About this file

Specifications

View the file

Other files

File Type Posted
11R0004_Am13.pdf PDF
11R0004_Am12.pdf PDF
11R0004_Am11.pdf PDF
Civil.zip ZIP file
Architectural.zip ZIP file
11R0004_Am10.pdf PDF
Geotech.zip ZIP file
Dwgs.zip ZIP file
11R0004_Am9.pdf PDF
11R0004_Am8.pdf PDF
JA.doc DOC document
11R0004-AM07.pdf PDF
11R0004-AM06.pdf PDF
11R0004-AM05.pdf PDF
11R0004-AM04.pdf PDF
Am3.pdf PDF
Am2.pdf PDF
11R0004-AM01.pdf PDF
W912PL-11-R-0004 Vol 2.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in Acrobat 9 or Adobe Reader 9, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

01 82 00-1

SECTION 01 82 00

COMMISSIONING REQUIREMENTS

PART 1 - GENERAL

1.1 DEFINITIONS

A. BOD: Basis of Design. A document, that records concepts, calculations, decisions, and product selections used to meet the Project Requirements (PR) and to satisfy applicable regulatory requirements, standards, and guidelines. The document includes both narrative descriptions and lists of individual items that support the design process.

B. Cx Plan: Commissioning Plan. A document, prepared by CxA, that outlines the organization, schedule, allocation of resources, and documentation requirements of the commissioning process.

C. Cx: Commissioning

D. CxA: Commissioning Authority independently contracted by the

Government to coordinate Commissioning.

E. Cx Issues Log: Commissioning tracking document, which captures deviations from PR and project issues.

F. PR: Project Requirements. A document that details the functional requirements of a Project and expectations of how it shall be used and operated. This document includes Project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information.

G. TAB: Testing, Adjusting, and Balancing.

H. Cx Team: Commissioning Team. Members Appointed by the Government and

CxA: Individuals, each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated actions.

1. The Cx team shall consist of, but not be limited to, the

Contractor, including CQC System Manager, and sub-contractors installers, suppliers, and specialists deemed appropriate by the CxA.

2. Members Appointed by Government:

a. CxA: An entity identified by the Government who leads, plans, schedules, and coordinates the Cx team to implement the Cx process.

01 82 00-2

b. Representatives of the facility user and operation and maintenance personnel

c. Architect and engineering design professionals

1.2 INCLUDED SYSTEMS

A. The following systems and their components are the focus of the Commissioning Process. Commissioning of these systems shall require coordination among the various subcontractors due to their complexity:

1. HVAC System

a. HVAC control systems

b. Building automation system & DDC Controls

c. Rooftop air handling units

d. HVAC Air distribution systems (ducts, VAV and fan powered boxes, air devices, exhaust fans, AC units, wall louvers, and roof hoods)

e. Boilers and Water heaters

f. Unit heaters

g. Radiant ceiling panels

h. Pumps

i. Piping

j. Testing, adjusting and balancing

2. Plumbing System

a. Hot and cold domestic water systems

b. Waste and vent piping

c. Plumbing fixtures and valves

3. Electrical System

a. Receptacle system

b. Lighting systems

c. Electric panels

d. Transformers

e. Electric motors

4. Other

a. Fire alarm system

b. Fire sprinkler system

c. Fire/smoke dampers

d. Building envelope

e. Energy applications – wall, window, and roofing

1.3 COMMISSIONING RESPONSIBILITIES

A. Refer to the Cx Plan for specific responsibilities of the Government, Contractor, Design Agent and CxA

01 82 00-3

1.4 COMMISSIONING DOCUMENTATION

A. The following is documentation that is provided by the Contractor to the CxA in support of completing the Cx process activities:

1. System coordination plans – Provide detailed description of the precedence of installing systems, assemblies, equipment, and components to achieve the PR prior to the start of construction.

2. Comments on the draft construction checklists provided by the commissioning authority. If contractor has checklists that they would like to use in lieu of the construction checklists, these need to be provided with their comments. Commissioning authority may incorporate all, some, or none of the comments or checklists.

3. Training documentation per requirements of this specification.

4. Instruction data and manuals per requirements of Section 01 73 00

OPERATIONS AND MAINTENANCE INSTRUCTIONS, in electronic and paper format.

5. Comments on the Cx process test procedures developed and provided by the CxA.

6. Comments on status of commissioning process issues.

7. Provision of copies of submittals to CxA

8. Provision of project construction schedule updates with up-to-date Cx milestone information.

1.5 COORDINATION

A. Pre-Functional Testing (PFT) Meetings: The contractor/sub-contractors shall conduct PFT meetings, coordinated with the CxA and the Government, consisting of the Cx team to review startup reports, testing procedures, testing personnel and instrumentation requirements, and manufacturers' authorized service representative services for each system, assembly, equipment, and component to be tested.

B. Testing Coordination: The Contractor shall coordinate Cx controls verification and functional performance testing activities to accommodate required quality-assurance requirements of the specifications with a minimum of delay.

C. Sub-contractor/Vendor/Installer Services: The Contractor shall coordinate services of sub-contractor/vendor/installer services as required to support Cx activities.

01 82 00-4

1.6 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Commissioning Team

List of team members who will represent the Contractor in the Cx construction checklist and functional performance testing, at least 2 weeks prior to the start of pre-commissioning checks. Proposed revision to the list, prior to the start of the impacted work.

Test Procedures

Detailed procedures for equipment start-up and pre-commissioning checks, at least 4 weeks prior to the start of pre-commissioning checks.

