This solicitation document describes a federal contract opportunity for construction services. The Army Corps of Engineers intends to issue a solicitation to construct an Advanced Skills Training Facility Annex and HAZMAT Facilities at Fort Bragg, North Carolina. The contractor shall provide all labor, materials, equipment, and services necessary to construct approximately 24,500 square feet of administrative offices, classrooms, conference rooms, lounges, instructional laboratories, locker rooms, storage, and a 1,200 square foot refabricated Hazardous Material Storage building. The facilities will include built-in fire suppression, energy management, communications, security, and ventilation systems. The project also includes site work such as utilities, parking, lighting, and landscaping. Sustainability measures complying with LEED Silver will be incorporated. The facilities are to be designed for a minimum 40-year life in accordance with Unified Facilities Criteria.

View the file

Other files for this federal contract opportunity

Other files attached to SOF Advanced Skills Training Facility Annex and HAZMAT Facilities, newest first.
File Type Posted
PN79439-2 SOF TST ANNEX_DRAWINGS VOL2of3_AM-002_2022-09-09.pdf PDF
PN79439-2 SOF TST ANNEX_DRAWINGS VOL2of3_AM-002_2022-09-09.pdf PDF
PN79439-2 SOF TST ANNEX_DRAWINGS VOL1of3_AM-002_2022-09-09.pdf PDF
W912PM22R00120002 PN 79439.2.pdf PDF
W912PM22R00120002 PN 79439.2 Conformed Copy.pdf PDF
PN79439-2 SOF TST ANNEX_DRAWINGS VOL3of3_AM-002_2022-09-09.pdf PDF
Conformed-AMDT002-79439.2-SOF-Annex-Tech-Summary-Changes.pdf PDF
PN79439-2_Drawing_T-100_AM-01_2022-08-31.pdf PDF
W912PM22R00120001 PN 79439.2.pdf PDF
PN79439-2 SOF TST ANNEX_SPECS_AM-01_2022-08-31 (.pdf PDF
PN79439-2_SOF TST ANNEX_BIDDER INQUIRY RESPONSES_2022-08-31.pdf PDF
PN79439-2 SOF TST ANNEX_DRAWINGS_AM-01_2022-08-31.pdf PDF
Site Visit 79439.2 24 August 2022.pdf PDF
PN79439-2_Drawings_RTA_Vol2of3_Aug-2022 (LOCKED).pdf PDF
VOL IV CE PN79439 2_FFE SID Package_RTA_Aug 2022.pdf PDF
PN79439-2_Specifications_Ready to Advertise_Vol2.pdf PDF
PN79439-2_Specifications_Ready to Advertise_Vol3.pdf PDF
W912PM22R0012 - 79439.2 RFP_SOF Technical Support Training Annex and Hazmat Storage.pdf PDF
PN79439-2_Drawings_RTA_Vol1of3_Aug-2022 (LOCKED).pdf PDF
PN79439-2_Drawings_RTA_Vol3of3_Aug-2022 (LOCKED).pdf PDF
PN79439-2_Specifications_Ready to Advertise_Vol1.pdf PDF
NAVFAC-USACE PPQ (fillable).pdf PDF
PN79439-2_Drawings_RTA_Vol2of3_Aug-2022 (LOCKED).pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. - W912PM22R0012 Date: 01-SEPTEMBER-2022 Project Title – 79439.2, SOF Annex and HAZMAT Facility Amendment No. 001

SUMMARY OF CHANGES

1. CHANGES TO SPECIFICATIONS. Attached hereto are revised and sections to the specifications.

A. REVISED SECTIONS. The following revised sections replace like numbered sections.

00 10 00 – SOLICITIATION CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

o Revisions are bookmarked and notated with “AM-001” to reflect the responses provided to the Bidder Inquiries.

01 33 29 – SUSTAINABILITY REQUIREMENTS AND REPORTING

o Revisions are bookmarked and notated with “AM-001” to reflect the responses provided to the Bidder Inquiries.

o LEED CHECKLIST Revisions are bookmarked and notated with “AM-001” to reflect the responses provided to the Bidder Inquiries.

2. CHANGES TO DRAWINGS. Attached hereto are revised drawing sheets. The revision tracker in the Title Block of each sheet is populated to reflect the current Amendment Number and issue date.

A. REVISED DRAWINGS (ISSUED):

CG101 CIVIL – GRADING AND DRAINAGE PLAN A

CE101A CIVIL – INITIAL EROSION CONTROL PLAN A

CE101B CIVIL – INITIAL EROSION CONTROL PLAN B

CE102A CIVIL – INTERMEDIATE EROSION CONTROL PLAN A

CE102B CIVIL - INTERMEDIATE EROSION CONTROL PLAN B

CE504 CIVIL – EROSION CONTROL DETAILS SEDIMENT BASIN AND BAFFELS

o These drawings are provided with revision clouds and “Amendment 001” notations, per the updates made for the E&SC Permit package submitted to NCDEQ.

T-100 TELECOMMUNICATIONS – TELECOMMUNICATION SITE PLAN

o Revision clouds and “Amendment 001” notations provided as Bidder Inquiry response.

…end of summary…

PN79439.2 SOF Technical Support Training Annex, Ft. Bragg, NC W912PM22R0012

SECTION 00 10 00 Page 1 of 7

SECTION 00 10 00 SOLICITATION CONTRACT LINE ITEM

NUMBER (CLIN) SCHEDULE

SECTION 00 10 00 Page 2 of 7

SOLICITATION CONTRACT LINE ITEM

NUMBER (CLIN) SCHEDULE

CLIN Description Unit Quantity Unit Price Total

BASE BID: Technical Support Training Annex Building Construction Complete.

LS 1

BASE BID: Site Development Outside Five Foot (5’) Line. All work required to fence the compound and provide gravel hardstand, gravel POV parking, and gravel access drive.

Note: The infrastructure for all utilities to five feet (5’) of the building shall be provided by the Utility Providers and not included in the Base Bid.

LS 1

BASE BID: Metal Poles, Bases, and Conduit for

CCTV.

