AM 0007_Complete File_W912PL20R0001.pdf

PDF 5 MB Posted

Attached to
Brownfield Border Patrol Station Federal contract opportunity
Solicitation number
W912PL20R0001
Issued by
Department of the Army Corps of Engineers Engineering District Los Angeles

About this file

This federal solicitation seeks proposals for the construction of the Brownfield Border Patrol Station project. The project includes construction of a 53,500 square foot border patrol station capable of supporting 400 agents with a 130-person detention area and sally port, as well as ancillary support facilities. The cost range for the project is $25 to $100 million. The NAICS code is 236220 and the small business size standard is $39.5 million. The performance period is 720 calendar days. Proposals are due on or about October 23, 2019. Award will be made using lowest-price technically acceptable criteria. The solicitation is full and open to all firms. Joint ventures must submit partnership agreements and mentor-protege agreements must be SBA approved. The Army Corps of Engineers is the issuing agency.

View the file

Other files for this federal contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

BROWN FIELD BORDER PATROL STATION, DULZURA, SAN DIEGO COUNTY, CALIFORNIA

Please see Attached Extended page for all of the changes made by way of this amendment.

Be advised the proposal due date has not changed.

U.S. Army Corps of Engineers Los Angeles District 915 Wilshire Boulevard, Suite 930 Los Angeles, California 90017-3401 Attn:Contracting Division CESPL-CT-W

W912PL-20-R-0001

1 269

01/07/2020

11/04/2019

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

Customs and Border Protection (CBP) W912PL-20-R-0001 Brown Field Border Patrol Station, Dulzura, California

SF30-2

Amendment 007

Continuation from Block 14, SF-30 Amendment 07 of Solicitation

Amendment issued to add / revise the following of above-referenced solicitation:

1) Replace entire section or section page with included section or section page:

00 00 03 AM007 Project Table of Contents 01 20 00 AM007 Price and Payment Procedures 01 91 00 AM007 Total Building Commissioning

2) Replace drawings or sheets with included drawings or sheets:

None

All other items remain unchanged.

Brown Field Border Patrol Station W912PL-20-R-0001 Dulzura, San Diego County, CA

Section 00 00 03 Page 1 of 6 Bold Italic denotes amendment Amendment 007

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 00 00 COVER

00 00 01 SF1442 AMEND 003

00 00 03 TABLE OF CONTENTS AMEND 007

00 01 05 CERTIFICATION PAGE

00 10 00 CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE AMEND 004

00 21 00 INSTRUCTIONS AMEND 002

00 21 00 INSTRUCTIONS (PAGE 8 OF 16) AMEND 001

00 21 16 INSTRUCTIONS TO PROPOSERS

00 21 16 INSTRUCTIONS TO PROPOSERS (PAGE 1 OF 23) AMEND 004

00 22 10 INSTRUCTIONS – SOURCE SELECTION PROCEDURES AMEND 005

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 70 00 CONDITIONS OF THE CONTRACT AMEND 002

00 73 00 SUPPLEMENTARY CONDITIONS

00 73 00 SUPPLEMENTARY CONDITIONS (PAGE 2 OF 22) AMEND 002

00 73 46 DAVIS BACON WAGE DECISION AMEND 006

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 20 00 PRICE AND PAYMENT PROCEDURES AMEND 007

01 30 00 ADMINISTRATIVE REQUIREMENTS AMEND 002

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS AMEND 002

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL

01 58 00 PROJECT IDENTIFICATION AMEND 002

01 62 35 RECYCLED / RECOVERED MATERIALS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS AMEND 002

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 36.00 24 WARRANTY OF CONSTRUCTION

01 78 39.00 24 AS-BUILT DRAWINGS

01 83 00.07 40 RELIABILITY CENTERED ACCEPTANCE FOR FACILITY SHELLS

01 91 00.15 TOTAL BUILDING COMMISSIONING AMEND 007

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION

Section 00 00 03 Page 2 of 6

DIVISION 03 - CONCRETE

03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 30 00.00 10 CAST-IN-PLACE CONCRETE

03 35 00.00 10 CONCRETE FINISHING

03 39 00.00 10 CONCRETE CURING

03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE

CONSTRUCTION

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 05 23.13 10 ULTRASONIC INSPECTION OF WELDMENTS

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID POLYMER (SOLID SURFACING) FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 13 53 ELASTOMERIC SHEET WATERPROOFING

07 21 16 MINERAL FIBER BLANKET INSULATION

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 19 AIR BARRIER SYSTEM FOR METAL BUILDINGS