Test Schedule; G

Schedule for pre-commissioning checks and functional performance tests, at least 2 weeks prior to the start of pre-commissioning checks.

SD-06 Test Reports

Test Reports; G

Completed pre-commissioning checklists and manufactures equipment start-up reports organized by system and by subsystem. The results of failed tests shall be included along with a description of the corrective action taken.

PART 2 - PRODUCTS

2.1 SCHEDULE

A. The Contractor shall provide the CxA with a detailed construction schedule within 30 days of the commencement of work. The construction schedule shall contain all Cx milestone activities and time durations as listed in the Cx Plan. The Contractor shall provide monthly updated to the construction schedule.

B. The CxA shall provide the Contractor with a schedule of Cx activities. The Cx activities shall be contained in the Cx Plan as part of the Cx process schedule. The Cx project schedule shall contain

01 82 00-5

Cx milestone activities and expected time durations. Cx activities shall not be critical path activities.

C. The Contractor shall update the overall project schedule to incorporate Cx activities as required to accommodate Cx activities for each revision to the construction schedule.

2.2 SUBMITTAL REQUIREMENTS

A. The CxA shall provide a listing to the Contracting Officer of the

Contractor’s submittals (shop drawings and manufacture’s data) that will be reviewed by the CxA concurrent with the designer’s review.

The CxA review shall help identify any issues that might otherwise result in re-work and/or modifications. Also, the CxA shall provide a listing of information required from the Contractor for development of the System and Manuals.

B. Within 90 days of submittal approval, the Contractor shall submit the following additional information:

1. Manufacturer’s installation instructions

2. Operation and maintenance manuals

3. Equipment specifications

4. Performance information. This shall include all ranges of operation (i.e. 0 to 100% load) for the entire range of expected performance characteristics (outdoor air temperature, supply air temperatures, etc.).

5. Warranties.

2.3 SITE OBSERVATION AND VERIFICATION

A. The CxA shall perform routine site visits during the construction period.

B. The CxA site visit reports shall provide a summary of commissioning activities accomplished including, but not limited to;

accomplishments, Cx process issues, systematic problems, and pending tasks.

PART 3 - EXECUTION

3.1 SAMPLING RATE VERIFICATION AND REIMBURSEMENT

A. Re-Testing: When the random sample for Cx construction checklists, controls verification, or functional performance testing does not meet the requirements of PR or construction documents, then the CxA shall in general perform an increased sample rate double the initial rate.

If this does not meet the expectations, then a meeting with the

01 82 00-6

Government, CxA and Contractor/subcontractor shall be scheduled to address the concerns and results of the verification by the CxA. As an example, if this involves a construction checklist, the Contractor/subcontractor shall be required to physically recheck all similar installed systems, assemblies, components, or equipment against the installation or checklist requirements, within five working days.

B. Contractor Reimbursement of CxA Verification: If any system deficiency prevents the successful completion of the test or if any participating non-Government commissioning team member of which participation is specified is not present for a specific commissioning verification, the Contractor shall reimburse all cost for travel, materials, and time for the CxA at the Professional Service Rates.

3.2 CONTROL SYSTEM VERIFICATION:

A. Point-to-Point Verification: All wiring shall be checked out by the

Control Contractor from end to end, point to point, from field to computer screen to ensure correct connection and a system free from wiring defects.

B. Prior to CxA verification, the Control Contractor shall be responsible for complete input/output checkout quality assurance.

1. Sensor and Actuator Calibration, General:

a. Instrument calibration shall be performed by the Control Contractor. “Factory calibration” or “calibration by exception” is not acceptable.

b. All field-installed temperature, relative humidity, CO, CO2 and pressure sensors and gages, and all actuators (dampers and valves) on all equipment shall be calibrated by the Contractor using the methods described below.

Alternate methods may be used, if approved by the Contracting Officer beforehand. All test instruments shall have had a certified calibration within the last 12 months. Sensors installed in the unit at the factory with calibration certification provided need not be field calibrated.

c. All calibration procedures used by the Contractor shall be fully documented as ”Pre-functional Checklists” or other suitable forms, clearly referencing the procedures followed and written documentation of initial, intermediate and final results.

2. Sensor Calibration Methods: The Contractor shall verify the following:

01 82 00-7

a. All Sensors and Transducers. Verify that all sensor and transducer locations are appropriate and away from causes of erratic operation. Verify that sensors and transducers with shielded cable are grounded only at one end.

b. Sensors without Transmitters. Make a reading with a calibrated test instrument within 6 inches of the site sensor. Verify that the sensor is within the specified tolerances. If not, install offset in BAS, calibrate or replace sensor.

c. Sensors with Transmitters. Connect a signal generator.

Adjust transmitter zero and span to match the signal generator until the ammeter reads 4 mA. Make a reading with a calibrated test instrument within 6 inches of the site sensor. Verify that the sensor reading is within the specified tolerances. If not, replace sensor and repeat.

d. Sensor Tolerances. The following are the tolerances of the actual sensors in the system. Unless noted differently on the CxA test procedure, use the following:

1) Temperature (space or room): +/- 1.0 degF.

2) Temperature (duct): +/- 0.5 degF.

3) Pressure (duct static): +/- 0.05 in. w.c.

4) Pressure (other): +/- 5.0 pct of reading.

5) Flow rates for air: +/- 5.0 pct of reading.

6) Flow rates for water: +/- 5.0 pct of reading.