LS 1

0004 BASE BID: HAZMAT Storage Building.

LS 1

OPTIONAL BID ITEM 01:

Concrete Pad for Modular Trailers.

LS 1

OPTIONAL BID ITEM 02:

Provide asphalt pavement and striping for hardstand.

LS 1

OPTIONAL BID ITEM 03:

Provide asphalt pavement, curbing, and striping for POV Parking. LS

SECTION 00 10 00 Page 3 of 7

OPTIONAL BID ITEM 04:

Provide asphalt pavement, curbing, and striping for access drive.

LS 1

0009 NOT USED. LS 1

OPTIONAL BID ITEM 06: FF&E

Purchase and installation.

(Information only, include CLINs 0010A and 0010B only once in Totals below).

LS 1

0010A OPTIONAL BID ITEM 06A:

FF&E Purchase.

LS 1

0010B OPTIONAL BID ITEM 06B:

FF&E Installation.

LS 1

OPTIONAL BID ITEM 07:

Audio-Visual (A/V) Purchase and Installation of Equipment. (Information only, include CLINs 0011A and 0011B only once in Totals below)

Note: A/V infrastructure is to be included in CLIN 0001 Base Bid.

LS 1

0011A

OPTIONAL BID ITEM 07A:

Audio-Visual Equipment Purchase.

LS 1

0011B

OPTIONAL BID ITEM 07B:

Audio-Visual Equipment Installation.

LS 1

SECTION 00 10 00 Page 4 of 7

OPTIONAL BID ITEM 08:

Access Control System (ACS) Purchase and Installation of Equipment. (Information only, include CLINs 0012A and 0012B only once in Totals below)

Note: ACS infrastructure is to be included in CLIN 0001 Base Bid.

LS 1

0012A

OPTIONAL BID ITEM 08A:

Access Control System Equipment Purchase.

LS 1

0012B

OPTIONAL BID ITEM 08B:

Access Control System Equipment Installation.

LS 1

OPTIONAL BID ITEM 09:

CCTV System Purchase and Installation of Equipment. (Information only, include CLINs 0013A and 0013B only once in Totals below).

Note: CCTV infrastructure is to be included in CLIN 0003 Base Bid.

LS 1

0013A

OPTIONAL BID ITEM 09A:

CCTV System Equipment Purchase.

LS 1

0013B

OPTIONAL BID ITEM 09B:

CCTV System Equipment Installation.

SECTION 00 10 00 Page 5 of 7

OPTIONAL BID ITEM 10:

Integrated Commercial Intrusion Detection System (ICIDS) Purchase and Installation of Equipment.

(1) The Contractor shall purchase and install a complete security alarm system in the required CAAs.

This includes the sensing devices, annunciators, batteries, and all associated equipment necessary to make a complete and useable system. A conduit system with junction boxes and signal wiring shall be provided for ICIDS back to the main communication room.

Provisions shall include dedicated power circuits, communications connections, raceways, and signal wiring for each device. Each security alarm system must transmit the alarm signals to the I2MC Central Control Console over dry copper and/or fiber cables.

SECTION 00 10 00 Page 6 of 7

(Cont ’d)

2) The intrusion detection system shall be the current Army Standard ICIDS-V, manufactured by DAQ.

Contractor will design, install, and provide programming based on system specifications, Ft. Bragg Physical Security Office, and Ft. Bragg Installation design guidelines.

(Information only, include CLINs 0014A and 0014B only once in Totals below).

Note: ICIDS infrastructure is to be included in CLIN 0001 Base Bid.

0014A

OPTIONAL BID ITEM 10A:

Integrated Commercial Intrusion Detection System (ICIDS) Equipment Purchase.

LS 1

0014B

OPTIONAL BID ITEM 10B:

Integrated Commercial Intrusion Detection System (ICIDS) Equipment Installation.

LS 1

TOTAL BASE BID ITEMS CLINs 0001-0004

TOTAL AMOUNT OF OPTIONAL BID ITEMS CLINs 0005-0014

TOTAL BID ITEMS CLINs 0001 – 0014

PROPOSED CONTRACT DURATION:

SECTION 00 10 00 Page 7 of 7

NOTICE TO BIDDERS

NOTE 2:

THE GOVERNMENT RESERVES THE RIGHT TO EXERCISE OPTIONAL BID ITEMS 1-10

(CLIN ITEMS 0005 - 0014), WITHIN 180 CALENDAR DAYS OF NOTICE TO

PROCEED.

NOTE 3:

THE EXERCISE OF OPTIONAL BID ITEMS 1-10 (CLIN ITEMS 0005 - 0014),

SHALL BE SUBJECT TO THE AVAILABILITY OF FUNDS.

NOTE 1:

FOR OPTIONAL BID ITEMS 1-10 (CLIN ITEMS 0005 - 0014), IF EXERCISED,

THE PERIOD OF PERFORMANCE SHALL NOT BE EXTENDED BEYOND THE ORIGINAL

CONTRACT DURATION OF 365 548 CALENDAR DAYS.

PERFORMANCE OF ANY AWARDED OPTIONAL BID ITEMS SHALL RUN CONCURRENTLY

WITH THE BASE BID ITEMS CONTRACT DURATION SO THAT THE PERIOD OF

PERFORMANCE SHALL NOT EXCEED 365 548

CALENDAR DAYS.

