Statement_of_Work.pdf

PDF 70 KB Posted

Attached to
Industrial Wastewater Filtration System
Solicitation number
W912PQ-17-T-0033
Issued by

View the file

Other files

File Type Posted
Q&A_V.pdf PDF
Q&A_IV.pdf PDF
Q&A_III.pdf PDF
Q&A_II.pdf PDF
Aerial_View.jpg JPG image
Q&A.pdf PDF
SF_1449_Solicitation_W912PQ-17-T-0033.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

105 AIRLIFT WING (ANG)

ONE MAGUIRE WAY

NEWBURGH NY 12550-5075

1. Background

The water currently being stored within the Industrial Waste (IW) lagoon comes from winter deicing processes, aircraft hangar maintenance and aircraft washes mainly, all through a closed drainage system. Since the recent threshold changes in PFOA/PFOS contaminates we cannot release our IW like in the past. Past processes allowed us to test the water and based on the results, given a release rate from the Town of New Windsor to discharge into the sanitary sewer system where they would then process the water in their treatment facility. The town will only accept a release if the PFOA/PFOS levels are non-detectable.

2. Scope

Contractor shall furnish all tools, testing, parts, material, labor, supplies, permits, equipment and incidentals required to properly perform work outlined below.

All work shall be performed in in a safe manner and shall be accomplished in accordance with all local, state, federal, and safety regulations to include any hazardous waste disposal.

All materials must be submitted and approved prior to installation.

3. Objectives

Contractor will provide a rental filtration system that is capable of removing all PFOA/PFOS from the IW lagoons to a non-detectable level. This will require a sample filtration be accomplished and testing of the filtered IW water be performed. Release rate to the Town of New Windsor treatment facility will be based off the results. The filtration system shall have a processing capability of 0 to 100 gpm and must be able to process 1,000,000 gallons in a 45 day period to include all sampling. The IW water contains trace heavy metals from aircraft maintenance procedures and glycol from winter deicing procedures that must be accounted for when selecting a filtering system.

4. Delivery

Performance shall take place at the 105th Airlift Wing, Stewart ANGB, Newburgh, NY.

5. Government Furnished Property: None

6. Security

Contractors should be aware that this is a Military Installation and that all access to this installation is granted by the 105 AW Base Defense Squadron. The U.S. government will not be held liable for any delays or breach of contract caused by refusal of the 105th AW Base Defense Squadron. If a gate pass is not granted to a contractor allowing the delivery of goods, execution of warranty support, or performance of services please contact the contracting officer.

A contractor’s badge will be issued once the contractor enters the main gate at Stewart Air National Guard Base. All employees are required to have the proper ID (social security card, driver’s license, state ID, immigration card, U.S. Passport, etc.). If they do not have the proper ID, they will be turned away. Vendors should be aware that Anti- Terrorism Force Protection Measures are applicable to this contract. Vendors will be briefed on these measures by Base Defense personnel if recurring or long term access is required to Stewart ANG Base. Otherwise you will be escorted at all times by a member of Stewart ANG Base.

7. Safety Requirements

The contractor shall comply with all Occupational Safety and Health Act (OSHA), federal, state, and local laws, regulations, and requirements regarding safety, as applicable to the services provided under this contract. In the event safety laws or regulations change during the term of this contract, the contractor is required to comply as such laws come into effect.

File details come from the government source that posted it. Updated .