7) Relative Humidity: +/- 5.0 pct of reading.

8) Oxygen or CO2 monitor: +/- 1.0 pct of span.

e. Valve and Damper Stroke Setup and Check

1) For all valve and damper actuator positions checked, verify the actual position against the EMS readout.

2) Set pumps or fans to normal operating mode (If the system could be affected by this, then shut down the system). Command valve or damper closed, visually verify that valve or damper is closed and adjust output zero signal as required. Command valve or damper open, verify position is full open and adjust output signal as required. Command valve or damper to a few intermediate

01 82 00-8 positions. If actual valve or damper position doesn’t reasonably correspond, replace actuator.

3) Closure for normally closed valves and dampers (spring-loaded only). Disconnect power to the actuator motor, and verify the valve or damper moves to full closed position. If not spring-loaded, conduct verification by disconnecting the signal wire. Restore to normal.

4) Closure for normally open valves and dampers (spring-loaded only). Disconnect power to the actuator motor, and verify the valve or damper moves to full open position. If not spring-loaded, conduct verification by disconnecting the signal wire. Restore to normal.

3.3 TRAINING

A. The Contractor shall coordinate and perform operations and maintenance (O&M) training of commissioned equipment/systems and equipment/systems as called out throughout the specifications to meet the PR (Project Requirements) with guidance from the CxA. O&M training shall comply with the requirements of this specification, and relevant equipment specific training specification requirements. The timing of provision of training deliverables as listed in this section shall be per the Cx process schedule as contained in the Cx Plan. O&M Training shall include the following:

1. Contractor shall provide the Government and CxA with a list of training sessions by equipment or system as required per contract specifications or requested by the CxA.

2. The Government shall provide Contractor and CxA with a list of groups who will be required attend training sessions by equipment or system. An example of the types of groups are Operations (custodial), Maintenance (Crafts), and Tech Services groups

3. Contractor shall provide the CxA with a training agenda for each training session for review by the CxA. The training agenda provides a means of communication between the Contractor and each sub-contractor/installer/vendor providing training. The CxA may provide guidance to the Contractor to produce the training agenda. The training agenda is a form, which guides the sub-contractor/installer/vendor to provide the following information to the Contractor prior to training;

a) Proposed Training Time, Date(s), and Location(s) - The amount of training time must be sufficient to cover all topics as required by specifications. Training time shall be at the minimum, what is required per corresponding specifications.

Provide anticipated dates and locations.

01 82 00-9

b) Trainer Contact Information - including address, phone number, fax number and e-mail.

c) Training Materials Provided by Trainer – Use/refer to O&M manual sections where applicable.

d) Trainee Groups – List trainee groups for which training will be provided for the training session.

e) Course Topics – Provide a review of each O&M data item as listed in the O&M Data Package described in Section 01 78 23 OPERATIONS AND MAINTENANCE DATA. Provide an explanation of each item’s relevance to site-specific operations and maintenance.

f) Confirmation that O&M data submittals and data content provided by the respective sub-contractor as per requirements of Section 01 78 23 OPERATIONS AND MAINTENANCE DATA, paragraphs SUBMITTALS and DATA CONTENT, are being used as training materials for training session.

g) List training type (classroom-type, demonstration-type, or a combination thereof) in order to provide training for each training topic listed in this specification and for any respective training requirements as contained in relevant equipment-specific specifications. The trainer shall estimate the amount of time of training that shall be required for each topic.

h) Videotaping – Confirmation that training conducted on Cx systems shall be videotaped. Videotaping of sessions shall be of sufficient quality to comprehend all training concepts presented, including ability to audibly and visually understand presenter presentation and demonstration(s).

i) Approval Section- Provide approval spaces for the Contractor and CxA, with dates

4. Sub-contractor/installer/vendor shall fill-out training agenda for each training session to the Contractor. Contractor shall provide CxA and the Government with a copy of training agendas for each training session for review no later than 4 weeks prior to training for review. Contractor shall work with CxA to ensure that training is addressing all requirements of PR and specifications via the training agendas no later than 2 weeks prior to training.

5. Training sessions shall provide instruction for installation. The trainer shall use a combination of demonstration and classroom training. The trainer shall use O&M data per respective equipment as submitted per requirements of Section 01 73 00

OPERATIONS AND MAINTENANCE INSTRUCTIONS.

01 82 00-10

6. Training sessions shall provide instruction for operation, to include but not limited to; prestart-up, start-up, break-in, shutdown, seasonal, emergency, and special operation procedures.

The trainer shall use a combination of demonstration and classroom training. The trainer shall use training data per the respective equipment as submitted per requirements of Section

01 73 00 OPERATIONS AND MAINTENANCE INSTRUCTIONS.

7. Training sessions shall provide instruction for maintenance, to include but not limited to; procedures and instructions for problem corrections, preventative maintenance, testing, alignment, adjustment, and repair. The trainer shall use a combination of demonstration and classroom training. The trainer shall use training data per the respective equipment as submitted per requirements of Section 01 73 0 OPERATIONS AND MAINTENANCE

INSTRUCTIONS.

8. Training sessions shall provide instruction for the removal, replacement, disassembly, and assembly of the critical components/assemblies. The instruction shall include information on the tools required and any specific tolerances, settings, and/or adjustments. The trainer shall use a combination of demonstration and classroom training. The trainer shall use training data per the respective equipment as submitted per requirements of Section 01 73 00 OPERATIONS AND MAINTENANCE

INSTRUCTIONS.