***AM-001\*** ***/AM-001***

***AM-001\*** ***/AM-001***

SOF Tech Support Training Annex PN79439.2 Fort Bragg, North Carolina

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 29

SUSTAINABILITY REQUIREMENTS AND REPORTING

02/21 providing sustainability documentation for Guiding Principles Validation (GPV) and Third Party Certification (TPC)

PART 1 GENERAL

1.1 REFERENCES

1.2 SUMMARY

1.3 SUBMITTALS

1.4 GUIDING PRINCIPLES VALIDATION (GPV)

1.4.1 Sustainability Action Plan

1.4.2 Calculations

1.5 SUSTAINABILITY SUBMITTALS

1.5.1 High Performance Sustainable Building (HPSB) Checklist

1.5.1.1 HPSB Checklist Submittals

1.5.2 "S" Submittals for Sustainability Documentation

1.5.3 Sustainability eNotebook

1.5.3.1 Sustainability eNotebook Format

1.5.3.2 Sustainability eNotebook Submittal Schedule

1.6 DOCUMENTATION REQUIREMENTS

1.6.1 Commissioning (Cx)

1.6.2 Energy Efficient Products

1.6.3 Building-level Power Metering

1.6.3.1 Construction Submittal Documentation

1.6.4 Indoor Water Use

1.6.5 Indoor Water Metering

1.6.5.1 Construction Submittal Documentation

1.6.6 Outdoor Water Use

1.6.6.1 Construction Submittal Documentation

1.6.7 Outdoor Water Meters

1.6.7.1 Construction Submittal Documentation

1.6.8 Moisture Control

1.6.8.1 Construction Submittal Documentation

1.6.9 Reduce Volatile Organic Compounds (VOC) (Low-Emitting

Materials)

1.6.10 Indoor Air Quality During Construction

1.6.11 Recycled Content

1.6.11.1 Construction Submittal Documentation

1.6.12 Bio-Based Products

1.6.13 Waste Material Management (Recycling – Construction)

1.6.14 Additional Sustainability Requirements

1.6.14.1 Third Party Certification (TPC) Documentation

1.6.14.1.1 TPC Registration

1.6.15 Additional Sustainability Requirements

PART 2 PRODUCTS

SECTION 01 33 29 Page 1

READY TO ADVERTISE

PART 3 EXECUTION

3.1 SUSTAINABILITY COORDINATION

3.2 TABLE 3-1 VOLATILE ORGANIC COMPOUNDS (VOC) (LOW EMITTING

MATERIALS) REQUIREMENTS

-- End of Section Table of Contents --

SECTION 01 33 29 Page 2

SECTION 01 33 29

SUSTAINABILITY REQUIREMENTS AND REPORTING

02/21

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

COUNCIL ON ENVIRONMENTAL QUALITY (CEQ) (WHITE HOUSE)

HPSB Guiding Principles (2016) Guiding Principles for Sustainable Federal Buildings and Determining Compliance with the Guiding Principles for Sustainable Federal Buildings

INTERNATIONAL CODE COUNCIL (ICC)

ICC IgCC (2018) International Green Construction Code

U.S. DEPARTMENT OF AGRICULTURE (USDA)

FSRIA 9002 Farm Security and Rural Investment Act Section 9002 (USDA BioPreferred Program)

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 1-200-02 (2020; with Change 1, 2020) High Performance and Sustainable Building Requirements

UFC 3-600-01 (2016; with Change 6, 2021) Fire Protection Engineering for Facilities

U.S. DEPARTMENT OF ENERGY (DOE)

Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System (FEMP)

U.S. GREEN BUILDING COUNCIL (USGBC)

LEED v4 BD+C LEED v4 Building Design and Construction

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 247 Comprehensive Procurement Guideline for Products Containing Recovered Materials

1.2 SUMMARY

This section includes requirements for Sustainability documentation and reporting submittals per the federally mandated High Performance and

SECTION 01 33 29 Page 3

Sustainable Building (HPSB) or HPSB "Guiding Principles" (GP), and Third Party Certification (TPC) requirements, in accordance with UFC 1-200-02 High Performance and Sustainable Building Requirements, and other identified requirements.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Preliminary High Performance and Sustainable Building Checklist; G

Sustainability Action Plan; G

Preliminary Sustainability eNotebook; G

SD-06 Test Reports

SD-11 Closeout Submittals

Final High Performance and Sustainable Building Checklist; G

Final Sustainability eNotebook; G

Amended Final Sustainability eNotebook; G

Amended Final High Performance and Sustainable Building Checklist;

G

1.4 GUIDING PRINCIPLES VALIDATION (GPV)

Provide the following sustainability activities and documentation to verify achievement of HPSB Guiding Principles Validation (GPV):

a. Analysis of each Guiding Principle Requirement and how project complies. Include final government approved narrative(s) in the HPSB Checklist submittal. Multiple checklists indicate multiple buildings that require individual HPSB Checklist tracking.

b. No changes to the HPSB Checklist are allowed without approval from the Contracting Officer, in accordance with Section 01 33 00 SUBMITTAL REQUIREMENTS. Immediately bring to the attention of the Contracting Officer any project changes that impact meeting the approved HPSB Guiding Principles Requirements for this project. Demonstrate the change will not increase the life-cycle cost and maintains or improves the building performance.

c. Documentation of all work required to incorporate the applicable HPSB Guiding Principles requirements indicated on the HPSB Checklist and in this contract, including all "S" submittals.

d. Sustainability Action Plan.

SECTION 01 33 29 Page 4

e. Construction related documentation for the project Sustainability eNotebook and keep updated with regularly-scheduled Construction Quality Control Meetings. Include construction related documentation containing the following components:

(1) HPSB Checklist(s)

(2) Sustainability Action Plan

(3) Documentation illustrating HPSB Guiding Principles Requirements compliance, including "S" submittals

1.4.1 Sustainability Action Plan

Include the following information in the Sustainability Action Plan:

a. Analysis of each HPSB Guiding Principles Requirement and how project will comply. Final government approved narrative(s) must be included in the HPSB Checklist submittal.

b. Name and contact information for: Contractor's Point of Contact (POC) ensuring sustainability goals are accomplished and documentation is assembled. For TPC that include on-site visit by third party representative, provide list of required attendees.

c. Indoor Air Quality plan.

1.4.2 Calculations

Provide all calculations, product data, labels and product certifications required in this specification to demonstrate compliance with the HPSB Guiding Principles Requirements.

1.5 SUSTAINABILITY SUBMITTALS

Provide HPSB Checklist and other documentation in the Sustainability eNotebook to indicate compliance with the sustainability requirements of the project.

1.5.1 High Performance Sustainable Building (HPSB) Checklist

Provide construction documentation that provides proof of, and supports compliance with, the completed HPSB Checklist.

1.5.1.1 HPSB Checklist Submittals

Submit updated HPSB Checklist with each Sustainability eNotebook submittal. Include the final HPSB Checklist(s) with the interim DD1354 Real Property Record Submittal.

