete pavement over the ductbank shown on the drawing titled “Manhole and Other Details” under the section “Typical Duct Bank Trench Detail”; (i.e.
confirm it’s the 4500 psi concrete mix specified under Section 321313 Concrete Paving, or one of the mixes listed under Section 03300 Cast-in-Place Concrete).
Note to Bidders
Concrete for encasement of underground ducts shall be 3000 psi (20 MPa), minimum 28-day compressive strength.
Concrete associated with electrical work for other than encasement of underground ducts shall be 4500 psi (35 MPa), minimum 28-day compressive strength unless specified otherwise.
53) Electrical One Line Plan, Note No. 1 reads:
“Existing Utility Pole OB-1 shall be reconfigured to provide power to SGR-1. This shall be the main source of power accessing the FLIGHTLINE FEEDER.”
ADD: Existing utility pole OB-1 has an existing pole mounted switch (SW-27) which shall remain in place upon completion of the reconfiguration of the pole to connect to SGR-1. SW-27 is sometimes left in the “open” position to isolate portions of the FLIGHTLINE FEEDER and merge certain areas with the EAST FEEDER. Contractor shall provide a pole configuration that insures power is always going to be able to feed new switchgear SGR-1 even if SW-27 is operated to close or open. Reconfiguration of utility pole OB-1 shall include new cross-arm replacements/additions, new cutouts, LA’s, insulators, connectors, etc.
See attached picture of existing utility pole OB-1 below
EXISTING UTILITY POLE OB-1 (See above)
54.) ADD: To Section 260050, General Provisions Electrical Paragraph 1.4.3 As mentioned in paragraph 1.4.1above, the drawings are diagrammatic. They are not intended to show the exact locations of equipment. Contractor shall also field verify the existing cable and conduit sizes feeding the existing transformers to remain and shall match those sizes when installing feeder connections from new switchgear. That applies to both primary and secondary transformer (new and existing) connections. All conduit and cable sizes shall fully comply with the requirements of the National Electrical Code 2017 version.
55.) DELETE Section 260050, General Provisions Electrical, Paragraph 1.3 CONNECTION TO OTHER
EQUIPMENT
1.3.1 Complete manufacturers' detailed shop drawings, and wiring and connection diagrams, of equipment requiring electrical connection will be provided as specified elsewhere. Contractor shall obtain drawings at time they are needed.
1.3.2 Work that must be altered because of Contractor's
failure to obtain shop drawings shall be corrected by the Contractor without additions to contract price.
ADD: Paragraph 1.3.1 Contractor shall provide all manufacturers' detailed shop drawings, wiring and connection diagrams for equipment requiring electrical connection.
56.) NOTE TO CONTRACTOR : Concerning existing overhead cabling on Granville Ave and Izzea Street.
The existing overhead cabling on Granville Ave and Izzea Street is 15KV No. 2 Bare copper conductor.
Contractor shall confirm that size is existing overhead and shall not go below 15kV 1/0 insulated copper EPR 133% Insulation Level with new underground cabling.
57.) Section 01-35-43 Environmental Procedures, Paragraph 8.1 Hazardous Waste Requirements ADD: General: This section includes the handling of all hazardous waste (HW) as generated by the contractor or government hazardous waste encountered by the contractor during the course of this contract. NOTE: In the vicinity of Granville Ave crossing South Outer Road, near the existing running track, there used to be a steam treatment facility. The possibility exists that there is some underground piping from that former plant location (near existing water tower no. 3) crossing the roadway and located several feet down (min 4 feet). Some of that piping may have Asbestos Containing Materials (ACM). This is HM and shall be disposed of properly by the contractor. Contractor shall make every effort possible to avoid any existing piping in that area that may have ACM when performing underground primary work. There are no plans readily available that shows actual locations of the former steam generating facility. (SEE RFI NO. 66 below)
58.) Section 024119 Selective Demolition, Paragraph 8.5
REMOVE: Hazardous materials will be removed by Owner before start of the Work. If suspected hazardous materials are encountered, do not disturb: immediately notify Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.