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 SPRAY FOAM AIR BARRIERS

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 22 20 FIBERGLASS REINFORCED PLASTIC (FRP) DOORS AND FRAMES

08 31 00 ACCESS DOORS AND PANELS

08 33 13 COILING COUNTER DOORS

08 33 23 OVERHEAD COILING DOORS AMEND 002

08 34 02 BULLET-RESISTANT COMPONENTS

08 34 59 VAULT DOORS AND DAY GATES

08 34 63 DETENTION HOLLOW METAL FRAMES, DOORS, AND DOOR FRAMES

Section 00 00 03 Page 3 of 6

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 56 63 DETENTION AND SECURITY WINDOWS

08 62 00 TUBULAR DAYLIGHTING DEVICE

08 71 00 DOOR HARDWARE

08 71 63 DETENTION HARDWARE

08 81 00 GLAZING

08 88 53 DETENTION AND SECURITY GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 24 23 CEMENT STUCCO

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 62 38 STATIC-CONTROL FLOORING

09 65 00 RESILIENT FLOORING

09 65 66 RESILIENT ATHLETIC FLOORING

09 67 26 QUARTZ FLOORING

09 68 00 CARPETING

09 69 19 STRINGERLESS ACCESS FLOORING

09 84 20 ACOUSTICAL PANELS

09 90 00 PAINTS AND COATINGS

09 97 13.16 INTERIOR COATING OF WELDED STEEL WATER TANKS

09 97 13.17 THREE COAT EPOXY INTERIOR COATING OF WELDED STEEL

PETROLEUM FUEL TANKS

09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES

DIVISION 10 - SPECIALTIES

10 11 00 VISUAL DISPLAY UNITS

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 14 53 ONSITE TRAFFIC SIGNAGE

10 21 13 TOILET COMPARTMENTS AM006

10 22 13 WIRE MESH PARTITIONS

10 22 39 FOLDING PANEL PARTITIONS

10 26 00 WALL AND DOOR PROTECTION

10 26 41 BULLET RESISTANT PANELS

10 28 13 TOILET ACCESSORIES

10 35 00 FLAGPOLES

10 44 16 FIRE EXTINGUISHERS

10 51 13 METAL LOCKERS AM006

10 56 13 SHELVING (CFCI)

10 70 00 EXTERIOR SUN CONTROL DEVICES

DIVISION 11 - EQUIPMENT

11 08 26 COMMISSIONING OF VEHICLE WASHING EQUIPMENT

11 11 00 VEHICLE SERVICE EQUIPMENT (CFCI)

11 11 26 VEHICLE WASHING EQUIPMENT

11 31 13 ELECTRIC KITCHEN EQUIPMENT (CFCI)

11 66 13 EXERCISE EQUIPMENT (CFCI)

11 66 23.53 COMBAT RING PANELS

11 98 19 DETENTION PADDING

Section 00 00 03 Page 4 of 6

DIVISION 12 - FURNISHINGS

12 24 13 ROLLER WINDOW SHADES

12 36 00 COUNTERTOPS

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

12 50 00.13 10 FURNITURE AND FURNITURE INSTALLATION (GFGI)

12 59 00 SYSTEMS FURNITURE (GFGI)

DIVISION 13 - SPECIAL CONSTRUCTION

13 04 80 CANOPY

13 19 13 KENNEL ENCLOSURES AND GATES

13 19 31 VERTICAL LIFT KENNEL DOORS

13 34 19 METAL BUILDING SYSTEMS

13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION AM006

21 13 17.00 10 DRY PIPE SPRINKLER SYSTEM, FIRE PROTECTION AM006

21 30 00 FIRE PUMPS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL

22 07 19.00 40 PLUMBING PIPING INSULATION

22 15 14.00 40 GENERAL SERVICE COMPRESSED-AIR SYSTEMS, LOW PRESSURE

22 31 00 WATER SOFTENERS, CATION-EXCHANGE (SODIUM CYCLE)

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 COMMON PIPING FOR HVAC

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 11 25 FACILITY GAS PIPING

23 21 23 HYDRONIC PUMPS

23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS

23 35 00.00 10 OVERHEAD VEHICLE TAILPIPE EXHAUST REMOVAL SYSTEM(S)

23 52 00 HEATING BOILERS AM004

23 54 16.00 10 HEATING SYSTEM; GAS-FIRED HEATERS

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS

23 73 13.00 40 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS

23 76 00.00 20 EVAPORATIVE COOLING SYSTEM

DIVISION 26 - ELECTRICAL

Section 00 00 03 Page 5 of 6

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL

26 05 19.10 10 INSULATED WIRE AND CABLE

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES

26 08 00 APPARATUS INSPECTION AND TESTING

26 09 23.00 40 LIGHTING CONTROL DEVICES

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 23 00.00 40 SWITCHBOARDS AND SWITCHGEAR