1.5.2 "S" Submittals for Sustainability Documentation

"S" submittals are the sustainability documentation requirements cited in the various sections of this contract. Submit the GPV and TPC sustainability documentation required in this section as "S" submittals in all affected UFGS Sections.

a. Highlight GPV and TPC compliance data in "S" submittal.

SECTION 01 33 29 Page 5

b. Add "S" submittals to the Sustainability eNotebook only after submittal approval, and bookmark them as required in paragraph SUSTAINABILITY ENOTEBOOK below.

c. Ensure all approved "S" submittals are included in each Sustainability eNotebook submittal.

1.5.3 Sustainability eNotebook

The Sustainability eNotebook is an electronic organizational file that serves as a repository for all required sustainability submittals. To support documentation of compliance with an approved HPSB and TPC checklist, provide and maintain a comprehensive and current Sustainability eNotebook. Include all required data in Sustainability eNotebook, to support full compliance with the HPSB Guiding Principles Requirements, including:

a. HPSB checklist

b. Sustainability Action Plan

c. Calculations

d. Labels

e. "S" submittals

f. Certifications, assessments, or validations and compliance report

g. TPC documentation required in paragraph THIRD PARTY CERTIFICATION

(TPC).

1.5.3.1 Sustainability eNotebook Format

Provide Sustainability eNotebook in the form of an Adobe PDF file;

bookmark each HPSB Guiding Principles Requirement, TPC requirement, and sub-bookmark at each document. Match format to HPSB Guiding Principles numbering system indicated herein. Maintain up-to-date information, such as spreadsheets, templates, with each current submittals. For TPC projects, provide a second Table of Contents using TPC numbering system, for maintaining documentation unique to TPC.

Contracting Officer may deduct from the monthly progress payment accordingly if Sustainability eNotebook information is not current and on track per project goals.

1.5.3.2 Sustainability eNotebook Submittal Schedule

Provide Sustainability eNotebook Submittals at the following milestones of the project:

a. Preliminary Sustainability eNotebook

Submit preliminary Sustainability eNotebook with updated Preliminary High Performance and Sustainable Building Checklist and TPC checklist at the first post award meeting in accordance with Section 01 30 00

ADMINISTRATIVE REQUIREMENTS.

b. Construction Quality Control Meetings.

SECTION 01 33 29 Page 6

Provide up-to-date GP and TPC documentation in the Sustainability eNotebook and TPC Online tool for each meeting.

c. Final Sustainability eNotebook

Submit updated Sustainability eNotebook with updated Final High Performance and Sustainable Building Checklist with TPC Checklist at Beneficial Occupancy Date (BOD). Final progress payment retainage may be held by Contracting Officer until Final Sustainability construction phase documentation is complete.

d. Amended Final Sustainability eNotebook

Amend and resubmit the Amended Final Sustainability eNotebook with Amended Final High Performance and Sustainable Building Checklist and amended TPC Checklist, to include post-occupancy corrections, updates, and requirements. Final progress payment retainage may be held by Contracting Officer until amended final sustainability documentation is complete. Submit the Amended Final Sustainability eNotebook Submittal on DVDs to the Contracting Officer no later than 30 days after final GP, TPC determination.

1.6 DOCUMENTATION REQUIREMENTS

a. Incorporate each of the following HPSB Guiding Principles requirements into project and provide documentation that proves compliance with each listed requirement. Items below are organized by HPSB Guiding Principles . For life-cycle cost analysis requirements, one document with all analyses is acceptable, with Contracting Officer approval.

b. For each of the following paragraphs that require the use of products listed on Government-required websites, provide documentation of the process used to select products, or process used to determine why listed products do not meet project performance requirements.

1.6.1 Commissioning (Cx)

Develop and incorporate Commissioning requirements into the documents, in accordance with Section 01 91 00.15 10 TOTAL BUILDING COMMISSIONING.

1.6.2 Energy Efficient Products

Provide only energy-using products that are Energy Star rated or have Federal Energy Management Program (FEMP) recommended efficiency. Where Energy Star or FEMP recommendations have not been established, provide most efficient products that are life-cycle cost-effective. Provide only energy using products that meet FEMP requirements for low standby power consumption. Energy efficient products can be found at:

https://www.energy.gov/eere/femp/federal-energy-management-program and http://www.energystar.gov/ .

For construction submittal documentation, provide proof that product is labeled energy efficient and complies with the cited requirements.

1.6.3 Building-level Power Metering

Provide building-level meters for electricity, natural gas, and steam

SECTION 01 33 29 Page 7 where applicable.

1.6.3.1 Construction Submittal Documentation

Provide manufacturer's data validating compatibility with base-wide system and component advanced meter requirements.

1.6.4 Indoor Water Use

Provide Construction Documentation proof that fixtures are labeled EPA WaterSense, for products available with EPA WaterSense labeling; for all other fixtures, proof they comply with EPA WaterSense efficiency requirements.

1.6.5 Indoor Water Metering

Provide building-level meters for potable water use. Provide the requirements cited in the following paragraphs:

1.6.5.1 Construction Submittal Documentation

Provide manufacturer's data validating compatibility with base-wide system and component advanced meter requirements.

1.6.6 Outdoor Water Use

Where new irrigation is required, provide only non-potable sources.

Provide the requirements cited in the following paragraphs:

1.6.6.1 Construction Submittal Documentation

Provide manufacturer's data validating compatibility with base-wide system and component advanced meter requirements.

1.6.7 Outdoor Water Meters

Provide meters for outdoor systems that use potable water. Provide the requirements cited in the following paragraphs:

1.6.7.1 Construction Submittal Documentation

Provide manufacturer's data validating compatibility with base-wide system and component advanced meter requirements.

1.6.8 Moisture Control

Provide the following:

1.6.8.1 Construction Submittal Documentation

Ensure construction materials are separated and protected in accordance with other sections in this contract document, with adequate humidity controls during construction. In accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA, includes plan for ongoing building moisture control.

Coordinate with the moisture control requirements of Section 01 45 00.00 10

QUALITY CONTROL.

