TWO PHASE Single Award Task Order Contract (SATOC) for General Construction and/or Design-Build for the United States Army Corps of Engineers (USACE) Wilmington District (SAW) for work to be performed at Military Ocean Terminal Sunny Point (MOTSU) located near Southport NC.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912PM-15-R-0003-0007.pdf | ||
| W912PM-15-R-0003-0006.pdf | ||
| W912PM-15-R-0003-0005.pdf | ||
| 15-R-0003_Amendment_4_Conformed_Copy.pdf | ||
| 15-R-0003_Amendment_4.pdf | ||
| 15-R-003_Amendment0003.pdf | ||
| 15-R-0003_Amendment_2.pdf | ||
| 15-R-0003_Amendment_2_Conformed_Copy.pdf | ||
| 15-R-0003_Amendment_1_Conformed_Copy.pdf | ||
| 15-R-0003_Amendment_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP No. W912PM-15-R-0003
IDIQ / SATERQ
Military Ocean Terminal Sunny Point (MOTSU), Brunswick County, North Carolina
This project was designed by theThis project was designed by the Wilmington District of the U.S. Army Corps of Wilmington District of the U.S. Army Corps of Engineers. The initials or signatures and registration designations of individuals Engineers. The initials or signatures and registration designations of individuals appear on these project documents within the scope of their employment as appear on these project documents within the scope of their employment as required by ER 1110required by ER 1110--11--8152.8152.
Specificationsp
January 2015
IDIQ/SATER W912PM-15-R-0003
MILITARY OCEAN TERMINAL SUNNY POINT (MOTSU)
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
STANDARD FORM 1442
00 10 00 SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
00 21 16 INSTRUCTIONS TO PROPOSERS
00 22 16 SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 72 00 GENERAL CONDITIONS
00 73 00 SUPPLEMENTARY CONDITIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 02 STATEMENT OF WORK/DESCRIPTION/SPECIFICATIONS
01 00 04 DELIVERY ORDER PROCEDURES
01 14 00 WORK RESTRICTIONS - MOTSU
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
TWO PHASE Single Aw ard Task Order Contract (SATOC) for General Construction and/or Design-Build for the United States Army Corps of Engineers (USACE) Wilmington District (SAW) for w ork to be performed at Military Ocean Terminal Sunny Point (MOTSU) located near Southport, NC.
This Acquisition is being offered as a Competitve 8(a) Set-Aside. NAICS: 236220.
This solicitation is a Firm Fixed Price using Tw o-Phase Design-Build Selection Procedures in accordance w ith Federal Acquisition Regulation (FAR) 36.303. The Government w ill use a Best Value Performance Price Trade-Off (PPT) Evaluation Process IAW FAR 15.101-1. The Government w ill evaulate Phase 1 proposals IAW criteria described herein and w ill select up to f ive (5) of the highest rated Offerors to participate in Phase 2. The proposal of the successful Offeror shall be incorporated by reference upon aw ard of the contract.
The total capacity of this contract is $14,900,000.00. Aw arded contract w ill be for a base period of three (3) years w ith tw o (2) one-year option periods.
**Blocks 11 and 12: As specified per Task Order **Block 13B: A Bid Guarantee is not required until Phase 2 of the solicitation.
DANIELLE DINGER 910-251-4700
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
30-Jan-2015
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______ calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Task Order
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________5 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________03 Mar 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
U S ARMY CORPS OF ENGINEERS
WILMINGTON DISTRICT
ATTN: CHARLENNE FIGGINS
69 DARLINGTON AVE
WILMINGTON NC 28403-1343
W912PM
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
04:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
910-251-4454FAX:TEL: 910-251-4473 TEL: FAX:
W912PM-15-R-0003 82
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912PM-15-R-0003
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
BASE YEAR
Three Year Performance Period
(To Be Completed in Phase 2 ONLY)
COEFFICIENT SCHEDULE:
Deisgn-Bid-Build (DBB) __________ Design-Build (DB) ___________
*The Coefficient is to be listed to the hundreds place. Example: A Contractor determines their total mark ups to be 32%. The Coefficient is displayed as 1.32.
ARCHITECTURAL ENGINEER PRICE SCHEDULE (AEPS):
*Rates shall be fully loaded to include all OH, Profit, and Bond.