26 24 13 SWITCHBOARDS

26 24 16.00 40 PANELBOARDS

26 28 00.00 10 SWITCHBOARDS AND PANELBOARDS

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 32 15.00 10 DIESEL-GENERATOR SET STATIONARY 100-2500 KW, WITH

AUXILIARIES

26 32 33.00 10 UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM ABOVE 15 KVA

CAPACITY

26 33 53.00 20 UNINTERRUPTIBLE POWER SUPPLY (UPS)

26 41 00 LIGHTNING PROTECTION SYSTEM

26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)

26 42 15.00 10 CATHODIC PROTECTION SYSTEM (STEEL WATER TANKS)

26 51 00 INTERIOR LIGHTING

26 52 00.00 40 EMERGENCY LIGHTING

26 53 00.00 40 EXIT SIGNS

26 54 21.00 10 HELIPAD LIGHTING AND VISUAL NAVIGATION AIDS

26 55 53.00 40 SECURITY LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING

27 21 00.00 20 INTERCOMMUNICATION SYSTEM

27 21 10.00 40 FIBER OPTIC DATA TRANSMISSION SYSTEM

27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 05 26.00 40 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

28 08 10 ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING

28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)

28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 05 19 GEOTEXTILE

31 11 00 CLEARING AND GRUBBING

31 23 00.00 20 EXCAVATION AND FILL

31 37 00 RIPRAP, BOULDERS, AND BEDDING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS

32 11 23 AGGREGATE BASE COURSES

Section 00 00 03 Page 6 of 6

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND FACILITIES

SITE

32 15 00 AGGREGATE SURFACING

32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS

32 17 23 PAVEMENT MARKINGS

32 31 13 CHAIN LINK FENCES AND GATES

32 31 13.10 CHAIN LINK VERTICAL PIVOT GATES

32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES

DIVISION 33 - UTILITIES

33 08 55 COMMISSIONING OF FUEL FACILITY SYSTEMS

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 11 13 POTABLE WATER SUPPLY WELLS

33 16 15 WATER STORAGE STEEL TANKS

33 30 00 SANITARY SEWERAGE

33 32 13.13 PACKAGED SEWAGE LIFT STATIONS, WET WELL TYPE

33 34 00 FORCE MAINS AND INVERTED SIPHONS; SEWER

33 40 00 STORM DRAINAGE UTILITIES

33 52 10 SERVICE PIPING, FUEL SYSTEMS

33 52 90.00 20 WELDING FOR POL SERVICE PIPING

33 56 10 FACTORY-FABRICATED FUEL STORAGE TANKS

33 58 00 LEAK DETECTION FOR FUELING SYSTEMS

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 83 19 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE

EQUIPMENT

43 21 20 POTABLE WATER TREATMENT EQUIPMENT

-- End of Project Table of Contents --

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/11

PART 1 GENERAL

1.1 ENTIRE CONTRACT

1.1.1 BID ITEMS

Payment items for the work of this contract for which contract payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a bid item shall be included in the listed bid item most closely associated with the work involved. The payment made for each item listed shall constitute full compensation for furnishing all technical knowledge, engineering, calculations, plant, labor, materials, equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided. Unless specifically identified the payment for each of the bid items shall be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction.

Unless specifically identified by a separate payment description in a bid item the following shall apply.

For the entire contract including all bid items (base and awarded options) the following shall be provided from the contractor including but not limited to: the items and features described in these solicitation documents for the subject work in the awarded bid item; meeting interim construction schedule; meeting approved construction schedule that includes awarded option bid items; phasing of construction for the entire contract including awarded option bid items; submittal review times for construction and fixtures and equipment for proper scheduling; submittals and schedule inclusion of long lead procurement items; schedule with permit processing time for the Contractor, the Government and the permitting agency;

submittal and schedule inclusion for Contractor development of and processing durations of Right of Entry for Construction Permits, Caltrans Access Permits, Caltrans Encroachment Permit ( see https://dot.ca.gov/obtain-permits ), potable water well permit (from State), water treatment permit and septic system permit (from County) for the project site; preparation of and submittal approval for the manufacturer information, catalog cuts, shop drawings and product data of intended construction, materials, fixtures and equipment as required in construction specifications to clearly indicate construction work; with exception to equipment brand Syntech Fuelmaster, Syntec FM Live ( Fueling System for Border Patrol Vehicles ), all other materials, fixtures and equipment identified by a brand name shall be considered as "brand name or equal" and the material, fixture or equipment that the Contractor decides upon must meet the salient features and intent of the design and the intent of the function as the brand name item; not starting construction of subject bid item and or its features until all materials, submittals, and equipment are on hand; provide all demolition, materials, equipment, construction, and labor to complete the bid item per plans and specifications; provision of contractor management during the entire contract consisting of but not limited to Site Safety and Health Officer