SECTION 01 33 29 Page 8

1.6.9 Reduce Volatile Organic Compounds (VOC) (Low-Emitting Materials)

Meet the requirements of Table 3-1 at the end of this specification.

For Construction submittal documentation, provide certifications or labels that demonstrate compliance with cited requirements, based on the attached

TABLE 3-1.

1.6.10 Indoor Air Quality During Construction

Prior to construction, create indoor air quality plan. Develop and implement an IAQ construction management plan during construction and flush building air before occupancy.

For new construction and for renovation of unoccupied existing buildings, meet the requirements of ICC IgCC 1001.3.1.5 (10.3.1.4) Indoor Air Quality (IAQ) Construction Management.

Provide documentation showing that after construction ends and prior to occupancy, HVAC filters were replaced and building air was flushed out in accordance with the cited standard.

1.6.11 Recycled Content

Comply with 40 CFR 247 . Refer to:

https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for assistance identifying products cited in 40 CFR 247 . Selected products must comply with non-proprietary requirements of the Federal Acquisition Regulation and must meet performance requirements.

1.6.11.1 Construction Submittal Documentation

a. Provide manufacturers' documents stating the recycled content by material, or written justification for claiming one of the exceptions allowed on the cited website.

b. Substitutions: Submit for Government approval for proposed alternative products or systems that provide equivalent performance and appearance and have greater contribution to project recycled content requirements. For all such proposed substitutions, submit with the Sustainability Action Plan accompanied by product data demonstrating equivalence.

c. In order to complete compliance with FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items, refer to submittal requirement for recycled/recovered material content in Section 01 78 00 CLOSEOUT SUBMITTALS.

1.6.12 Bio-Based Products

Provide products and materials composed of the highest percentage of bio-based materials (including rapidly renewable resources and certified sustainably harvested products), consistent with FSRIA 9002 USDA BioPreferred Program, to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user and when available at a reasonable cost. Use only supplies and materials of a type and quality that conform to applicable specifications and standards.

SECTION 01 33 29 Page 9

Comply with FSRIA 9002 USDA BioPreferred Program. Refer to www.biopreferred.gov for the product categories and BioPreferred Catalog.

Selected products must comply with non-proprietary requirements of the Federal Acquisition Regulation and must meet performance requirements.

Provide the following documentation:

a. USDA BioPreferred label for each product; for bio-based products used on project but not listed with BioPreferred program, provide bio-based content and percentage.

b. In order to complete compliance with FAR 52.223-1 Biobased Product Certification, refer to submittal requirement for biobased products in Section 01 78 00 CLOSEOUT SUBMITTALS, paragraphs CERTIFICATION OF EPA DESIGNATED ITEMS and CERTIFICATION OF USDA DESIGNATED ITEMS.

1.6.13 Waste Material Management (Recycling – Construction)

Divert demolition and construction debris in accordance with Section

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL.

1.6.14 Additional Sustainability Requirements

Provide the additional sustainability requirements cited in this paragraph.

1.6.14.1 Third Party Certification (TPC) Documentation

Third Party Certification certificate, assessment, or validation, and compliance report requirements are in addition to all requirements under header above GUIDING PRINCIPLES VALIDATION (GPV).

1.6.14.1.1 TPC Registration

This project has been designed for, and must be constructed to be "certifiable" under the LEED v4 BD+C for New Construction rating system at the Certified level equivalent rating. Project is not pursuing formal registration with the TPC Organization. Provide construction related sustainability documentation, in the format required by the TPC Organization, to the Contracting Officer for approval. Execute the following:

a. Refer to TPC Checklist at the end of this specification section.

(Multiple checklists indicate multiple buildings that require TPC.)

b. Immediately bring to the attention of the Contracting Officer any project changes that impact meeting the approved TPC Requirements for this project. Demonstrate the change will not increase the life-cycle cost and maintains or improves the building performance.

c. Complete all work required to incorporate the applicable TPC Requirements.

d. Maintain the construction related information in the Sustainability eNotebook pertaining to additions and changes to the approved sustainability requirements. Maintain the Sustainability eNotebook in electronic format. For more explanation, refer to paragraph SUSTAINABILITY eNOTEBOOK. Provide the following components in the Sustainability eNotebook, in addition to the GPV components above:

(1) TPC Checklist

SECTION 01 33 29 Page 10

(2) Provide construction documentation required to achieve the equivalent of third party certification

e. Provide the following information in the Sustainability Action Plan.

Provide this TPC information in addition to the GPV Action Plan items above:

(1) Planned method to achieve each TPC equivalent requirement.

(2) For each TPC requirement that is attempted but not achieved, provide narrative explaining how mission or activity precludes achieving specific sustainability requirement or goal. Provide analysis of particular requirement and level to which project is able to comply.

(3) Provide name and contact information for: Sustainability Point of Contact (POC) and other names of sustainability professionals responsible for ensuring TPC sustainability goals are accomplished and documentation is assembled. Sustainability POCs are also responsible for ensuring GPV required in paragraph GUIDING PRINCIPLES VALIDATION (GPV) above.

f. Bear all costs associated with construction changes that affect sustainability design requirements, constructing, demonstrating, and documenting that project complies with approved TPC requirements, including but not limited to:

(1) TPC coordination with Government's AE and other consultants, and management for construction related documentation.

(2) Construction work required to incorporate TPC requirements.

(3) Submittals required to demonstrate compliance with Government approved TPC checklists.

(4) Documentation illustrating compliance with TPC requirements.

g. Provide all calculations, product data, and certifications, assessments, or validations required in this contract to demonstrate compliance with the TPC Requirements of this section.

