Text version
COMMITTENZA / COMMITTEE
COMANDO USAG ITALY
DARBY MILITARY COMMUNITY
VIA VECCHIA LIVORNESE
56121 TIRRENIA (PI)
STRUTTURA ORGANIZZATIVA NELLA QUALE SARA’ SVOLTA L’ATTIVITA’ / ORGANIZATIONAL STRUCTURE WHERE ACTIVITY WILL TAKE PLACE
DATORE DI LAVORO / EMPLOYER
DPW-ENVIRONMENTAL OFFICE
VIA AURELIA SS1
ZONA DEPOSITO
56121 TIRRENIA PISA
COMANDANTE / COMMANDER: COL DANIEL J. VOGEL
DMC MANAGER: Mr. Robert K. Larimore
RSPP Ufficio SPP / Safety Officer _Ing. Chiara Chelossi_ UFFICIO / OFFICE DIRECTORATE OF PUBLIC WORKS Medico Competente / Occupational Health Doctor _Dr. Raffaele Peluso_
Manager del PWO/ PWO Manager
Stephen L. Donnelly_
RLS / Workers’ Safety Representative
_ Manrico Bendinelli_ _Massimo Ferrari___ _Luca Vannucchi___ _Riccardo Kolman__
Responsabile di area / Area Supervisor
Committente / Commissioning Employer
Comando USAG Italy Addetti al pronto soccorso / First Aid qualified Employees
DES – Fire Section
Addetti all’antincendio / Building Fire Wardens
DITTA APPALTATRICE / CONTRACTOR
INDIRIZZO / ADDRESS
DATORE DI LAVORO / EMPLOYER: ___________________
Responsabile di cantiere / Contractor’s on-site Representative
Medico competente / OH Doctor
RSPP / Safety Officer _______________ Addetti al pronto soccorso (cantiere) / First Aid qualified Employees (Contractor)
Addetti all’antincendio (cantiere) / Fire Wardens (Contractor)
RLS / Employees’ Safety representative
DPW SITE MANAGER
VERIFICATO/REVIEWED
Safety Office
VERIFICATO/REVIEWED
Stephen L. Donnelly Date:_________
Signature_______________
Ing. Chiara Chelossi Date: _27 Aug 2019__
Signature________________
DUVRI
DOCUMENTO DI VALUTAZIONE DEI RISCHI DI INTERFERENZA
ART. 26 COMMA 3, D.LGS. 81/08
SINGLE DOCUMENT FOR THE ASSESSMENT OF INTERFERENTIAL RISKS
Article 26, paragraph 3, Legislative Decree 81/08
DESCRIZIONE ATTIVITÀ / DESCRIPTION OF ACTIVITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti presso USAG Italy DMC (Stimata n. 1 giornata di lavoro/mese e n.1 uomo/giorno)
Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials, USAG Italy DMC (Estimated 1 working day/month and 1 worker/day)
DARBY MILITARY COMMUNITY
VIA AURELIA
DOCUMENTO UNICO DI VALUTAZIONE DEI RISCHI Art. 26 comma 3, D. Lgs 81/08
Oggetto del contratto
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy
Numero di contratto
Appaltatore
Anagrafica dell'Appaltatore
Ragione sociale
Legale rappresentante
Sede legale
Sede operativa
Telefono/Fax e-Mail
Codice fiscale
Partita iva
Iscrizione alla C.C.I.A.A
Posizione assicurativa INAIL
Posizione INPS
C.C.N.L. applicato
Responsabile del Servizio di Prevenzione e Protezione (RSPP)
Rappresentante dei Lavoratori per la Sicurezza (RLS)
Medico Competente
Responsabile Prevenzione Incendi
Responsabile Pronto Soccorso
Referente della ditta appaltatrice per il coordinamento e la sicurezza
Periodo di lavoro PERIODO: gg/mm/aa – gg/mm/aa
ORARIO: dalle 8.00 alle 17.00 dal Lunedi al Venerdi
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy
RISCHI AMBIENTALI PRESENTI ALL’INTERNO DEGLI EDIFICI OGGETTO DELL’INTERVENTO / POTENTIAL RISKS PRESENT INSIDE THE
BUILDINGS OBJECT OF THIS WORK CONTRACT
Edifici Bldgs
N. Addetti –Descrizione Generale / No. Employees On site/description
Attrezzature – Macchinari / Machinery - equipment
Rischi presenti / Risks
USAG ITALY
DMC
Affollamento tot: Popolazione di 1005 persone tra civili e militari –Manutenzione e riparazione del raccordo ferroviario, DMC- USAG Italia./Civilian and military popolation of 1005 persons – Maintenance and repair railroad, DMC-USAG Italy Employees per bldg/area:
nr.2/30
Macchinari ed attrezzature:
muletto,camion , macchine meccaniche su rotaia, trapano, cacciaviti, chiavi, mola, saldatrice, generatore elettrico/ Machines and equipment: fork lift, truck, rail mechanical machines, drill, screwdrivers, wrenches, grinder, welding machine, power generator.