ADD: Contractor shall be responsible for the proper disposing of asbestos containing material, (ACM) found as a result of digging in the vicinity of Granville Ave crossing South Outer Road, near the water tower and running track. That area, in the past, was a steam production plant. There may be underground piping that has ACM pipe lagging. Contractor shall make every effort to avoid those areas when performing the underground primary work. Contractor shall be responsible for proper disposal of HM disturbed as a result of excavation. (SEE RFI NO. 66 below)
59.) Section 015000 Temporary Facilities and Controls, Paragraph 3.3.1.4 REMOVE: Coordinate elevations of temporary roads and paved areas with permanent roads and paved areas.
ADD: Provide temporary access road for federal/military employees to use to go to their respective buildings while construction of the underground work is taking place.
Coordinate elevations of temporary roads and paved areas with permanent roads and paved areas.
60.) SITE PLAN DRAWING
ADD: Note. 29 General Contractor shall be responsible for soil sampling and soil borings throughout the project to safely and properly locate all underground equipment.
The cost for all removal of necessary soils and provisions for new soil material shall be borne by the contractor.
61.) EXISTING REMOVAL PLAN
In reference to Note 3 on the plan: Contractor shall refeed the existing 225kVA pad mounted transformer that powers building 197. The referenced pole transformers (on the note) were replaced with the pad mounted transformer.
62.) NOTE: BUILDINGS 167, 198 and 191 ARE
SCHEDULED TO BE DEMOLISHED. THE WORK
SHOWN ON PLANS TO POWER UP THESE THREE (3)
FACILITIES CAN BE ELIMINATED. HOWEVER, THE
ASSOCIATED UTILITY POLES, DISTRIBUTION
CABLING, AND ELECTRICAL EQUIPMENT THAT
POWERS THESE FACILITIES SHALL BE REMOVED
AS PART OF THIS PROJECT.
SEE “lighting section and perimeter loop” (H01 Lighting Plan) Spec That document describes the Contractors Responsibility to produce the lighting design And construction
16 Aug 2018 16 Aug 2018 22 Aug 2018 See answer below 22 Aug 2018
Page 12 of Section 265600, issued with Amendment 01, contains a map. On the map it states "Remove and Replace with Sidewalks" with bold dark lines and bold green lines. Is this map simply to show the area or work or something else. Are we to remove and replace sidewalks? If so, what are the bold black lines and bold green lines indicating?
This map is shown in Section 265600 LIGHTING to indicate the areas that are to get new lighting. Contractor shall use this layout to prepare lighting plans for the project. There are no sidewalks to be “Removed & Replaced” as part of this project.
Do not consider the dark black line and green line as part of this project. Use the plan to assess locations for new lighting.
Section 265600 para 1.2.2 discusses the need for "primarily street lighting and other areas shall require sidewalk illumination." However, it also states "Also, provide for exterior lighting for ne "Perimeter Loop" layout per attached plan." What is meant by "Perimeter Loop"?
Are the forty-five (45) exterior street lights and additional eighty-five
(85) exterior sidewalk illumination pole mounted fixtures mentioned in this paragraph additional as part of the "Perimeter Loop" or are these
(45) street lights and (85) sidewalk lights estimates of what will be needed in total for the entire project inclusive of the "Perimeter Loop", streets and sidewalks in the work area?
Paragraph 1.2.2 says: “…..Also, provide for exterior lighting for new “Perimeter Loop” layout per attached plan. Provide for approximately forty-five (45) exterior street lights where designated by lighting professional design. Provide for an additional forty-five (45) exterior sidewalk illumination pole mounted fixtures.”
That’s a total of ninety (90) overall lighting fixtures that are intended to be included for all of the lighting for the work area based on a lighting professional design that is to be accepted by CES and Base Commander. The Perimeter Loop is the area that’s going to be revised by Civil Engineering. CES will be changing sidewalks, etc.