1.6.15 Additional Sustainability Requirements

The following requirements are included, as required by the project scope or the applied sustainability Third Party Certification program:

Refer to SECTION 01 33 29 APPENDIX A - SUSTAINABLE DESIGN REQUIREMENTS

LEED V4 BD+C

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 SUSTAINABILITY COORDINATION

Provide sustainability focus and coordination at all meetings to achieve

SECTION 01 33 29 Page 11 sustainability goals. Coordinate meeting requirements with other UFGS Sections meeting requirements in this project. Ensure the designated TPC accredited sustainability professional responsible for GP and TPC documentation participates in these meetings to coordinate documentation completion. Review GP and TPC sustainability requirements, HPSB Checklist and TPC documentation, Sustainability Action Plan, and completeness status of Sustainability eNotebook, and equivalent TPC status at the following meetings:

a. Pre-Construction Conference

b. Construction Quality Control Meetings

g. Facility Turnover Meetings

Conduct review no later than 60 days before final turnover and identify any outstanding issues that affect correct completion of all documentation, and actions that will achieve requirements. Conduct corrective actions prior to turnover, to ensure all requirements are achieved.

SECTION 01 33 29 Page 12

3.2 TABLE 3-1 VOLATILE ORGANIC COMPOUNDS (VOC) (LOW EMITTING MATERIALS)

REQUIREMENTS

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

Source: ICC IgCC Chapter 8 (Materials) (Interior Applications Only)

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

EMISSIONS

REQUIREMENTS

Adhesives and Sealants

CDPH/EHLB/Standard method V1.1 (Ca lifornia Section 01350) (Use "office" or "classroom" space limits for all applications) or Adhesives (carpet, resilient, wood flooring; base cove; ceramic tile; drywall and panel; primers) Sealants (acoustical;

firestop; HVAC Air duct; primers) Caulks

SCAQMD Rule 1168 (Use "other" category for HVAC duct sealant) (for firestop adhesive, UFC 3-600-01 overrides conflicting requirements)

Aerosol adhesives Section 3 of Green Seal Standard GS-36 (except:

cleaners, solvent cements, and primers used with plastic piping and conduit in plumbing, fire suppression, and electrical systems; HVAC air duct sealants when the application space air temp is less than 40 F (4.5 C).

SECTION 01 33 29 Page 13

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

Source: ICC IgCC Chapter 8 (Materials) (Interior Applications Only)

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

EMISSIONS

REQUIREMENTS

Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Flat and nonflat, nonflat high-gloss, specialty, basement specialty, fire-resistive, floor, low-solids, rust preventative, wood, reflective wall coatings;

concrete/masonry sealers; primers;

sealers;

undercoaters;

shellacs (clear and opaque);

stains; varnishes;

conjugated oil varnish; lacquer;

clear brushing lacquer

Green Seal Standard GS-11

SECTION 01 33 29 Page 14

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

Source: ICC IgCC Chapter 8 (Materials) (Interior Applications Only)

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

EMISSIONS

REQUIREMENTS

Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or Concrete curing compounds; dry fog, faux finishing, graphic arts (sign paints), industrial maintenance, mastic texture, metallic pigmented, multicolor, recycled coatings;

pretreatment wash primers, reactive penetrating sealers; specialty primers, wood preservatives, and zinc primers

California Air Resources Board (CARB) Suggested Control Measure for Architectural Coatings or SCAQMD Rule 1113r

Paints and Coatings CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) or High-temperature coatings; stone consolidants;

swimming-pool coatings; tub- and tile-refining coatings; and waterproofing membranes

California Air Resources Board (CARB) Suggested Control Measure for Architectural Coatings

SECTION 01 33 29 Page 15

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

Source: ICC IgCC Chapter 8 (Materials) (Interior Applications Only)

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

EMISSIONS

REQUIREMENTS

Floor Covering Materials

For carpet, all locations:

CDPH/EHLB/Standard Method V1.1 ( California Section 01350) or label for Section 9 of CDPH/EHLB/Standard Method V1.1 (Cali fornia Section 01350) none none

Insulation CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) none none

SECTION 01 33 29 Page 16

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

Source: ICC IgCC Chapter 8 (Materials) (Interior Applications Only)

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

EMISSIONS

REQUIREMENTS

Composite Wood, Wood Structural Panel, and Agrifib er Products , no added urea-formaldehyde resins including laminating adhesives for composite wood and agrifiber assemblies -particleboard, medium density fiberboard (MDF), wheatboard, strawboard, panel substrates, door cores

Third-party certification (approved by CARB) of California Air Resource Board's (CARB) regulation , Airborne Toxic Control Measure to Reduce Formaldehyde Emissions from Composite Wood Products or none CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) (except:

Structural panel components such as plywood, particle board, wafer board, and oriented strand board identified as "EXPOSURE 1," "EXTERIOR," or

"HUD-APPROVED"

are considered acceptable for interior use.)

Office Furniture Systems and Seat ing installed prior to occupancy

ANSI/BIFMA X7.1

ANSI/BIFMA X7.1:

(95-percent of installed office furniture system workstations and seating units)

Section 7.6.2 of ANSI/BIFMA e3 (50-percent of office furniture system workstations and seating units) none none

SECTION 01 33 29 Page 17

TABLE 3-1 Volatile Organic Compounds (VOC) (Low Emitting Materials) Requirements

Source: ICC IgCC Chapter 8 (Materials) (Interior Applications Only)

MATERIAL CATEGORY EMISSIONS

REQUIREMENT

MATERIALS WITH

ADDED VOC

REQUIREMENT

EMISSIONS

REQUIREMENTS

Ceiling and Wall assemblies and systems including:

acoustical treatments;

ceiling panels and tiles; tackable wall panels and coverings; wall coverings; wall and ceiling paneling and planking

CDPH/EHLB/Standard method V1.1 (California Section 01350) (Use "office" or "classroom" space limits for all applications) none none

-- End of Section --

SECTION 01 33 29 Page 18

01 33 29 APPENDIX A

SUSTAINABLE DESIGN REQUIREMENTS FOR LEED v4 BD+C

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes general requirements and procedures for compliance with certain prerequisites and credits needed for Project to be “certifiable” under "LEED Version 4 for Building Design and Construction" (LEED v4 BD+C) Certified level equivalent certification based on USGBC's LEED v4

BD+C.

1. Specific requirements for LEED are also included in other Sections.

2. Some LEED prerequisites and credits needed to obtain equivalent LEED certification depend on product selections and may not be specifically identified as LEED requirements. Compliance with requirements needed to obtain LEED prerequisites and credits may be used as one criterion to evaluate substitution requests and comparable product requests.