Brown Field Border Patrol Station Dulzura, California W912PL-20-R-0001

Bold Italic denotes amendment 01 20 00 Amendment 07

(SSHO), Contractor Quality Control (CQC) System Manager, Construction Superintendent and Project Manager; provision of competent individuals for the tasks assigned by the contractor to that individual; contractor construction personnel access requirements that include but are not limited to e-verify; preparing a site specific Safety Plan to be approved by Corps of Engineers prior to start of the entire contract; meeting all safety requirements for the entire contract – all contract personnel are required to have participated in an OSHA-approved 10-hour safety course prior to working on site, additionally the on-site supervisor is required to have participated in an OSHA-approved 30-hour safety course; obtaining all hot work permits for all welding and or cutting and or soldering and or brazing that are to be obtained from the USACE COR; provide full demolition and site preparation for the subject bid item construction based on plans and specifications; provide for and maintain all necessary protection of building systems and services during subject bid item construction; provide protection and or cover to any new fixture and or equipment in subject base bid item construction areas to protect from dust buildup and or exposure to construction and or environment elements while performing work; perform touch-up finishing work including gypsum wall board re-work,painting and flooring refinish as necessary before final turnover; periodic thorough cleaning of affected and effected subject bid item areas of all construction debris and trash; for the entire contract the following item is required - meeting with, planning with, scheduling for and cooperating with the Government environmental monitoring contractor to prevent incidents between construction contractor and listed species / listed species habitat; for the entire contract the following item is required -meeting with, planning with, scheduling for and cooperating with the Government environmental restoration contractor for restoration of habitat affected by the construction activities; furnishing and installing all fixtures and equipment that are identified as Contractor Furnished Contractor Installed (CFCI) in accordance with the contract documents for the subject bid item; for the entire contract the following item is required - meeting with, planning with, scheduling for and cooperating with the Government and the Government Furniture Installer during Furniture move in and installation for the Government Furnished Government Installed (GFGI) furniture; for the subject bid item the following items are required as necessary - inspections, testing, adjusting and balancing, commissioning for hot weather and cold weather, training of Customs and Border Protection staff; for the entire contract tests shall be conducted after complete systems and or subsystems are installed and operational, and where end dates are not provided tests shall be conducted and continued per specification requirements through just the warranty period after acceptance by owner; for the entire contract the following items are required - closeout documents consisting of but not limited to final submittals, product data, operations and maintenance manuals, testing, adjusting and balancing reports, commissioning reports for hot weather and for cold weather, training reports, inspection notices, final inspection notice, final punchlist complete with signatures, warranty letters and warranty tags, as-builts and renderings; for the entire contract the following item is required - warranty which does not begin until all closeout documents are accepted by the Government for the entire contract;

for the entire contract the following items are required - noise control;

dust control; vibration controls; verify Electric Phasing Polarity for 3-Phase circuits; phasing of construction traffic around the subject bid item; phasing of construction traffic onto and off of Highway 94, the Contractor is responsible for traffic control and for bidding purposes shall include in their proposal costs for all submittals, all traffic control devices and activities including but not limited to multiple

Brown Field Border Patrol Station Dulzura, California W912PL-20-R-0001 barricades with flashers, trailer mounted illuminated boards, and flagmen, complete.

1.2 BASE BID ITEMS

1.2.1 0001 BUILDING 1 BORDER PATROL STATION AND BUILDING 1A CENTRAL PLANT

FACILITY INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING 1 AND BUILDING

1A This is the construction fee for the new Brown Field Border Patrol Station base bid item 0001 BUILDING 1 BORDER PATROL STATION AND BUILDING 1A CENTRAL

PLANT FACILITY INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING 1 AND

BUILDING 1A in accordance with contract specifications and drawings and not including option bid items. Payment for construction fee for the base bid item 0001 BUILDING 1 BORDER PATROL STATION AND BUILDING 1A CENTRAL PLANT

FACILITY INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING 1 AND

BUILDING 1A will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above, complete.