HOURLY RATES:
Project Manager $__________ Architect $__________ Mechanical Engineer $__________ Electrical Engineer $__________ Structural Engineer $__________ Civil Engineer $__________ Sanitary Engineer $__________ Landscape Architect $__________ Surveyor $__________ 2-man Survey Crew $__________ Environmental Engineer $__________ Industrial Hygienist $__________ Fire Protection Engineer $__________ Geotechnical Engineer $__________ Plumbing Engineer $__________ Power Engineer (High Voltage) $__________ Estimator $__________ HVAC Controls Engineer $__________ Scheduler $__________ Security Engineer $__________ Security Specialist $__________ Safety Engineer $__________ Certified LEED Professional $__________ Interior Designer $__________ Systems Furniture Designer $__________
PRICE PER EACH:
Reproduction Copies: 22x34 $__________ Reproduction Copies: 8.5x11 $__________ Reproduction Copies Color: 8.5x11 $__________ Reproduction Copies: 11x17 $__________ Reproduction Copies Color: 11x17 $__________
CD-ROM (Material Only) $__________
Note: These rates will only be used if a modification to the design is required that is outside the Division 1 deliverables. Design fees in the task orders will be compensated through the Design- Build coefficient and fees will not be negotiated separately.
FIELD OFFICE STAFFING PRICE SCHEDULE (FOSPS):
*Rates shall be fully loaded to include all OH, Profit, and bond.
HOURLY RATES:
Superintendent $__________ Quality Control $__________ Project Manager $__________ Safety $__________ Office Assististant $__________ Laborer $__________
Note: These rates will only be used if a staff is required for a field office per task order or agreed upon by the Contracting Officer. All other field office overhead requirements, unless excluded by this contract, are to be applied within the Design- Bid- Build coefficients and Design-Bid coefficients, the fees will not be negotiated separately.
FOB: Destination
NET AMT
OPTION OPTION YEAR 1
One Year Performance Period
(To Be Completed in Phase 2 ONLY)
COEFFICIENT SCHEDULE:
Deisgn-Bid-Build (DBB) __________ Design-Build (DB) ___________
*The Coefficient is to be listed to the hundreds place. Example: A Contractor determines their total mark ups to be 32%. The Coefficient is displayed as 1.32.
ARCHITECTURAL ENGINEER PRICE SCHEDULE (AEPS):
*Rates shall be fully loaded to include all OH, Profit, and Bond.
HOURLY RATES:
Project Manager $__________ Architect $__________ Mechanical Engineer $__________ Electrical Engineer $__________ Structural Engineer $__________ Civil Engineer $__________ Sanitary Engineer $__________ Landscape Architect $__________ Surveyor $__________ 2-man Survey Crew $__________ Environmental Engineer $__________ Industrial Hygienist $__________ Fire Protection Engineer $__________ Geotechnical Engineer $__________ Plumbing Engineer $__________ Power Engineer (High Voltage) $__________ Estimator $__________ HVAC Controls Engineer $__________ Scheduler $__________ Security Engineer $__________ Security Specialist $__________ Safety Engineer $__________ Certified LEED Professional $__________ Interior Designer $__________ Systems Furniture Designer $__________
PRICE PER EACH:
Reproduction Copies: 22x34 $__________ Reproduction Copies: 8.5x11 $__________ Reproduction Copies Color: 8.5x11 $__________ is outside the Division 1 deliverables. Design fees in the task orders will be compensated through the Design- Build coefficient and fees will not be negotiated separately.
FIELD OFFICE STAFFING PRICE SCHEDULE (FOSPS):
*Rates shall be fully loaded to include all OH, Profit, and bond.
HOURLY RATES:
Superintendent $__________ Quality Control $__________ Project Manager $__________ Safety $__________ Office Assististant $__________ Laborer $__________
Note: These rates will only be used if a staff is required for a field office per task order or agreed upon by the Contracting Officer. All other field office overhead requirements, unless excluded by this contract, are to be applied within the Design-
OPTION OPTION YEAR 2
One Year Performance Period
(To Be Completed in Phase 2 ONLY)
COEFFICIENT SCHEDULE:
Deisgn-Bid-Build (DBB) __________ Design-Build (DB) ___________
*The Coefficient is to be listed to the hundreds place. Example: A Contractor determines their total mark ups to be 32%. The Coefficient is displayed as 1.32.