9. The trainers shall provide sufficient time to reply to questions raised by training groups.

10. Arrange for video recording of commissioned system demonstrations and training sessions, including all question and answers segments of the training sessions. Submit two copies of indexed recordings in CD and DVD format, labeled to identify each session.

11. Contractor shall provide an approved (signed) copy of the final training agenda and training session attendance sign-off sheet for each training session to the Government and CxA at the completion of all training sessions. The training session attendance sign-off sheet shall contain; the training session title, equipment or system covered, the printed and signed name of each attendee and trainer, date(s) of training, and name of trainee department. The training session sign-off sheet shall also include a full description of any equipment or systems that were not operational or functioning properly during demonstration training. The CxA will insert the signed training agenda and training session sign-off sheet for each session into the Cx Record.

01 82 00-11

B. All training sessions shall be scheduled and coordinated by the Contractor.

C. Training shall be completed and accepted prior to application for substantial completion.

-- End of Section --

PART 1 - GENERAL

DEFINITIONS

BOD: Basis of Design. A document, that records concepts, calculations, decisions, and product selections used to meet the Project Requirements (PR) and to satisfy applicable regulatory requirements, standards, and guidelines. The document includes b...

Cx Team: Commissioning Team. Members Appointed by the Government and CxA: Individuals, each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated actions.

2. Members Appointed by Government:

a. CxA: An entity identified by the Government who leads, plans, schedules, and coordinates the Cx team to implement the Cx process.

b. Representatives of the facility user and operation and maintenance personnel

c. Architect and engineering design professionals

INCLUDED SYSTEMS

The following systems and their components are the focus of the Commissioning Process. Commissioning of these systems shall require coordination among the various subcontractors due to their complexity:

a. HVAC control systems

b. Building automation system & DDC Controls

c. Rooftop air handling units

d. HVAC Air distribution systems (ducts, VAV and fan powered boxes, air devices, exhaust fans, AC units, wall louvers, and roof hoods)

e. Boilers and Water heaters

f. Unit heaters

g. Radiant ceiling panels

h. Pumps

i. Piping

j. Testing, adjusting and balancing

4. Plumbing System

a. Hot and cold domestic water systems

b. Waste and vent piping

c. Plumbing fixtures and valves

5. Electrical System

a. Receptacle system

b. Lighting systems

c. Electric panels

d. Transformers

e. Electric motors

6. Other

a. Fire alarm system

b. Fire sprinkler system

c. Fire/smoke dampers

d. Building envelope

e. Energy applications – wall, window, and roofing

COMMISSIONING RESPONSIBILITIES

Refer to the Cx Plan for specific responsibilities of the Government, Contractor, Design Agent and CxA

COMMISSIONING DOCUMENTATION

The following is documentation that is provided by the Contractor to the CxA in support of completing the Cx process activities:

COORDINATION

Pre-Functional Testing (PFT) Meetings: The contractor/sub-contractors shall conduct PFT meetings, coordinated with the CxA and the Government, consisting of the Cx team to review startup reports, testing procedures, testing personnel and instrumentat...

Testing Coordination: The Contractor shall coordinate Cx controls verification and functional performance testing activities to accommodate required quality-assurance requirements of the specifications with a minimum of delay.

Sub-contractor/Vendor/Installer Services: The Contractor shall coordinate services of sub-contractor/vendor/installer services as required to support Cx activities.

SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for t...

PART 2 - PRODUCTS

SCHEDULE

The Contractor shall provide the CxA with a detailed construction schedule within 30 days of the commencement of work. The construction schedule shall contain all Cx milestone activities and time durations as listed in the Cx Plan. The Contractor sha...

The CxA shall provide the Contractor with a schedule of Cx activities. The Cx activities shall be contained in the Cx Plan as part of the Cx process schedule. The Cx project schedule shall contain Cx milestone activities and expected time durations

The Contractor shall update the overall project schedule to incorporate Cx activities as required to accommodate Cx activities for each revision to the construction schedule.

SUBMITTAL REQUIREMENTS

The CxA shall provide a listing to the Contracting Officer of the Contractor’s submittals (shop drawings and manufacture’s data) that will be reviewed by the CxA concurrent with the designer’s review. The CxA review shall help identify any issues tha...

Within 90 days of submittal approval, the Contractor shall submit the following additional information:

2. Operation and maintenance manuals

3. Equipment specifications

4. Performance information. This shall include all ranges of operation (i.e. 0 to 100% load) for the entire range of expected performance characteristics (outdoor air temperature, supply air temperatures, etc.).

5. Warranties.

SITE OBSERVATION AND VERIFICATION

The CxA shall perform routine site visits during the construction period.

The CxA site visit reports shall provide a summary of commissioning activities accomplished including, but not limited to; accomplishments, Cx process issues, systematic problems, and pending tasks.

PART 3 - EXECUTION

SAMPLING RATE VERIFICATION AND REIMBURSEMENT

Re-Testing: When the random sample for Cx construction checklists, controls verification, or functional performance testing does not meet the requirements of PR or construction documents, then the CxA shall in general perform an increased sample rate ...

Contractor Reimbursement of CxA Verification: If any system deficiency prevents the successful completion of the test or if any participating non-Government commissioning team member of which participation is specified is not present for a specific c...

CONTROL SYSTEM VERIFICATION:

Point-to-Point Verification: All wiring shall be checked out by the Control Contractor from end to end, point to point, from field to computer screen to ensure correct connection and a system free from wiring defects.