1.2.2 0002 BUILDING 2 VEHICLE MAINTENANCE FACILITY INCLUDING ALL CFCI

FIXTURE AND EQUIPMENT FOR BUILDING 2

This is the construction fee for the new Brown Field Border Patrol Station base bid item 0002 BUILDING 2 VEHICLE MAINTENANCE FACILITY INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING 2 in accordance with contract specifications and drawings and not including option bid items. Payment for construction fee for the base bid item 0002 BUILDING 2 VEHICLE

MAINTENANCE FACILITY INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING

2 will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph

1.1.1 above; including Piping for oil in the Vehicle Maintenance Facility shall be seamless Copper, Type L, hard drawn, conforming to ASTM B88.

Wrought copper and bronze solder-joint pressure fittings must conform to ASME B16.22 and ASTM B75. Cast copper alloy solder-joint pressure fittings must conform to ASME B16.18. Cast copper alloy fittings for flared copper tube must conform to ASME B16.26 and ASTM B62, complete.

1.2.3 0003 BUILDING 3 WATER WELL PUMPHOUSE INCLUDING ALL CFCI FIXTURE AND

EQUIPMENT FOR BUILDING 3

This is the construction fee for the new Brown Field Border Patrol Station base bid item 0003 BUILDING 3 WATER WELL PUMPHOUSE INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING 3 in accordance with contract specifications and drawings and not including option bid items. Payment for construction fee for the base bid item 0003 BUILDING 3 WATER WELL PUMPHOUSE INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING 3 will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above, including but not limited to: above grade crossing shown on drawing sheet SS108 and appurtenances; the domestic water line and fire protection line shown on draing sheet CU-206 and related appurtenances; potable water well permit (from State) and water treatment permit, complete.

Brown Field Border Patrol Station Dulzura, California W912PL-20-R-0001

1.2.4 0004 BUILDING 4A VEHICLE FUELING FACILITY INCLUDING CANOPY AND

INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING 4A

This is the construction fee for the new Brown Field Border Patrol Station base bid item 0004 BUILDING 4A VEHICLE FUELING FACILITY INCLUDING CANOPY AND INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING 4A in accordance with contract specifications and drawings and not including option bid items. Payment for construction fee for the base bid item 0004 BUILDING 4A

VEHICLE FUELING FACILITY INCLUDING CANOPY AND INCLUDING ALL CFCI FIXTURE

AND EQUIPMENT FOR BUILDING 4A will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above; including the entire canopy for the Fuel Facility and the Wash Facility consisting of all of the canopy footings, pilasters, grade beams, concrete walls, trench drains etc. that will provide a complete canopy for the Fueling Station and the Wash Facility, whether the wash facility option item is awarded or not, complete.

1.2.5 0005 ALL SITEWORK EXCLUDING HIGHWAY 94 IMPROVEMENTS AND CLIN 0007

This is the construction fee for the new Brown Field Border Patrol Station base bid item 0005 ALL SITEWORK EXCLUDING HIGHWAY 94 IMPROVEMENTS AND CLIN 0007 in accordance with contract specifications and drawings and not including option bid items. Payment for construction fee for the base bid item 0005 ALL SITEWORK EXCLUDING HIGHWAY 94 IMPROVEMENTS AND CLIN 0007 will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above and this includes but is not limited to: the earthwork and grading for the helipad (OPTION ITEM 4 CLIN 0010); the domestic water line and fire protection line and related appurtenances shown on drawing sheet CU-206;

the sanitary lift station; septic tank, distribution box and related appurtenances; the leach field and related appurtenances shown on drawing sheet CU-301; the 84 foot length of reinforced concrete box culvert and appurtenances shown on drawing sheet CO-102; the salvaging and stockpiling of topsoil as indicated in the plans and specifications; the salvaging and stockpiling of excavated earth materials as indicated in the plans and specifications; the furnishing of a transformer pad of 100 square feet total area and 6 inches thick and electric grounding for the San Diego Gas & Electric transformer; the replacement of portions of visible transite (asbestos) drainage pipe within Campbell Ranch Road boundaries (approximately 20 linear feet of 10" diameter pipe) with suitable pipe of similar dimensions and durability and suitable joints and cutting of existing pipe and capping of ends of existing pipe as necessary, complete.

Blasting shall NOT be utilized for any portion of the excavation work and or earthwork in this contract line item. For crushing operations - after topsoil salvage and earth excavation but before final grading the Contractor shall determine a laydown area within the future parking lot for the purposes of crushing operations. For the laydown area - the contractor shall utilize the area that is bounded on the west by the existing east fence of the CalFire Station, bounded on the south by the northern ground level edge of the proposed 1.3 Acre Feet Detention Pond, and bounded along the northeast by the area required for the proposed 30 foot drive from Highway 94 to the new Station. The Contractor, at no additional cost to the Government, shall maintain and restore existing fences during the duration of the contract. The Contractor is responsible for traffic control and for bidding purposes shall include in their proposal costs for

Brown Field Border Patrol Station Dulzura, California W912PL-20-R-0001 all submittals, all traffic control devices and activities including but not limited to multiple barricades with flashers, trailer mounted illuminated boards, and flagmen, complete.