Rischio di caduta nei canali,fosse di drenaggio o scavi.
Utilizzo di utensili e macchinari rumorosi.
Presenza di contenitori di liquidi facilmente combustibili.
Rischio di proiezione di schegge/materiali.
Movimentazione di materiali tramite carrelli elevatori.
Spostamento di veicoli e mezzi tattici.
Movimentazione di materiale esplosivo.
Movimentazione di veicoli su rotaia.
Rischio presenza di pozzetti per connessioni terre / Rischio di caduta materiali dall’alto.
Attenzione ai carichi sospesi.
Presenza di personale armato e cani addestrati per il pattugliamento.
Non fumare in prossimità (15 metri) delle entrate principali di ogni edificio.
Risk of falling into drainage canals, ditches or excavations.
Noisy equipments and mowers.
Combustible liquid present.
Risk of flying particles by using machines MHE movement on site.
Tactical vehicle traffic.
Explosive material movement.
Rail vehicle movement Risk of ground connection pits presence Risk of falling of material.
Warning to hung weight.
Presence of armed forces and trained dogs for patrolling.
No smoking within 50 feet.
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy
ALTRI RISCHI PRESENTI nelle Aree/ OTHER GENERAL HAZARDS PRESENT IN THE AREAS
1. Traffico veicolare; automezzi privati, muletti, (talvolta questi ultimi sprovvisti di segnalatori acustici e/o ottici), bus navetta, veicoli militari, cisterne rifornimento serbatoi di olio combustibile o GPL esterni agli edifici, veicoli per la raccolta dei rifiuti. / Vehicular Traffic: POVs, forklifts, (sometimes with no regular yellow/orange blinking light and backward maneuvering beeper), shuttle bus, military vehicles, refueling tanks for combustible oil or LPG, trash collection dumpers.
Rischi: collisione – schiacciamento – interferenza con operazioni di rifornimento/raccolta rifiuti. / Risks: collision – crushing – interference with refueling/trash collection operations.
2. Presenza di veicoli per emergenze dei Vigili del Fuoco in prossimita’ della Stazione dei Pompieri / Presence of Fire Department emergency response vehicles near the Fire Department
Rischi: investimento - interferenza con operazioni di intervento/salvataggio / Risks: crash - interference with response/rescue operations
3. Traffico pedonale / pedestrian traffic Rischi: investimento. / Risks: hitting a pedestrian.
4. Segnaletica si sicurezza non sempre conforme alle vigenti norme di sicurezza e non sempre bilingue. / Road signs / marking not always IAW traffic code and not always bilingual.
Rischi: fraintendimento dei segnali. / Risks: misinterpretation of road signs / marking.
5. Presenza di personale di lingua non Italiana. / Presence of non-Italian speaking personnel.
Rischi: fraintendimento nelle comunicazioni verbali. / Risks: verbal communication misinterpretation.
6. Possibile interazione con personale della sicurezza militare all’interno dell’area/edificio per esigenze di carattere operativo. / Potential interaction with security personnel in the area/facility due to operational contingencies.
Rischi: interferenza con operazioni di pubblica sicurezza -fraintendimento nelle comunicazioni verbali. / Risks: interference with security forces operations - verbal communication misinterpretation.
7. Possibile presenza di derivati dell’amianto in vecchie condutture, rivestimenti, guarnizioni;
(riferimento documento valutazione presenza amianto disponibile presso Environmental Office, edificio 5155) / Potential presence of asbestos containing materials on old pipelines, coverings, gaskets; (refer to specific evaluation document available at Environmental Office, Bldg. 5155)
Rischi: esposizione accidentale all’amianto / Risks: asbestos accidental exposure
8. Presenza deposito materiali tossici (pesticidi) all’edificio 5013. Possibile presenza di veicoli in ingresso o uscita dall’area / Presence of toxic materials, (pesticides), at Bldg.5013. Possible presence of transports accessing or exiting the area
Rischi: esposizione accidentale / Risks: accidental exposure
8. Incrocio a 4 vie (STOP sui quattro lati – non conforme). / 4-Way stop crossroad (not European traffic code compliant).
Rischi: fraintendimento della precedenza – collisione. / Risks: yield misinterpretation - collision.