Prior to CxA verification, the Control Contractor shall be responsible for complete input/output checkout quality assurance.

a. Instrument calibration shall be performed by the Control Contractor. “Factory calibration” or “calibration by exception” is not acceptable.

b. All field-installed temperature, relative humidity, CO, CO2 and pressure sensors and gages, and all actuators (dampers and valves) on all equipment shall be calibrated by the Contractor using the methods described below. Alternate methods may be used, �

c. All calibration procedures used by the Contractor shall be fully documented as ”Pre-functional Checklists” or other suitable forms, clearly referencing the procedures followed and written documentation of initial, intermediate and final results.

2. Sensor Calibration Methods: The Contractor shall verify the following:

a. All Sensors and Transducers. Verify that all sensor and transducer locations are appropriate and away from causes of erratic operation. Verify that sensors and transducers with shielded cable are grounded only at one end.

b. Sensors without Transmitters. Make a reading with a calibrated test instrument within 6 inches of the site sensor. Verify that the sensor is within the specified tolerances. If not, install offset in BAS, calibrate or replace sensor.

c. Sensors with Transmitters. Connect a signal generator. Adjust transmitter zero and span to match the signal generator until the ammeter reads 4 mA. Make a reading with a calibrated test instrument within 6 inches of the site sensor. Verify that the �

d. Sensor Tolerances. The following are the tolerances of the actual sensors in the system. Unless noted differently on the CxA test procedure, use the following:

1) Temperature (space or room): +/- 1.0 degF.

2) Temperature (duct): +/- 0.5 degF.

3) Pressure (duct static): +/- 0.05 in. w.c.

4) Pressure (other): +/- 5.0 pct of reading.

5) Flow rates for air: +/- 5.0 pct of reading.

6) Flow rates for water: +/- 5.0 pct of reading.

7) Relative Humidity: +/- 5.0 pct of reading.

8) Oxygen or CO2 monitor: +/- 1.0 pct of span.

e. Valve and Damper Stroke Setup and Check

1) For all valve and damper actuator positions checked, verify the actual position against the EMS readout.

2) Set pumps or fans to normal operating mode (If the system could be affected by this, then shut down the system). Command valve or damper closed, visually verify that valve or damper is closed and adjust output zero signal as required. Command valve or�

3) Closure for normally closed valves and dampers (spring-loaded only). Disconnect power to the actuator motor, and verify the valve or damper moves to full closed position. If not spring-loaded, conduct verification by disconnecting the signal wire. Res�

4) Closure for normally open valves and dampers (spring-loaded only). Disconnect power to the actuator motor, and verify the valve or damper moves to full open position. If not spring-loaded, conduct verification by disconnecting the signal wire. Restore�

TRAINING

The Contractor shall coordinate and perform operations and maintenance (O&M) training of commissioned equipment/systems and equipment/systems as called out throughout the specifications to meet the PR (Project Requirements) with guidance from the CxA

All training sessions shall be scheduled and coordinated by the Contractor.

Training shall be completed and accepted prior to application for substantial completion.

01 04 00-1

SECTION 01 04 00

MECHANICAL ROOM LAYOUT AND COORDINATION

1.1 GENERAL REQUIREMENTS

The Contractor shall coordinate the layout of mechanical, fire protection, and electrical equipment within the mechanical room and shall insure that equipment to be furnished is located such that all equipment is accessible for operation, maintenance, filter replacement, and code requirements.

Contractor shall coordinate with all subcontractors and manufacturers to assure that equipment provided will meet the functional parameters specified and conform to the necessary clearances required by the manufacturer for operation, maintenance and repair.

1.2 SUBMITTALS

Government approval is required for submittals with a “G” designation;

submittals not having a “G” designation are for information only. When used, a designation following the “G” designation identifies the office

SD-01 Preconstruction Submittals

Mechanical Room Plan; G

The Contractor shall submit for approval a mechanical room floor plan of all equipment, including piping, valves, conduits, electrical panels, control panels, and fire protection panels. The floor plan shall be drawn to 1:20 metric scale (1/2" = 1 foot scale) and shall indicate dimensionally the locations of all equipment and required clearances recommended by the manufacturer and/or codes. Equipment shall be drawn to scale and noted as to type and model. Interior elevations shall be provided to indicate the intended use of vertical space. The drawings shall reflect all ducting and piping that will affect equipment clearances. The mechanical room layout drawings shall be submitted within 60 calendar days after receipt of notice to proceed in accordance with Section, SUBMITTAL PROCEDURES. These drawings shall show all of the constraints specified in the GENERAL REQUIREMENTS paragraph above and applicable mechanical and electrical technical specification sections. The Contractor shall obtain approval of the mechanical room layout drawings prior to the construction of any component (stub-outs, floor slab, walls, etc.) of the mechanical room.

01 04 00-2

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

PART 1 - GENERAL

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

INDEX

FOR

DESIGN/BUILD

FY11 AEROSPACE MAINTENANCE AND REGENERATION

GROUP (AMARG) HANGAR

DAVIS-MONTHAN AIR FORCE BASE,

PIMA COUNTY, TUSCON, ARIZONA

PROPOSAL REQUIREMENTS,

CONDITIONS OF THE CONTRACT

AND SPECIFICATIONS VOLUME 1 OF 2

APPENDIX VOLUME 2 OF 2

01 08 00-1

SECTION 01 08 00

PERMITS

1.1 EXCAVATION PERMITS

a. All excavation permits will be issued to the Contractor from the Base Civil Engineer (BCE) through the Contracting Officer. The appropriate form for this request may be obtained from the Contracting Officer. Processing time required by the BCE is 21 calendar days. Questions concerning the excavation permit should be directed to the Contracting Officer.

b. Contractor shall obtain an Activity Permit from Pima County Department of Environmental Quality for any earth moving and/or trenching activities.