1.2.6 0006 SEE OPTION 1

0006 SEE OPTION 1

1.2.7 0007 ROCK EXCAVATION ALLOWANCE QUANTITY 1,000 LOOSE CUBIC YARDS

This is the construction fee for the new Brown Field Border Patrol Station base bid item 0007 ROCK EXCAVATION ALLOWANCE QUANTITY 1,000 LOOSE CUBIC YARDS in accordance with contract specifications and drawings and not including option bid items. Payment for construction fee for the base bid item 0007 ROCK EXCAVATION ALLOWANCE QUANTITY 1,000 LOOSE CUBIC YARDS will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above and with the unit of measure in Cubic Yard, complete.

Measurement

The total quantity of excavated loose rock material for which payment will be made will be by in-place (quantity) measurement in cubic yards by computing the difference in loose rock material between the pre-excavation survey of the loose rock material and the post-excavation survey. Available loose rock material is defined as loose rock material located within the boundaries of the required excavation. Specifically, the quantity of excavated loose rock material will be computed using the vertical differences between the pre-excavation survey and the post excavation survey and or the solid rock surface uncovered by excavation. The difference between these two available quantities (pre-excavation and post-excavation) will constitute the quantity of material excavated. Misplaced materials (including any required removal and placement), excessive overdepth excavation and material falling or drawn into the cut from beyond the side slope plane or beyond the limits indicated, will be excluded from the quantities for which payment will be made. The Planemeter and or Triangulated Irregular Network (TIN) method will be used for quantity determination. Blasting shall NOT be utilized for any portion of the excavation work and or earthwork in this contract line item.

Unit of Measure: cubic yard

See Variation in Estimated Quantity Clause.

1.2.8 0008 ELECTRIC AND COMMUNICATION WIRE ALLOWANCE

The $163,276.00 is the estimated fee that the electric utility will charge for the connection of the electric grid to the new Brown Field Border Patrol Station base bid item 0008 ELECTRIC AND COMMUNICATION WIRE ALLOWANCE in accordance with contract specifications and drawings and not including option bid items. Payment for the fee for the base bid item 0008 ELECTRIC AND COMMUNICATION WIRE ALLOWANCE will be made at the applicable contract price which payment shall constitute full compensation for: all fees

Brown Field Border Patrol Station Dulzura, California W912PL-20-R-0001 incurred by San Diego Gas & Electric (SDG&E) related to the electric power connection between the power grid and the new facility, including conductors, underground appurtenances and conduits, poles and appurtenances, excavation, backfilling, compaction, transformer, meter and final electric power connection; the installation of new power poles from existing grid to the new facility for San Diego Gas and Electric (SDG&E) power lines; the coordination for relocation of power lines with San Diego Gas and Electric; all fees incurred by AT&T related to the communication wire (fiber optic line) connection between the communication grid and the new facility, including any wire / fiber optic lines, underground appurtenances and conduits, poles and appurtenances, excavation, backfilling, compaction, and final communication wire / fiber optic connection; the installation of new telephone/communication poles from existing grid to the new facility for AT&T lines; the coordination for relocation of telephone/communication lines with AT&T; the power poles and communication poles and power line work and communication line work shall be performed in accordance with each utility company's installation design and construction requirements, complete. A modification will be issued to account for the difference between the actual cost incurred by the electric utility and the communication utility fee and the fee of $163,276.00.

1.3 OPTION BID ITEMS

1.3.1 OPTION 1 CLIN 0006 HIGHWAY 94 IMPROVEMENTS

This is the construction fee for the new Brown Field Border Patrol Station option bid item OPTION 1 CLIN 0006 HIGHWAY 94 IMPROVEMENTS in accordance with contract specifications and drawings and not including other option bid items. Payment for construction fee for the option bid item OPTION 1 CLIN 0006 HIGHWAY 94 IMPROVEMENTS will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above and this includes but is not limited to: the phasing of work on the drive ways and accesses to Highway 94 as indicated in Section 01 30 00 Paragraph 1.18. DIGGING PERMITS AND ROAD CLOSINGS; the scheduling and phasing of this work with OPTION 8 CLIN 0015 UTILITY ALLOWANCE RELATED TO OPTION 0001; All materials within the "Route 94" drawings shall follow Caltrans standards; the removal (salvage if possible), and the replacement and reinstallation of wood post / metal post and barbed wire fencing and other fencing within the Highway 94 Improvements with the centerline of the reinstalled fences to be on the edge of the new right of way, complete. Blasting shall NOT be utilized for any portion of the excavation work and or earthwork in this contract line item. The Contractor is responsible for traffic control and for bidding purposes shall include in their proposal costs for all submittals, all traffic control devices and activities including but not limited to multiple barricades with flashers, trailer mounted illuminated boards, flagmen and mobilization and demobilization for these traffic control devices for this option bid item, complete.