ARCHITECTURAL ENGINEER PRICE SCHEDULE (AEPS):
*Rates shall be fully loaded to include all OH, Profit, and Bond.
HOURLY RATES:
Project Manager $__________ Architect $__________ Mechanical Engineer $__________ Electrical Engineer $__________ Structural Engineer $__________ Civil Engineer $__________ Sanitary Engineer $__________ Landscape Architect $__________ Surveyor $__________ 2-man Survey Crew $__________ Environmental Engineer $__________ Industrial Hygienist $__________ Fire Protection Engineer $__________ Geotechnical Engineer $__________ Plumbing Engineer $__________ Power Engineer (High Voltage) $__________ Estimator $__________ HVAC Controls Engineer $__________ Scheduler $__________ Security Engineer $__________ Security Specialist $__________ Safety Engineer $__________ Certified LEED Professional $__________ Interior Designer $__________ Systems Furniture Designer $__________
PRICE PER EACH:
Reproduction Copies: 22x34 $__________ Reproduction Copies: 8.5x11 $__________ Reproduction Copies Color: 8.5x11 $__________ is outside the Division 1 deliverables. Design fees in the task orders will be compensated through the Design- Build coefficient and fees will not be negotiated separately.
FIELD OFFICE STAFFING PRICE SCHEDULE (FOSPS):
*Rates shall be fully loaded to include all OH, Profit, and bond.
HOURLY RATES:
Superintendent $__________ Quality Control $__________ Project Manager $__________ Safety $__________ Office Assististant $__________ Laborer $__________
Note: These rates will only be used if a staff is required for a field office per task order or agreed upon by the Contracting Officer. All other field office overhead requirements, unless excluded by this contract, are to be applied within the Design-
CLAUSES INCORPORATED BY FULL TEXT
52.214-4006 Solicitation/Technical Inquiries via ProjNet (Local Instruction CECT-SAW October 2012)
1. Solicitation/Technical Inquiries.
a. Inquiries are to be submitted via Bidder Inquiry at the ProjNet website at https://www.projnet.org <https://www.projnet.org> .
b. If you have technical problems accessing the Bidder Inquiry via the ProjNet website, contact the ProjNet Help Desk at 1-800-428-4357 (HELP). This number is for technical issues accessing the website ONLY.
2. Read this paragraph in conjunction with contract provision FAR 52.214-6, “Explanation to Prospective Bidders”.
3. Any prospective bidder/offeror desiring an explanation or interpretation of the solicitation, drawings specifications, etc., must request it in writing via Bidder Inquiry in ProjNet within no less than ten (10) calendar days prior to the date of bid opening or receipt of proposals. The Government reserves the right to decline addressing questions received less than ten
(10) calendar days prior to receipt of bid opening or receipt of proposals.
4. No Inquiries will be accepted by the Bidder Inquiry system within ten (10) calendar days prior to the date of bid opening. However, you may still access the Bidder Inquiry system to view answers/replies to previous inquiries until the bid opening.
5.ProjNet - Bidder Inquiry module.
a. To submit and review bid inquiry items, bidders/offerors will need to be a current registered user or self-register into system. To access Bidder Inquiry, go to the ProjNet web page at http://www.projnet.org <http://www.projnet.org> and click the “Quick Add” link. Once at the Quick Add screen, select agency USACE, enter Bidder Inquiry Key for this solicitation listed below, and bidder’s/offeror’s e-mail address, then click login. If this is bidder’s/offeror’s first time logging in they will be taken to the Bidder Inquiry Create Account screen to self-register. Fill in all required information and click create user. Verify that information on next screen is correct and click continue. Please remember your Secret Question Answer and email address used for future access to this website.
b. From this page you may view all bidder/offeror inquiries under Reports or post a new inquiry under Submit.
c. Bidders/Offerors will receive an acknowledgement of their question via email, followed by another email notification that an answer to their question has been posted after it has been reviewed by our technical team and responded to by a Contracting Officer. It is the responsibility of the Bidder/Offeror to check their junk email and email delivery options to ensure delivery of these acknowledgement emails.
d. Bidders/Offerors are responsible for checking bid inquiry items.
e. Bidders/Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. The name of the submitter or firm is not published for the public on the report of all Bidder Inquiries. Bidders/ Offerors are on notice of, and assumed to be aware of, all inquiries, responses, and information posted in the Bidder Inquiry System up to the date of bid submission, whether the inquiry was generated by the Bidder themselves or another potential Bidder/ Offeror. Bidders are responsible for incorporating all such information into their bid, or for requesting further clarification."