1.2 ASBESTOS DEMOLITION

Contractor shall obtain an Activity Permit from Pima County Department of Environmental Quality for demolition activities by submitting the Asbestos NESHAP Notification/Permit Activity Application For Renovation/Demolition Activities Form.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

PART 1 - GENERAL

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

01 10 12-1

SECTION 01 10 12

DESIGN AFTER AWARD

1. GENERAL. The requirements within this section of this Request for Proposals (RFP) establish the design efforts of the successful proposer, following Notice to Proceed. The design documents shall conform to:

(a) Section 00800 SPECIAL CONTRACT REQUIREMENTS.

(b) Section 01 10 10 DESIGN REQUIREMENTS.

(c) Unified Facilities Guide Specifications (UFGS).

(d) Appendix.

1.1 Compliance and Certification. The Contractor shall certify that all items submitted in the design documents (after contract award) comply with all the stated RFP requirements. This certification shall be included on the cover sheet of working drawings. The criteria specified in this RFP are binding contract criteria. In case of any conflict between the RFP criteria and Contractor's submittals, the RFP criteria will govern unless there is a written and signed agreement between the Contracting Officer and the Contractor waiving a specific requirement.

1.2 Order of Design Criteria Precedence. Section 01 10 10 DESIGN REQUIREMENTS is intended to identify specific project requirements. In cases of criteria conflict, Section 01 10 10 DESIGN REQUIREMENTS holds precedence over all other criteria mentioned or referenced. UFGS define minimum material quality requirements for material and installation.

2. SPECIFIC REQUIREMENTS

2.1 Field Verification. The Contractor shall verify field conditions which are required for final design. The information shall be reflected in the design documents.

2.2 Topographical Information. The Government has supplied all available topographic and existing utility information. Any additional topographic or utility information required for design after award of the contract shall be the responsibility of the Contractor.

2.3 Drawings. All design drawings submitted shall be (24 inch x 36 inch) size drawings. The graphic border is available on the Albuquerque District web page at:

http://www.spa.usace.army.mil/ec/cadd/index.htm (under ‘Requirements’).

Lettering shall be in all capitals, with a minimum height of 1/8” on full-size drawing, and all lettering fonts shall be Microstation “Font # 1” or AutoCad “Roman Simplex” with a width factor of one point zero (1.0). In addition to these requirements, all drawings shall be prepared per the CAD standards given in the A/E/C CADD Standards Release 2.0, available on the Internet at:

http://www.spa.usace.army.mil/ec/cadd/index.htm�

01 10 12-2 https://cadbim.usace.army.mil/CAD.

Drawings shall be in soft metric in accordance with the Appendix, Metric Design Guide.

2.4 Design Analysis. The Design Analysis shall be developed in accordance to the criteria specified within this RFP, Section 01 10 10 DESIGN REQUIREMENTS and Appendix, DESIGN ANALYSIS GUIDANCE. An electronic template of the Design Analysis is available to the Contractor. The Design Analysis shall include all features with the necessary calculations, tables, methods and sources used in determining equipment and material sizes and capacities, and shall provide sufficient information to support the design.

2.5 Specifications: Specifications shall be developed utilizing Unified Facilities Guide Specifications (UFGS) in conjunction with Section 01 10 10 DESIGN REQUIREMENTS and Appendix, SPECIFICATIONS GUIDANCE. All specifications shall be in sufficient detail to fully describe and demonstrate the quality of materials, the installation and performance of equipment, and the quality of workmanship. For specifications not available in UFGS, the Contractor shall create the specifications so that all of the submittal, quality control and testing requirements given in all of the UFGS are included. In addition, the quality control procedures used shall include the testing and quality control requirements given in the Quality Assurance/Quality Control found in Section 01 45 01 QUALITY CONTROL. The Contractor shall not alter specifications Section 00800 SPECIAL CONTRACT REQUIREMENTS or any Division 01 specifications during the design process.

These shall be submitted verbatim with the Final, Corrected Final, and Construction Set specifications.

2.5.1 SpecsIntact. All specifications shall be edited in SpecsIntact. The SpecsIntact software is a Government specification editing system and is available without charge at the following NASA website:

http://specsintact.ksc.nasa.gov/. SpecsIntact shall be utilized for all review submittals, both hard copy and electronic. Marked-up specifications shall be printed directly from SpecsIntact with tags off and notes and editing shown. Handwritten marked-ups of the specifications will not be accepted.

2.5.2 Unified Facility Guide Specifications (UFGS). The Contractor shall obtain the latest Unified Facilities Guide Specifications, except specifications specifically identified in Section 01 10 10 DESIGN REQUIREMENTS, from the NASA website: http://specsintact.ksc.nasa.gov/.

Structural specifications shall be downloaded from the Albuquerque District website. See Section 01 10 10 DESIGN REQUIREMENTS, STRUCTRUAL DESIGN for instructions.

2.6 Color Boards. Color/finish boards shall be in accordance with Section

01 34 10 COLOR/FINISH SAMPLE BOARDS.

2.7 Electronic Data Deliverables. Electronic files for Preliminary, Final, and Corrected Final review drawings shall be submitted in MicroStation™ V8.