1.3.2 OPTION 2 CLIN 0014 ABANDONED ITEMS

This is the construction fee for the new Brown Field Border Patrol Station option bid item OPTION 2 CLIN 0014 ABANDONED ITEMS in accordance with contract specifications and drawings and not including other option bid

Brown Field Border Patrol Station Dulzura, California W912PL-20-R-0001 items. Payment for construction fee for the option bid item OPTION 2 CLIN 0014 ABANDONED ITEMS will be made at the applicable contract price which payment shall constitute full compensation for the removal and disposal of items left on Government property including but not limited to - wood pile, various man made items, wood pallets, shed(s), metal cabinets, pool / jacuzzi like object with light blue interior lining, metal frames of various sorts, metal parts, boxes and trash, including Contractor determination of the abandoned items within the Government property, complete.

1.3.3 OPTION 3 CLIN 0009 BUILDING 4 VEHICLE WASH FACILITY (CANOPY TO REMAIN

OVER BUILDING 4A) AND INCLUDING ALL CFCI FIXTURE AND EQUIPMENT FOR BUILDING 4

This is the construction fee for the new Brown Field Border Patrol Station option bid item OPTION 3 CLIN 0009 BUILDING 4 VEHICLE WASH FACILITY (CANOPY

TO REMAIN OVER BUILDING 4A) AND INCLUDING ALL CFCI FIXTURE AND EQUIPMENT

FOR BUILDING 4 in accordance with contract specifications and drawings and not including other option bid items. Payment for construction fee for the option bid item OPTION 3 CLIN 0009 BUILDING 4 VEHICLE WASH FACILITY (CANOPY

TO REMAIN OVER BUILDING 4A) AND INCLUDING ALL CFCI FIXTURE AND EQUIPMENT

FOR BUILDING 4 will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above, complete.

1.3.4 OPTION 4 CLIN 0010 HELIPAD PAVING, LIGHTING, GROUNDING, (EXCLUDES

GRADING)

This is the construction fee for the new Brown Field Border Patrol Station option bid item OPTION 4 CLIN 0010 HELIPAD PAVING, LIGHTING, GROUNDING, (EXCLUDES GRADING) in accordance with contract specifications and drawings and not including other option bid items. Payment for construction fee for the option bid item OPTION 4 CLIN 0010 HELIPAD PAVING, LIGHTING, GROUNDING, (EXCLUDES GRADING) will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above, including State Heliport Permit, excluding earthwork and grading for the helipad that are accomplished in

CLIN 0005 ALL SITEWORK EXCLUDING HIGHWAY 94 IMPROVEMENTS AND CLIN 0007,

complete.

1.3.5 OPTION 5 CLIN 0011 COMMUNICATION TOWER INCLUDING FOUNDATION

This is the construction fee for the new Brown Field Border Patrol Station option bid item OPTION 5 CLIN 0011 COMMUNICATION TOWER INCLUDING FOUNDATION in accordance with contract specifications and drawings and not including other option bid items. Payment for construction fee for the option bid item OPTION 5 CLIN 0011 COMMUNICATION TOWER INCLUDING FOUNDATION will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above, complete.

Brown Field Border Patrol Station Dulzura, California W912PL-20-R-0001

1.3.6 OPTION 6 CLIN 0012 SECOND WATER WELL

This is the construction fee for the new Brown Field Border Patrol Station option bid item OPTION 6 CLIN 0012 SECOND WATER WELL in accordance with contract specifications and drawings and not including other option bid items. Payment for construction fee for the option bid item OPTION OPTION 6 CLIN 0012 SECOND WATER WELL will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above; including depth of this second well shall be not less than 1,010 feet below ground surface (bgs) nor greater than 1,020 feet bgs for pricing purposes; and that this second well shall be located within the area denoted "area available for second well" shown on drawing CU-201 to avoid conflicts with both the environment sensitive areas and the first well, complete.