6. Solicitation Information: IFB/RFP No: W912PM-15-R-0003
Bidder Inquiry Key: SFRM8G-ZDZ58D
(end)
52.215-4005 COEFFICIENTS
The “Coefficient” is a numerical percentage factor that represents contractor indirect costs and profits not included in the unit prices (NOTE: the coefficients include PERFORMANCE AND PAYMENT BONDING TO cover the MAXIMUM CONTRACT AMOUNT for any given year). The coefficients proposed and accepted are incorporated in the Indefinite Delivery Indefinite Quantity Contract award. Unit costs are multiplied by the coefficient to determine the cost of each individual task order or modification thereto.
Reference: Delivery order procedures, Section 01 00 04, 2.4.2, for further coefficient explanation.
(End of Clause)
52.232-4001 COST LIMITATION – JUNE 1999
The contract award for design and construction shall not exceed $ *** for this project. Offerors are under no obligation to approach this amount.
*** The Construction Cost Limitation (CCL) will be determined on a Task Order by Task Order basis.
52.236-4011 Disclosure of Magnitude of Construction (FAR 36.204 and DFARS 236.204)
The total capacity of this contract is $14,900,000.00.
*The estimated price range of each project will be determined on each task order solicitation.
Section 00 21 16 - Instructions to Proposers
INSTRUCTIONS TO PROPOSERS
SECTION V
SECTION 00 21 16
INSTRUCTIONS TO PROPOSERS
GENERAL INSTRUCTIONS & PROPOSAL FORMAT
1. OVERVIEW
1.1. This Request for Proposal (RFP) solicits for a Single Award Task Order Contract (SATOC) under which task orders for Design/Build, General Construction, and/or Renovation Type Projects are expected to be issued with work at MOTSU located near Sunny Point, NC. This RFP is a 100% 8(a) set-aside. Task Orders issued under any resultant contract(s) will be Firm-Fixed Price and may be either of a Construction or Design/Build nature. A project requiring use of civil funds is not authorized under this contract.
1.2. The purpose of the Source Selection plan is to establish a uniform evaluation procedure for the technical evaluation of proposals by the Source Selection Evaluation Board (SSEB) and the development of the Best Value Decision by the Source Selection Authority (SSA) using the Trade- Off Process (See Federal Acquisition Regulation 15.101-1). In as much as the proposal shall describe the capability of the Offeror to perform any resulting contract, and task orders issued there under, the proposal should be specific and complete in every detail as well as be prepared simply and economically, providing a straightforward and concise description of capabilities to satisfactorily perform the contract and task orders issued thereafter.
1.3. For the purposes of this solicitation, the Government will utilize the Two (2) Phase Design Build Process. This will result in one award based on Best Value to the Government, price and other factors considered. The contract is for three years with two option years. The total estimated value for the contract will not exceed $14,900,000.00. Projects will vary in size, but will not exceed $1,000,000.00.
1.4. In Phase 1 of the 2 phase design-build selection procedure, interested Offerors will submit specified performance capability proposals for review and consideration by the Government. The Government will evaluate these performance capability proposals in accordance with the criteria described herein.
1.5. The Government will evaluate the performance capability proposals in accordance with the criteria described herein and will select up to five (5) of the highest rated Offerors to participate in Phase 2.
1.6. In Phase 2 of this process, the Government will evaluate both technical capability and price proposals.
1.7. Only those Offerors who receive a written notification from the Wilmington District Contracting Officer that their firm has been selected to participate in Phase 2 of this solicitation will be invited to submit a Phase 2 proposal. The Government intends to announce the names of Offerors selected for Phase 2 in the FEDBIZOPS website. An Offeror that does not want this information released must provide a written notification and explanation of its objections to release of the information.