Construction drawing electronic files shall be submitted in MicroStation™ V8 https://cadbim.usace.army.mil/CAD� http://specsintact.ksc.nasa.gov/� http://specsintact.ksc.nasa.gov/�

01 10 12-3 and AutoCAD™ Version 2008. Specifications shall be delivered in SpecsIntact.

Design Analysis shall be delivered in Microsoft MS Word 2003. Electronic data deliverables shall be on compact disk.

2.8 Certification of Computer Media: Certification of Computer Media shall be in accordance with the Appendix, DRAFTING STANDARDS.

2.9 RMS Requirements. The Contractor shall use the Government furnished Resident Management System (RMS) software module entitled Quality Control System (QCS) (see Section 01 45 02 QUALITY CONTROL SYSTEM (QCS)) to create the Submittal Register during the design phase of this contract. The data generated by the Contractor during the design phase will be used by the CQC manager in the construction phase of the project.

2.10 Building Information Modeling (BIM) Requirements. This project requires the use of BIM in compliance with the Air Force “Building Information Modeling Requirements”. This document includes a requirement to develop and provide an “Implementation Plan” prior to the initial design conference. It also outlines deliverables required at various stages during design and construction.

2.11 Fast Track Design For Construction. The Contractor is encouraged to utilize fast tracking in design for construction whenever possible. The Contractor will be allowed to begin construction on any portion of the design scheduled for fast tracking that has been completed and accepted as a Corrected Final submittal. Opportunities for fast track design shall be identified by the Contractor, incorporated into the construction schedule in accordance with Section 01 32 01 PROJECT SCHEDULE, and submitted for approval. Fast track design shall, as a minimum, be distributed for 100% and Corrected Final review.

3. DESIGN SUBMITTALS.

3.1 General. The first submittal shall include the Preliminary Design. The second design submittal shall include the Final Design. The third submittal shall be the Corrected Final Design. The fourth submittal shall be the Construction Set. Further submittal clarification can be found in Section

01 10 10 DESIGN REQUIREMENTS.

3.2 Contractor Design Review. Contractor shall ensure that all design documents including all drawings and calculations are reviewed by registered senior engineers/architects in the required discipline, who are independent from, and not associated with, the design. These individuals may be associated with the organization that did the original design. See CESPD-R 1110-1-8, Quality Management Plan. All drawings and design calculations in the Design Analysis shall be co-signed by the independent reviewers. The independent reviewer shall submit within the Design Analysis a signed letter of certification stating that the design documents for that discipline are complete, correct, and in conformance with the requirements of the RFP.

3.3 Reproduction. The Contractor shall be responsible for reproduction and distribution of design documents.

01 10 12-4

3.4 PRELIMINARY (60%) DESIGN SUBMITTAL REQUIREMENTS. This submittal shall include the 60 percent complete design and shall be appropriately stamped to describe the submittal package as follows: "For Review Only - 60% Design.

This submittal shall consist of a Design Analysis, Geotechnical Design Analysis, both full-size working drawings and half-size drawings, marked-up specifications, and any required environmental permits.

3.4.1 Drawings: All drawings included in the required technical data for the proposal submission shall be developed to a level of 60% completion.

Certain items shall be 100% completed, where indicated. Drawings required for the 60% Design submittal shall include as a minimum:

3.4.1.1 General.

a. Cover sheet and index of drawings.

b. Location and vicinity map including haul routes.

3.4.1.2 Building and Site Demolition Plan. 60% complete.

3.4.1.3 Civil.

a. Site plan/details.

b. Grading Plan. Contour lines shall be with intervals of not more than

1.0 foot, and spot elevations to 0.01 foot accuracy. Show new and existing storm drain lines and inlets.

c. Utility Plan. Show all utilities and associated products, i.e., cleanouts, manholes, fire hydrants, valve boxes, etc. Show existing water lines, point of connection, and relocations. Show existing sanitary sewer lines, new laterals and manholes. Show location of existing gas lines, points of connection, valves, and relocations.

d. Utility and storm drain profiles/details.

e. Rigid and flexible pavement plan and details.

f. Soils boring logs.

g. Rigid pavement joint layout plan.

h. Subsurface investigation site plan and boring logs.

i. Landscaping plan. Include limits of landscaping and seeded areas and area of trees to be removed, if required.

3.4.1.4 Architectural.

a. Floor plans with gross and net area analysis schedule.

b. Building elevations.

01 10 12-5

c. Roof plan.

d. Reflected ceiling plan.

e. Interior and exterior wall sections.

f. Room finish and color schedules.

g. Door and window schedules.

h. Life Safety plans.

i. Modular systems furniture layouts.

j. Modular systems furniture power, voice and data plans.

3.4.1.5 Structural.

a. CESPA Standard Structural Drawing Sheets. Reference the Structural Section of Section 01 10 10 DESIGN REQUIREMENTS, paragraph “Standard Drawings” of this RFP document for the requirements of these sheets.

b. Foundation Plan(s). Comply with the requirements of the Structural Section of Section 01 10 10 DESIGN REQUIREMENTS of this RFP document.

c. Second Floor Framing Plan(s). Comply with the requirements of the Structural Section of Section 01 10 10 DESIGN REQUIREMENTS of this RFP document.

d. Roof Framing Plan(s). Comply with the requirements of the Structural Section of Section 01 10 10 DESIGN REQUIREMENTS of this RFP document.

e. The foundation drawings (plans and details) only need to be to a 35% level at this 60% design stage.

f. The floor and/or roof framing drawings (plans and details) should be at a 60% or better design stage. All vertical load carrying framing members (joists, purlins, girders, beams, columns, etc) shall be specified and detailed to a 60% level. All lateral load carrying framing members (braces, moment frames, connections, etc) shall be specified and detailed to an 80% level. It is essential that the lateral load carrying members be well detailed at this level of design so there are no surprises to the architectural floor plans, building section, building elevations, etc., that could affect the architectural design at the “Final Design” stage.