3. A copy of the LEED Project checklist is attached at the end of this Section for information only.

B. Some LEED prerequisites and credits needed to obtain the indicated LEED equivalent certification depend on Architect's design and other aspects of Project that are not part of the Work of the Contract. Related Sections include the following:

1. Divisions 1 through 32. Sections for LEED requirements specific to the Work of each of those Sections. These requirements may or may not include specific reference to LEED.

2. 01 74 19 Construction Waste Management

3. 01 91 13 General Commissioning Requirements

1.3 DEFINITIONS

A. LEED: USGBC's "LEED Version 4 for Building Design and Construction."

1. Definitions that are a part of "LEED Version 4 for Building Design and Construction" (LEED v4 BD+C) apply to this Section.

B. Bio-based materials. Bio-based products must meet the Sustainable Agriculture Network’s Sustainable Agriculture Standard. Bio-based raw materials must be tested using ASTM Test Method D6866 and be legally harvested, as defined by the exporting and receiving country. Exclude hide products, such as leather and other animal skin material. Products meeting bio-based materials criteria are valued at 100% of their cost for the purposes of credit achievement calculation.

C. Chain-of-Custody Certificates: Certificates signed by manufacturers certifying that wood used to make products was obtained from forests certified by an FSC-accredited certification body to comply with FSC STD- 01-001. Certificates shall include evidence that manufacturer is certified for chain of custody by an FSC-accredited certification body.

D. Composite Wood: A product consisting of wood or plant particles or fibers bonded together by a synthetic resin or binder.

E. Environmental Product Declaration (EPD): A standardized way of communicating the environmental impacts, such as global warming potential and energy resource depletion, of a product or system.

F. Extended producer responsibility: Products purchased from a manufacturer (producer) that participates in an extended producer responsibility program or is directly responsible for extended producer responsibility.

G. Industry-Wide (Generic) declarations: Third-party (Type III) certification, which includes verification. The declaration is generic to a product, such as concrete, not specific to a particular manufacturer or company. For the product to be eligible, the manufacturer must claim representation either directly on the EPD or through the Program Operator for the associated EPD.

H. LEED: Leadership in Energy & Environmental Design.

I. Forestry Stewardship Council (FSC) Sets standards for responsible forestry management.

J. Product Category Rule (PCR): Defines how to standardize this information for a specific product type, such as flooring. The PCR defines scope, system boundary, measurement procedures, impact measures and other technical requirements

K. Product-Specific Declarations: publicly available and critically reviewed (but not necessarily verified) by a third party to ensure that they conform to ISO 14044, which defines how LCAs are critically reviewed

L. Product-specific Type III declarations: Third-party certification that includes verification. Unlike generic EPDs, however, product-specific declarations are specific to a particular manufacturer and do not necessarily reflect the practices of the rest of the industry.

M. Regionally Manufactured Materials: Materials that are manufactured or assembled as a finished product within a 100-mile radius of the Project site. Assembly does not include on-site assembly, erection or installation of finished components.

N. Regionally Extracted, Harvested, or Recovered Materials: Materials that are extracted, harvested, or recovered, as well as manufactured, within a radius of 100 miles from the Site.

1. Extracted materials refer to materials that are removed from the Earth by mining or similar processes.

2. Harvested materials refer to materials that are removed from the Earth through an agricultural process.

3. Recovered materials are recycled or salvaged materials that are reprocessed for use in a subsequent manufacturing process.

O. Recycled Content: The recycled content value of a material assembly shall be determined by weight. The recycled fraction of the assembly is then multiplied by the cost of assembly to determine the recycled content value.

1. "Post-consumer" material is defined as waste material generated by households or by commercial, industrial, and institutional facilities in their role as end users of the product, which can no longer be used for its intended purpose.

2. "Pre-consumer" material is defined as material diverted from the waste stream during the manufacturing process. Excluded is reutilization of materials, such as rework, regrind, or scrap, generated in a process and capable of being reclaimed within the same process that generated it.

P. Salvaged Materials: Construction materials recovered from existing buildings or construction sites and reused in other buildings.

Q. Volatile Organic Compounds (VOCs): Any compound of carbon, excluding carbon monoxide, carbon dioxide, carbonic acid, metallic carbides or carbonates, and ammonium carbonate, which participates in atmospheric photochemical reactions. Compounds that have negligible photochemical reactivity, listed in EPA 40 CFR 51.100(s), are also excluded from this regulatory definition.

1.4 ADMINISTRATIVE REQUIREMENTS

A. Respond to questions and requests from Architect and the Government regarding LEED credits that are the responsibility of the Contractor, that depend on product selection or product qualities, or that depend on Contractor's procedures until the Government has made its determination on the Project's LEED equivalence. Document responses as informational submittals.

B. Submit documentation to the Government and respond to questions and requests from the Government regarding LEED credits that are the responsibility of the Contractor, that depend on product selection or product qualities, or that depend on Contractor's procedures until the Government has made its determination on the Project's LEED equivalence.

1. Document correspondence with Government as informational submittals.

1.5 ACTION SUBMITTALS

A. General: Submit additional sustainable design submittals required by other Specification Sections.

B. Multiple Re-Submittals: The Government’s LEED Administrator will review the first submittal from the contractor and respond with comments and will review one re-submittal for the same item(s) form the contractor and respond with comments.

C. Sustainable design submittals are in addition to other submittals.

1. If submitted item is identical to that submitted to comply with other requirements, include an additional copy with other submittal as a record copy of compliance with indicated LEED requirements instead of separate sustainable design submittal. Mark additional copy "Sustainable design submittal."

D. Project Materials Cost Data: Provide statement indicating total cost for building materials used for Project, as specified in Divisions 3 through 10 and 31, 32.

E. Sustainable Design Documentation Submittals:

1. SSc5– Heat Island Reduction:

1. Non Roof: Product Data for site paving materials indicating solar reflectivity (SR) . Also, provide cut sheets for all pervious paving materials.