Those Offerors selected for Phase 2 will be provided the technical requirements package for a Seed
Task Order that may be representative of the type work and task orders anticipated to be issued under any resultant contract(s).
2. GENERAL INSTRUCTIONS
2.1. Firms formally organized as design-build entities, design firms and construction contractors that have associated specifically for performance of this contract, consortia of firms, or any other interested parties may submit proposals. A design firm or construction contractor may offer more than one proposal by entering into more than one association. Associations may be joint ventures or include key team subcontractors. Any legally organized Offeror may submit a proposal. All executed teaming arrangements shall be submitted under Phase 1, Volume 1, Tab D.
2.2. Contractor Team Arrangements. Contractor Team Arrangements are considered an arrangement in which (1) two or more companies form a partnership or joint venture to act as a potential prime contractor; or (2) a potential prime contractor agrees with one or more other companies to have them act as its subcontractors under a specified Government contract or acquisition program. In accordance with FAR Subpart 9.6, the Government will recognize the integrity and validity of contractor team arrangements; provided, the arrangements are identified and company relationships are fully disclosed in the offer. The Offeror shall identify the major or critical aspects of the requirement to be performed by those identified in the Contractor Team Arrangement. The submission must contain a narrative that clearly explains the relevance to a particular factor of information concerning a company that is part of a Contractor Team Arrangement. The Government will consider the adequacy of this explanation in deciding the relevance of the information to this procurement. Any narrative provided should be incorporated into the Offeror’s proposal at Phase 1, Volume 1, Tab D.
2.3. Notwithstanding the specific requirements of any other area of the RFP, information submitted about any company other than the Offeror, whether a predecessor company, affiliated company, subsidiary (including wholly owned subsidiaries), or subcontractors that will perform major or critical aspects of this requirement, or other associated business, WILL NOT be evaluated for any factor unless the proposal contains a detailed narrative explaining why this submitted information is relevant to this acquisition. The Government will consider the adequacy of this explanation in deciding the relevance and weight, if any, of the information to this procurement. Where information about a subcontractor is properly submitted and given significant weight during the evaluation, the failure of the Offeror to actually perform with that subcontractor may be grounds for termination for default. Any narrative provided should be incorporated into the Offeror’s proposal at Phase 1, Volume 1, Tab D.
2.4. Offerors shall submit their proposal to the address shown in Block 7 of Standard Form 1442.
2.5. Proposals are due no later than the time and date specified in Block 13 of Standard Form 1442.
3. GENERAL PROPOSAL FORMAT
3.1. Title Page. Include the title of the solicitation, solicitation number, Offeror name, and date of the submittal.
3.2. Table of Contents. Each volume of the proposal shall contain a detailed table of contents. If more than one binder is used, the complete table of contents shall be included in each. Any materials submitted but not required by this solicitation (such as company brochures) shall be relegated to appendices.
3.3. Printed Matter Submissions. Written material shall be on 8 ½ x 11 inch paper printed in no less than a 10 pitch or 10 font. Page limitations, where specified in the RFP, shall be considered a maximum. Pages in excess of any specified limitation may not be evaluated. A single 8 ½ x 11 inch sheet with written material on one side only shall constitute one page. However, if both sides of the sheet bear written material then this single sheet shall be counted as two pages.
3.4. Binders. Proposals shall be submitted in tabbed, three ring binders.
3.5. Number of Copies. Offerors shall submit an original and one (1) copy of Volume I and an original and five (5) hard copies of Volume II, for both phases.
3.6. Electronic Submission. In addition to the hard copies required in paragraph 3.5, all Offerors shall submit their Phase 1 & Phase 2 proposal(s) on a CD-ROM. Offerors SHALL submit an electronic version (PDF Format) of the original Volume I and Volume II, for both phases. Offerors SHALL submit only two files in PDF format (i.e. Volume I and Volume II), for each phase. These two files should be named in a specific format: Solicitation Number, Offerors Company and the volume (i.e.
W912HN-13-R-0004_COMPANY_VolumeI.pdf). Given the limited time and resources of the evaluation board, failure to provide proposal in the correct format may hinder the board's ability to evaluate the Offeror's proposal and may result in the Offeror’s proposal being determined ineligible for award.