1.3.7 OPTION 7 CLIN 0013 BUILDING 5 CANINE KENNEL FACILITY INCLUDING ALL

CFCI FIXTURE AND EQUIPMENT IN BUILDING 5

This is the construction fee for the new Brown Field Border Patrol Station option bid item OPTION 7 CLIN 0013 BUILDING 5 CANINE KENNEL FACILITY INCLUDING ALL CFCI FIXTURE AND EQUIPMENT IN BUILDING 5 in accordance with contract specifications and drawings and not including other option bid items. Payment for construction fee for the option bid item OPTION 7

CLIN0013 BUILDING 5 CANINE KENNEL FACILITY INCLUDING ALL CFCI FIXTURE AND

EQUIPMENT IN BUILDING 5 will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above, complete.

1.3.8 OPTION 8 CLIN 0015 UTILITY ALLOWANCE RELATED TO OPTION 0001

The $66,988.00 is the estimated construction fee that the electric power utility and the communication utility will charge for the relocation of existing poles and or the installation of new poles and for the relocation of power lines and communication lines and reconnection of power lines and communication lines for the new Brown Field Border Patrol Station option bid item OPTION 8 CLIN 0015 UTILITY ALLOWANCE RELATED TO OPTION 0001 in accordance with contract specifications and drawings and not including other option bid items. Payment for construction fee for the option bid item OPTION 8 CLIN 0015 UTILITY ALLOWANCE RELATED TO OPTION 0001 will be made at the applicable contract price which payment shall constitute full compensation for all necessary features of construction as indicated in this Section 01 20 00 Price and Payment Procedures Paragraph 1.1.1 above and this includes but is not limited to: the relocation existing power poles or installation of new power poles for San Diego Gas and Electric (SDG&E) power lines; the coordination for relocation of power poles and or installation of new power poles and relocation of existing and or installation of new power lines with San Diego Gas and Electric; the relocation of existing telephone/communication poles or installation of new telephone/ communication poles for AT&T lines; the coordination for relocation of communication poles and or installation of new telephone/ communication poles and relocation of existing and or new telephone/ communication lines with AT&T; the power poles and communication poles and power line work and communication line work shall be performed in accordance with each utility company's installation design and construction requirements; the scheduling and phasing of this work with Option 0001, Brown Field Border Patrol Station Dulzura, California W912PL-20-R-0001 complete. A modification will be issued to account for the difference between the actual cost incurred by the electric utility and communication utility and the fee of $66,988.00.

1.4 OPTIONS

1.4.1 52.217-3 EVALUATION EXCLUSIVE OF OPTIONS (APR 1984)

The Government will evaluate offers for award purposes by including only the price for the basic requirements i.e. options will not be included in the evaluation for award purposes.

(End of Provision)

1.4.2 EXERCISE OF OPTION 1, 2, 3, 4, 5, 6, 7 and 8

A. The Government reserves the right to exercise the option(s) by written notice to the Contractor either singularly or in any combination for up to the following calendar days after the Contractor’s receipt of Award Notice without an increase in the Offeror’s bid price. Completion of added options shall continue at the same schedule as the Base Bid and as indicated in this RFP solicitation and or unless otherwise noted in SECTION 00 70 00 SPECIAL CONTRACT REQUIREMENTS Paragraph COMMENCEMENT, PROSECUTION

AND COMPLETION OF WORK.

B. The price for exercise of the option includes all work and effort associated with the scope of that item. For determination of lowest bid, see paragraph: EVALUATION EXCLUSIVE OF OPTIONS in this Section. No additional time for contract completion will be allowed when an option is exercised. The given contract completion time was formulated to include time necessary to perform all option work.

C. OPTION 1 – The Government reserves the right to Award Option 1 within 360 Calendar Days from Contractor Receipt of Award Notice of the contract base work.

D. OPTION 2, 3, 4, 5, 6, 7 and 8 – The Government reserves the right to Award Option 2, 3, 4, 5, 6, 7 and 8 within 120 Calendar Days from Contractor Receipt of Award Notice of the contract base work.

1.5 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule

1.6 SUBMITTALS

Brown Field Border Patrol Station Dulzura, California W912PL-20-R-0001

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Schedule of Prices; G, RE

Earned Value Report; G, RE

Right of Entry for Construction Permits; FIO

Caltrans Access Permit; FIO

Caltrans Encroachment Permit; FIO

Potable Water Well Permit; FIO

Water Treatment Permit; FIO

Septic System Permit; FIO

Second Well Location as applicable; FIO

State Heliport Permit; FIO

SD-02 Shop Drawings

Calculations; G

1.7 SCHEDULE OF PRICES and EARNED VALUE REPORT

1.7.1 Data Required

This contract requires the use of a cost-loaded Network Analysis Schedule (NAS). The information required for the Schedule of Prices will be entered as an integral part of the Network Analysis Schedule. Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices and an Earned Value Report consistant with the construction contract line items or as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices.

This is the start of the file's text. The full file is on GovTribe.