2. Roof: Product Data for roofing materials indicating reflectance, emittance, and initial and 3-year aged solar reflectance index (SRI).

2. WEp2– Indoor Water Use Reduction:

1. Provide product documentation as per the labeling and performance requirements stated in the Informational Submittals section within this specification.

3. MRp2: Construction and Demolition Waste Management Planning

1. Documentation complying with Division 1 Section 01 74 19 "Construction Waste Management."

4. MRc2 – Building Product Disclosure and Optimization - Environmental Product Declarations (EPD)

1. Provide product documentation as per the quantity listed and manufacturer diversification criteria stated in Part 2- Products.

2. Complete MR building product disclosure and optimization calculator or equivalent tracking tool.

a. Do not include plumbing, mechanical and electrical components, and specialty items, such as elevators, escalators, process equipment and fire suppression systems, in the calculation.

a) An exception of the following “passive” (meaning not part of the active portions of the system) products may be included in the calculations: piping, pipe insulation, ducts, duct insulation, conduit, plumbing fixtures, showerheads and lamp housings.

Note if they are included in the credit calculations, they must be included consistently across relevant MR credits.

3. EPD and LCA reports or compliant summary documents

a. Product-Specific Declarations

a) Name of declaration holder or producer (typically the manufacturer)

b) Contact information

c) Product type

d) Product name

e) Product description

f) Summary of impact categories measured and overall values

g) Functional unit

h) Standards met

i) Independent review entity’s name and statement

b. Documentation of EPDs

a) Declaration holder (the company, usually the manufacturer, that the EPD is attributed to)

b) EPD program operator (the entity that creates and registers the EPD)

c) LCA verifier (the third-party entity that verifies the life-cycle assessment)

d) PCR reviewer (the third-party entity that has reviewed the product category rules)

5. MRc3 - Building Product Disclosure and Optimization - Sourcing of Raw Materials

1. Raw Material Source and Extraction Reporting. Provide product documentation as per the quantity listed and manufacturer diversification criteria stated in Part 2-Products.

2. MR building product disclosure and optimization calculator or equivalent tracking tool.

a. Do not include plumbing, mechanical and electrical components, and specialty items, such as elevators, escalators, process equipment and fire suppression systems, in the calculation.

a) An exception of the following “passive” (meaning not part of the active portions of the system) products may be included in the calculations: piping, pipe insulation, ducts, duct insulation, conduit, plumbing fixtures, showerheads and lamp housings.

Note if they are included in the credit calculations, they must be included consistently across relevant MR credits.

3. Corporate sustainability reports for 100% of products contributing toward credit.

4. Third-party verified corporate sustainability reports (CSR) including environmental impacts of extraction operations and activities associated with the manufacturer’s product and the product’s supply chain Acceptable CSR frameworks include the following:

a) Global Reporting Initiative (GRI) Sustainability Report

b) Organization for Economic Co-operation and Development (OECD) Guidelines for Multinational Enterprises

c) U.N. Global Compact: Communication of Progress

d) ISO 26000: 2010 Guidance on Social Responsibility

e) USGBC approved program: Other USGBC approved programs meeting the CSR criteria.

5. Leadership Extraction Practices

a. Provide product documentation as per the cost percentage criteria stated in Part 2-Products.

b. MR building product disclosure and optimization calculator or equivalent tracking tool and product data, which includes the following:

a) Extended producer responsibility - Product data and certification letter from product manufacturers, indicating participation in an extended producer responsibility program and statement of costs.

b) Bio-based materials - Product data and certification for bio-based materials, indicating that they comply with the Sustainable Agriculture Standard. Include statement of costs.

c) Wood products - Itemized invoice showing certification by the Forest Stewardship Council or USGBC-approved equivalent.

d) Material reuse - Receipts for salvaged and refurbished materials used for Project, indicating sources and costs.

e) Recycled content - Product data and/or letter from product manufacturers, indicating percentages by weight of post-consumer and pre-consumer recycled content for products having recycled content. Include statement of costs.

f) Documentation for regional materials, indicating location and distance from Project of material manufacturer and point of extraction, harvest, or recovery for each raw material and costs of regional materials.

6. MRc4-Building Product Disclosure and Optimization - Material Ingredients

1. Provide product documentation as per the cost percentage criteria stated in Part 2-Products.

2. MR building product disclosure and optimization calculator or equivalent tracking tool and product data, which includes the following:

a. Documentation of chemical inventory through Health Product Declarations, Cradle to Cradle certification labels, Declare labels, ANSI/BIFMA e3 Furniture Sustainability Standard, Cradle to Cradle Material Health Certificates, manufacturers’ lists of ingredients with GreenScreen assessment reports for confidential ingredients, or USGBC-approved programs (if applicable)

b. Verification of ingredient optimization through Cradle to Cradle certification labels, manufacturers’ lists of ingredients with GreenScreen benchmarks listed for all ingredients, or manufacturers’ declaration (for REACH), or USGBC-approved programs (if applicable)

c. Documentation for products that comply with LEED requirements for product manufacturer supply chain optimization.

d. Do not include plumbing, mechanical and electrical components, and specialty items, such as elevators, escalators, process equipment and fire suppression systems, in the calculation.

a) An exception of the following “passive” (meaning not part of the active portions of the system) products may be included in the calculations: piping, pipe insulation, ducts, duct insulation, conduit, plumbing fixtures, showerheads and lamp housings.

Note if they are included in the credit calculations, they must be included consistently across relevant MR credits.

3. Include documentation for regional materials, indicating location and distance from Project of material manufacturer and point of extraction, harvest, or recovery for each raw material and costs of regional materials.

7. MRc5 Construction and Demolition Waste Management

1. Comply with Division 1 Section 01 74 19 "Construction Waste Management."

8. EQc2 – Low Emitting Materials

1. USGBC Low Emitting Materials Calculator

2. Adhesives and Sealants

a. Product data for adhesives and sealants used inside the weatherproofing system, indicating VOC content and laboratory test reports showing compliance with requirements for low-emitting materials.

3. Paints and Coatings

a. Product data for paints and coatings used inside the weatherproofing system, indicating VOC content and laboratory test…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .