This document contains bidder inquiry responses related to solicitation number W912PM22R0012 for the construction of an Advanced Skills Training Facility Annex and HAZMAT Facilities at Fort Bragg, North Carolina. The Army Corps of Engineers intends to issue the solicitation for a contractor to provide all labor, materials, equipment, and services for construction of approximately 24,500 square feet of administrative offices, classrooms, labs, storage, and support facilities. Additionally, the project includes a 1,200 square foot Hazardous Materials Storage building and site work. Key details include a required construction duration of 548 calendar days, responses to bidder questions dated through August 30th clarifying contract requirements and specifications, and confirmation that amendments would update the solicitation to reflect responses by September 1st.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PN79439.2 SOF Technical Support Training Annex, Fort Bragg, NC
ID Discipline Sheet Detail Spec Bidder Inquiry Date Received Evaluation (Response) Response By Response
Date Requires Amendment
(Y/N)?
9889909 Contracting NA NA 3.8.1 / 00 21 16 3.8.1 states the bond sould be submitted in original form. Please provide the address and specify the recipient for the bond.
8/22/2022 Response to be provided by USACE. USACE TBD TBD
9890470 Program Management
All NA NA The RFP documents including Specifications and Drawings are marked with "CUI" however there are no instructions to the Contractor regarding any required controls. The documents are available for public download on the SAM.GOV website. Are there any restrictions as to the storage or distribution of the RFP documents?
8/23/2022 CPARS evaluations may not be substituted for PPQ(s). If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow‐up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Mr. Robert Law or Mr. John Hill via email at robert.n.law@usace.army.mil or john.t.hill@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
John Hill
(USACE)
8/24/2022 No
9890497 Program Management
All NA 00 21 16 Paragraph 6.2.2 of the Evaluation Criteria for Key Personnel lists the "Licensed Architect/Designer of Record (DOR)." Please clarify that this is a Design‐Bid‐ Build project and no resume for a DOR is required.
8/23/2022 This project is fully designed. The reference to 'Licensed Architect/ Designer of Record (DOR) will be removed via amendment.
John Hill
(USACE)
8/24/2022 YES
(by USACE)
9890555 Program Management
NA NA 00 10 00 The CLIN Schedule in Section 00 21 16 does not match the CLIN Schedule in Section 00 10 00. Please confirm that we are to use the CLIN Schedule in Section 00 10 00
8/23/2022 Note to USACE: CLIN Schedule provided in 00 10 00 is understood by A‐E to be correct. 00 21 16 may need to be revised by USACE.
USACE TBD TBD
9890575 Program Management
NA NA 00 10 00 Section 00 10 00 under Note 1 states that the contract duration is 365 calendar days, however Section 00 21 16 and Standard Form 1442 state the contract duration is 730 calendar days. Please clarify the contract duration. Also, the CLIN Schedule in Section 00 10 00 has a blank next to "Proposed Contract Duration". Can the contractor propose a duration different than the 730 calendar days?
8/23/2022 RESPONSE:
Contract duration shall be 548 calendar days. Sections 00 10 00 and 00 21 16 shall be updated accordingly in forthcoming Amendment.
Blank next to "Proposed Contract Duration" in Section 00 01 00 is intended for the Contractor to acknowledge/confirm their proposed work shall be completed within the stated Duration. This is not for the Contractor to propose a completion beyond the given Duration.
exp Federal 8/29/2022 YES:
00 10 00 (by A‐E)
00 21 16 (by USACE)
9897324 Program Management
A‐103 Sheet Note 2
NA Please confirm that the stationary scissor lift is Contractor Furnished, Contractor Installed.
8/26/2022 RESPONSE:
Concur, scissor lift shall be CFCI.
exp Federal 8/29/2022 NO
9897336 Civil CS501 Detail 7 NA CS501, Detail 7; please confirm there are no roadway barrier wall on this project as shown on the detail 7 of sheet CS501.
8/26/2022 RESPONSE:
Please refer to grid D3/4 on sheet CS101 for the location of the barrier wall.
exp Federal 8/29/2022 NO
9897356 Civil CP501 Option Note
NA CP501, upper left corner note states: "OPTION NOTE: ALL ASPHALT PAVEMENT
SHOWN IS AN OPTION BASE BID WOULD SIMPLY BE AN ADDITIONAL 5.5
INCHES OF AGGREGATE BASE COURSE." Please confirm the total aggregate in the base bid for the POV lot and Access Road will be total 9" (incl. agg. in place of 3" asphalt pavement for light duty) and 13.5" (incl. agg. in place of 5.5" asphalt pavement for heavy duty), respectively?
8/26/2022 RESPONSE:
That note is specific to the access road which would be 13.5” total rock in the base bid. The access road typical section (Detail 1, CP501) refers to the Heavy Duty Pavement detail (3B).
exp Federal 8/29/2022 NO
9897384 Civil GI001 NA NA GI001 ‐ CONSTRUCTION AND DEMOLITION (C&D) WASTE PERMIT: Please confirm the base onsite landfill has reached capacity and the "new phase III" section of the landfill has not open and operating and contractor shall haul construction and demolition waste off the installation to a state certified C&D landfill or sub Title "D" landfill.