4. EXCEPTIONS. Exceptions to the contractual terms and conditions of the solicitation (e.g., standard company terms and conditions) may result in a determination to reject a proposal.
5. RESTRICTIONS. Failure to submit all the data in the format indicated in this section may be cause for determining a proposal incomplete and, therefore, not considered for evaluation, and for subsequent award.
6. PHASE 1 – PROPOSAL TABBING REQUIREMENTS. Phase 1 proposals shall be organized and tabbed as follows:
VOLUME I
TAB A – Standard Form 1442, completed and signed by authorized individual(s) of the Offeror.
Offers submitted in the name of a Joint Venture must be signed in accordance with the terms and conditions specified in the joint venture agreement as evidenced in the proposal.
TAB B – Section 00600 – Representations and Certifications.
TAB C – Proposal Data Sheet – See Attachment 1 provided at the end of this section. Offerors should ensure telephone number, fax number, e-mail address and DUNS number are all included. The DUNS number provided will be used to access Contractor Performance Assessment Reporting System (CPARS) data. If a separate DUNS has been created for a joint venture (J-V) it must be submitted. A DUNS number shall also be provided for each company identified in any other proposed association of firms or Contractor Team Arrangement. The Offeror should also submit their Tax ID number on the proposal data sheet.
TAB D – Teaming Agreements and Narratives, if applicable. See paragraph 2.2 and 2.3.
TAB E –Financial Information & Bonding Capability (e.g. past three years financial statements, annual reports, Dun & Bradstreet Ratings and/or number, etc.) Provide a list of all current contracts held, total dollar value, award date, anticipated completion, performance and payment bond amount.
The Offeror is not required to submit a bid bond but is required to submit a letter, stamped with an official seal and notarized, from the contractor’s surety validating the Offeror’s single and aggregate bonding capability and a power of attorney if applicable. Submit originals; photocopied or scanned copies are not acceptable. Contractors MUST have a minimum bonding capability of $1,000,000.00 single and $14.9M aggregate.
VOLUME II
TAB D –Teaming Agreement (Duplicate of Volume I)
TAB F– SUB-FACTOR 1 Past Performance
TAB G – SUB-FACTOR 2 Design Experience
7. PHASE 2 – PROPOSAL TABBING REQUIREMENTS. Phase 2 proposals shall be organized and tabbed as follows:
VOLUME I
TAB A – Standard Form 1442, completed and signed by authorized individual(s) of the Offeror.
Offers submitted in the name of a Joint Venture must be signed in accordance with the terms and conditions specified in the joint venture.
TAB B – Proposal Pricing Schedule, Section 00 10 00— Schedule A, Bid Schedule & Schedule B, Seed Task Order Pricing.
TAB C – Bid Bond – The Offeror is required to submit a bid bond. Submit originals; photocopied or scanned copies are not acceptable. FAR clause 52.228-1, “Bid Guarantee” will be included in the contract. At the discretion of the Contracting Officer, a Bid Bond will be required for each task order.
VOLUME II
TAB D – Technical Approach
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management JUL 2013 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-20 Requirements for Certified Cost or Pricing Data or
Information Other Than Certified Cost or Pricing Data
OCT 2010
52.215-22 Limitations on Pass-Through Charges--Identification of Subcontract Effort
OCT 2009
52.232-13 Notice Of Progress Payments APR 1984 52.232-14 Notice Of Availability Of Progress Payments Exclusively For
Small Business Concerns
APR 1984
252.203-7005 Representation Relating to Compensation of Former DoD Officials
NOV 2011
252.236-7006 Cost Limitation JAN 1997 252.236-7008 Contract Prices-Bidding Schedules DEC 1991
52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2004)
(a) Definitions. As used in this provision--
“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.
“In writing or written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
“Proposal modification” is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
“Time”, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror.
Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show--
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, or revision, of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications, or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and--
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall--
(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed--in whole or in part--for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of--or in connection with-- the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award. (1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government's interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government's best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
(End of provision)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
20.7% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Brunswick and New Hanover County, North Carolina.
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT-- CONSTRUCTION MATERIALS UNDER
TRADE AGREEMENTS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American -- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability.