WKVB022017 Water Distribution System Repair 77875 Gabreski ANGB, Westhampton Beach, New York
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Preliminary Work Schedule
Utility Outage Requests
Utility Connection Requests
Excavation Permits
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The project is to repair/replace the existing potable water distribution system. Excavate and trench ground to the pipe as appropriate for service level. Provide valves, shutoff, seals, pumps as necessary.
The Contractor shall refer to the contract documents (both plans and specifications) for the complete scope of the project.
1.2.2 Location
The work is located at the Gabreski Air National Guard Base in Westhampton Beach, New York, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 CONTRACT DRAWINGS
The following drawings accompany this specification and are a part thereof.
Two sets of full size contract drawings, maps, and specifications will be furnished to the Contractor without charge. Reference publications will not be furnished. Immediately check furnished drawings and notify the Government of any discrepancies.
1.4 WORK RESCHEDULING
Contractor shall allow time in their anticipated schedule to submit and procure all required permits for the construction and site work for the project. The schedule shall be submitted to the Government for approval prior to the start of construction activities.
SECTION 01 11 00 Page 1
WKVB022017 Water Distribution System Repair 77875
Normal duty hours for work are from 7 a.m. to 4 p.m., Monday through Friday. Requests for additional work requires written approval from the Contracting Officer 7 days in advance of the proposed work period.
1.5 OCCUPANCY OF PREMISES
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.6 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.7 ON-SITE PERMITS
1.7.1 Utility Outage Requests and Utility Connection Requests
Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 21 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.7.2 Borrow, Excavation, Welding, and Burning Permits
ACTIVITY SUBMISSION DATE SUBMISSION FORM
Excavation Permits 14 calendar days prior to work
Base Safety and Environmental Office
Post permits at a conspicuous location in the Contractor's construction trailer.
Burning of trash or rubbish is not permitted on project site.
1.8 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with
SECTION 01 11 00 Page 2
WKVB022017 Water Distribution System Repair
77875
Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 72 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.8.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.9 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Pursuant to Contract Clause 11 FAR 52.245-1, Government Property 11 , the Government will furnish the following materials and equipment for installation by the Contractor:
( None.
1.9.1 Delivery Schedule
Notify the Contracting Officer in writing at least 30 calendar days in advance of the date on which the materials and equipment are required.
Pick up materials and equipment no later than 30 calendar days after such date.
1.10 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 2 miles of the construction site.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
1.11 Antiterrorism / Operations Security / Information Protection
1.11.1 Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area.
The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR).
SECTION 01 11 00 Page 3
WKVB022017 Water Distribution System Repair
The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1.11.2 For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.11.3 AT Level I Training. This standard language is for contractor employees with an area of performance within a Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I Awareness Training is available through ADLS by completing the Force Protection CBT.
1.11.4 For contracts that require an OPSEC Plan. The contractor shall develop an OPSEC Plan and provide it to the COR or KO within 30 calendar days of contract award to be reviewed and approved by the responsible Government OPSEC officer, per AFI 10-701, Operations Security. This Plan shall include the government's critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it. For the contractor to effectively comply with OPSEC provisions of the contract, the organization will provide the following guidance:
(1) Organization’s Critical Information; (2) Adversaries’ collection threat information as it applies to the organization’s mission and the contract;
(3) Operations Security guidance; and (4) Specific OPSEC measures the organization requires (as appropriate).
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
- - End of Section - -