Use that layout when locating the new street lights and pedestrian walkway lights.
16 Aug 2018 16 Aug 2018 22 Aug 2018 See answer below 22 Aug 2018
Please refer to Q&A #40, #57 and #58. Please provide a LF of asbestos piping removal to be carried for the purpose of this bid. If there is no known information provided for the contractor, how is the contractor supposed to provide an accurate competitive bid? Could this be handled as an allowance in the bid?
As a follow up to the reference of asbestos pipe lagging on old steam plant piping, it has since been determined that there was no asbestos containing material (ACM) on any of the outside piping that originated from the old steam plant. The asbestos HM was only located inside the plant itself and has since been removed over 15 years ago. For purposes of this contract, there is no need to include any associated cost for asbestos removal in the vicinity of the project associated with the old steam plant. It’s also been determined that piping associated with the former steam plant was located in excess of 15 feet below grade.
16 Aug 2018 16 Aug 2018 22 Aug 2018 See answer below 22 Aug 2018
Please refer to Q&A #50. The question is referring to reinforcement within the concrete ductbank. The answer refers to Answer #47 which is in reference to concrete paving. Please clarify if reinforcing is required in the ductbank concrete. If so, what are the requirements (size, spacing, etc.)
There is none required in the ductbank
16 Aug 2018 16 Aug 2018 22 Aug 2018 See answer below 22 Aug 2018
Please clarify Answer 60 Note to bidders. Are the soil borings required to classify the soil or to locate the underground utilities. Is the intent of
Contractor shall be responsible for soil borings to assist him/her in locating underground equipment. You’d want to know if you’re dealing with heavy rock material or soils that this note to say the contractor id responsible for all "potholing" to locate existing utilities? It is confusing because utility locating and removal and replacement of soils don't have anything to do with one another.
can easily be removed when locating manholes, etc. Not doing soil borings is the contractor’s prerogative.
Regarding the lighting plan: It is cut off and it is color coded but doesn`t tell us what colors mean.
Please see response in Item no. 65 above
23 Aug 2018 23 Aug 2018 28 Aug 2018 See answer below 28 Aug 2018
RFI #44 response confirms that Pole R3 cutouts are to be refed from SGR-2. This will require a 15KV switch / fuse position at SGR-2 to be the source for refeed to Pole R3. The Electric One Line Plan does not show this refeed. Is this feed to share a position on SGR-2 or does SGR- 2 need an additional switch / fuse position added?
SGR-2 will require an additional switch/fuse position added
23 Aug 2018 23 Aug 2018 28 Aug 2018 See answer below 28 Aug 2018
The same issue is also present at SGR-6. Note #15 on Existing Removals Plan states “Provide new Riser at this pole (OC-23) from underground primary Switchgear..” This will require a 15KV switch / fuse position at SGR-6 to be the source for refeed to Pole OC-23. The Electric One Line Plan does not show this refeed. Is this feed to share position on SGR-6 or does SGR-6 need an additional switch / fuse position added?
SGR-6 will require an additional switch/fuse position added
24 Aug 2018 28 Aug 2018 28 Aug 2018 See answer below 28 Aug 2018
In my review of the bid documents for the above referenced solicitation, on page 5 of 70 Item #4(a) it references that the SF 1442 needs to be signed in the “front and back” of the page ? We realize that block 20B requires the signature but do not see a signature block on the front page. Can you please clarify (see below).
There is no offeror signature on page one of SF1442.
28 Aug 2018 28 Aug 2018 28 Aug 2018 See answer below 28 Aug 2018
Bid form only has two items for the project on the solicitation. As part of Addendum #2 we are asked to provide 3 light fixture options which have different costs. How should these be presented on the form?
Bids shall have a lighting option included that has been identified in the plan as acceptable. Multiple lighting options are not necessary.
Should we carry the lowest in our bid and inched a sheet with the adders for the others?
| PROJECT TITLE: Underground Utilities |
| Date: 28 August 2018 |