3.4.1.6 Mechanical.

a. HVAC equipment schedules and mechanical legend.

b. HVAC equipment locations and unit designations.

c. Single-lined HVAC ductwork layout plan and major details. Scale – 1/8”=1’-0” (1:100).

01 10 12-6

d. Hydronic piping layout plans and major details. Scale – 1/8”=1’-0” (1:100).

e. Enlarged Mechanical room and yard plans with equipment clearances.

Scale – 1/4”=1’-0” (1:50).

f. Control diagrams and schematics and EMCS points schedule.

g. Plumbing plans, enlarged plumbing plan, plumbing equipment schedules, risers, and details. Scale – 1/8”=1’-0” (1:00) and 1/4”=1’-0” (1:50).

h. Fire suppression system performance plan which includes water supply line sizing, equipment and riser layout, room by room hazard classification and respective design density and floor area coverage requirements;

identification of all flow zones and control valve locations.

3.4.1.7 Electrical (Combined Exterior and Interior).

a. Site plans; including medium and low voltage feeders, metering, switchgear, sectionalizers, transformers, distribution switchboards, telephone and data routing, detail callouts, exterior lighting, etc.

b. Cathodic protection plan and details.

c. Electrical one-line diagrams and riser diagrams for all special systems. The electrical power one-line diagram shall be in the form given in the latest version of the ANSI/IEEE Std. 141.

d. Interior Power plan(s).

e. Interior Lighting plan(s).

f. Interior Special systems plan(s); including communication, LAN Cabling, security and audio-visual systems, lightning protection and fire alarm systems.

g. Details; including equipment foundations, trenches, switchboard supports, equipment details for service, power equipment, lighting fixtures, special systems, and grounding.

h. Schedules; including transformers, secondary switchboards, light fixtures and panels.

i. Drawings for the LAN System. The drawings shall include a LAN System Cabling Plan for the complete system and layouts of each patch panel and concentrator rack. Included in each rack layout drawing shall be details of equipment supplied, features, and connection indications.

3.4.1.8 Electronic Drawing Files. Provide random samples of the drawing files for review by the Government to ensure mandatory compliance with the Tri-Service A/E/C CADD Standards. As minimum, provide two drawing files from

01 10 12-7 each discipline. Additionally, each design submittal shall be provided in a read-only electronic format, on CD-ROM, that will allow review by any organization, regardless of that organization's existing software capabilities. The Contractor shall be responsible for insuring that drawings, specifications, design analyses, and calculations are accessible with the appropriate software.

3.4.2 Specifications. Marked-up specifications for the entire project shall be provided in accordance with the Appendix. For the structural specifications only, use CESPA standard specification sections; reference paragraph titled “Guide Specifications” in paragraph, STRUCTURAL DESIGN, of Section 01 10 10 DESIGN REQUIREMENTS of this RFP document.

3.4.3 Design Analysis. The Design Analysis shall be in accordance with the Appendix, and shall include design calculations developed to the extent required to support the design included in this submittal unless additional requirements are called out in the following sub-paragraphs.

3.4.3.1 Civil. 60% complete, all items.

a. Storm run-off calculations, drainage areas and patterns.

b. Storm drain line calculations.

c. Curb inlet and surface drainage.

d. Detention pond calculations (if applicable).

e. Water (including irrigation) and fire demand lines calculations.

f. Gas line calculations.

g. Sanitary sewer line (average and peak flows, flow velocity).

h. Description of how the floor elevation was set.

3.4.3.2 Architectural.

a. Describe proposed facility, capacity, and type of construction.

b. List building gross, programmed, and proposed net areas for all areas.

c. Roof and wall thermal transmission “U-value” calculations.

d. Wall and ceiling acoustical ratings, where required by Section

01 10 10 DESIGN REQUIREMENTS.

e. Calculations and detailed references to support the Life Safety Plan.

f. All LEEDTM calculations, submittals and worksheets.

01 10 12-8

3.4.3.3 Structural Narrative.

a. Describe the foundation system.

b. Describe the framing system selected and the reasons for the final selection. Vertical and lateral load resisting systems shall be clearly described.

c. State the live loads used for the design.

d. State the various coefficients used in computing the seismic forces, and describe the structural system to be used to resist these forces. Also describe any special seismic design features.

e. State the basic wind speed, exposure category and importance factor.

Cite specific codes or standards used as the basis for calculating wind pressures.

f. The lateral design shall be completed to a 95% design level at this 60% design stage. This requirement is so there are no surprises in the lateral stability of the building at the “Final Design” submittal stage that would change the “Final Design” stage of the architectural design.

3.4.3.4 Mechanical HVAC Calculations (90 percent completed). The following Mechanical calculations shall be provided as part of the 60% design submittal. Designer shall also indicate all assumptions made in performing the calculations that are not specified in this document or in Section

01 10 10 DESIGN REQUIREMENTS.

a. EPACT 05, Energy Load Simulation for a typical year of the facility.

The result of this simulation shall be in…