8/26/2022 Note to USACE: No information has been provided to the A‐E to indicate the GI001 information is outdated. Recommend response be provided by USACE/Ft Bragg DPW.
USACE TBD TBD
9898637 Sustainability NA NA 01 33 29 Section 01 33 29 Appendix A Sustainability Requirements for Design‐Build, paragraphs 1.2, 1.6, 2.1, 2.2, and LEED NC v4 Checklist Worksheet: The LEED NC v4 Checklist Worksheet indicates that LEED v4.1 credit substitution is recommended on some of the credits. However, the cited paragraphs do not include v4.1 reference or criteria. Confirm substitution of LEED v4.1 credits is allowed.
8/26/2022 RESPONSE:
Comply with LEED v4.0 requirements unless noted in the LEED Checklist.
LEED v4.1 credit substitution is allowed. The project team has been instructed by the Government to follow the LEED v4 rating standards, but the project is not required to submit for LEED certification (i.e. the project is being designed to LEED equivalence only). The substitution of LEED version
4.1 for the listed credits allow the credit to be achieved more easily (and less costly) compared to the version 4 counterpart. Specifications regarding the products, submittals and execution would remain the same. The only difference would be the thresholds calculated at the end of the project. See updated LEED Checklist for additional information in forthcoming Amendment.
exp Federal 8/30/2022 YES 01 33 29 LEED Checklist
(by A‐E)
9898639 Sustainability NA NA 01 33 29 Section 01 33 29 Appendix A Sustainability Requirements for Design‐Build, paragraph 1.5, E.1 SSc5 – Heat Island Reduction and LEED NC v4 Checklist Worksheet: The LEED NC v4 Checklist Worksheet indicates this credit as "No".
The metal roofing specification does not identify a required SRI value for the roofing material. Confirm documentation for this credit is required if the credit is not being considered.
8/26/2022 RESPONSE:
Documentation of SRI value is not required for this credit since the associated LEED credit is not being obtained, nor is it required under spec section 07 61
14.00 20 1.4 Submittals.
exp Federal 8/29/2022 NO
9894641 Sustainability NA NA 01 33 29 Section 01 33 29 Appendix A Sustainability Requirements for Design‐Build, paragraphs 1.5, E.8 – Eqc2 Low Emitting Materials, 2.2, A – Low‐Emitting Materials, and LEED NC v4 Checklist Worksheet: The LEED NC v4 Checklist Worksheet EQc2 indicates only 1 point in the "Probable" column and 2 points in the "Not Probable" column. This in conflict with Section 01 33 29 Sustainability Requirements for Design‐Build, Table 3‐1 Volatile Organic Compounds 9VOC) (Low Emitting Materials) requirements and UFC 1‐200‐02 High Performance and Sustainable Buildings Requirements, which requires compliance with emissions/ VOC requirements for all categories identified by LEED v4, but has slightly different performance requirements for some of the categories. Confirm project is to only attempt compliance in 2 categories for 1 point.
8/26/2022 RESPONSE:
LEED Checklist will be updated to indicate three points are required and to comply with Section 01 33 29. Note, LEED version 4.1 credit substitution is recommended as it provides an easier (and less costly) path towards credit achievement.
Specifications regarding the products, submittals and execution would remain the same with the only difference being the thresholds calculated at the end of the project. Refer to forthcoming Amendment.
exp Federal 8/30/2022 YES 01 33 29 LEED Checklist
(by A‐E)
9898645 Sustainability NA NA 01 33 29 Section 01 33 29 Appendix A Sustainability Requirements for Design‐Build, LEED NC v4 Checklist Worksheet, EQc4 Indoor Air Quality Assessment: The LEED NC v4 Checklist worksheet indicates "Not Probable" for this credit as flush‐out may take 15‐20 days. However, Section 01 33 29 Sustainability Requirements for Design‐Build, paragraph 1.6.10 Indoor Air Quality During Construction indicates that building flush‐out is required per IgCC 1001.3.1.5 (10.3.1.4). Confirm if building flush‐out is required in compliance with the cited standard.
8/26/2022 RESPONSE:
Response: As IgCC is required per Section 01 33 29, either flush out (Option 1) or IAQ testing (Option 2) is required. The LEED Checklist indicates one point shall be achieved. Therefore Option 1 Flush Out is recommended for compliance.
exp Federal 8/30/2022 YES 01 33 29 LEED Checklist
(by A‐E)
9898449 Sustainability NA NA 01 33 29 Section 01 33 29 Appendix A Sustainability Requirements for Design‐Build, paragraph 3.2 Soil Testing, and LEED NC v4 Checklist Worksheet: The LEED NC v4 Checklist Worksheet indicates that SSc2 Site development – Protect and Restore Habitat criteria is not met for the project and is listed in the "No" column. Paragraph 3.2 Soil Testing indicates collection of soil and soil tests requirements for compliance with SSc2. As project will not be pursuing this credit, confirm soil collection and testing are not required.
8/26/2022 RESPONSE:
Paragraph 3.2 Soil Testing shall be deleted from Spec Section 01 33 29 Appendix A Sustainable Design Requirements for LEED v4 BD+C on forthcoming Amendment.
exp Federal 8/30/2022 YES 01 33 29 LEED Checklist
(by A‐E)