9. Gli edifici circondati da prato possono ospitare nelle adiacenze nidi di insetti, (vespe ad esempio), o altri animali / Green area surrounding facilities may hide insects or other animals’ nests
Rischi: biologico / Risks: biological
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy
10. Presenza di alberi intorno i parcheggi e/o lungo le vie di passaggio / Trees surrounding parking areas and/or along cross ways
Rischi: esposizione alle pine che cadono dagli alberi / Risks:
exposure to pine cones falling
11. Incrocio a 4 vie (STOP sui quattro lati – non conforme) / 4-Way stop crossroad (not European traffic code compliant)
Rischi: fraintendimento della precedenza – collisione / Risks: yield misinterpretation - collision
12. Apertura di nuovi cantieri che puo’ comportare / New construction sites activation may imply the following:
a. Modifiche alla viabilita’ dell’area / Traffic flow changes
b. Scavi temporanei / Temporary open diggings
c. Incremento traffico veicoli pesanti / Increased number of heavy vehicles
d. Installazione opere provvisionali / Temporary work provisions on the installation
e. Rumore/vibrazioni / Noise/vibrations
Rischi: collisione – schiacciamento - interferenza con operazioni di cantiere / Risks: collision – crushing - interference with construction site operations Rischi: caduta / Risks: fall
Rischi: collisione – schiacciamento - interferenza con operazioni di cantiere / Risks: collision – crushing - interference with construction site operations Rischi: inciampo - interferenza con operazioni di cantiere / Risks:
trip & fall - interference with construction site operations
Rischi: esposizione / Risks: exposure
13. Armadi chiusi riportanti l’indicazione “Materiale Infiammabile – Flammable materials” / Closed cabinets/storage room with “Materiale Infiammabile – Flammable materials” signs
Rischi: incendi - esposizione accidentale / Risks: fire – accidental exposure
14. Presenza di depositi di materiali pericolosi segnalati con la scritta “HAZARDOUS WASTE” / Presence of dangerous materials with HAZARDOUS WASTE signs
Rischi: esposizione accidentale / Risks: accidental exposure
15. Presenza di cassoni porta rifiuti e relative operazioni periodiche di svuotamento con mezzi pesanti / Presence of trash collectors on related removal operations performed with dumpers
Rischi: collisione – schiacciamento – interferenza con operazioni di rimozione rifiuti / Risks: collision – crushing – interference with trash collection
16. Segnaletica stradale orizzontale non sempre chiaramente leggibile / Marking on the roads signs not always readable
Rischi: collisione / Risks: collision
ATTIVITA’ SVOLTA DALL’APPALTATORE E FASI LAVORATIVE / CONTRACTOR WORK ACTIVITIES
Campionamenti eseguiti da tecnici di laboratorio di acqua potabile, acque di scarico, rifiuti e materiali sconosciuti (Stimata n. 1 giornata di lavoro/mese e n.1 uomo/giorno)
Sampling made by laboratory technicians of potable water, waste water and unknown waste and materials, (Estimated 1 working day/month and 1 worker/day))
Fasi lavorative previste / Scheduled Work Phases:
a) Arrivo della ditta all’ingresso della Base presso il quale si rechera’ il COR o un suo rappresentante, che accompagnera’ la ditta nelle zone previste dal Contratto, se la ditta e’ gia’ in possesso dell’autorizzazione e dei relativi pass si rechera’ autonomamente presso tali zone. Per recarsi presso le aree dovra’ essere seguita la strada piu’ breve procedendo ad una velocita’ non superiore ai 40Km/h e rispettando tutte le regole del codice della strada incluso
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy l’obbligo di indossare le cinture di sicurezza / Arrival of Contractor at Base where they will be met by the COR or his/her representative, who will accompany them to the Contracted zones, if the Contractor already has in its possession an authorization and relative passes it can proceed to these zones on its own. In order to reach these areas the Contractor must take the shortest route and travel at a speed not to exceed 40km/h and observe all traffic regulations including compulsory wearing of seat belts.
b) Al fine di evitare le interferenze le attivita’ saranno svolte adottando le seguenti precauzioni / In order to avoid interference work will be accomplished adopting the following precautions:
- La ditta incaricata dovra’ provvedere a delimitare con relativa segnaletica in caso di campionamenti di terreno o in copertura / The Contractor commissioned to perform the sampling of soil or on the roof, will be responsible for delimitation, by specific warning signs, of the work area;
- Il responsabile di area dovra’ evitare l’esecuzione di attivita’ particolari che possano determinare rischi all’interno di ogna zona di lavoro / The person responsible for the area will prevent any particular activity that can put at risk anyone present in each work area;
- Sara’ vietato transitare all’interno dell’area delimitata durante i lavori contrattuali / Shall be forbidden to walk during the contract operations
- Considerando i possibili rischi dovuti a caduta di pine e rami, collisione, schiacciamento e proiezione di schegge sara’ opportuno indossare scarponi antinfortunistici con puntale rinforzato , guanti antitaglio, elmetto protettivo e visiera / Considering the possible risks present in the work area associated with falling of pine cones and tree branches, collusion, crushing, and risk of flying particles by using machines it will be necessary to swear capped safety shoes, safety gloves, elmet and protective safety shield.
- All’interno della zona delimitata la ditta potra’ eseguire il lavoro di campionamento previsto in autonomia utilizzando le proprie attrezzature / On the inside of the delimited area the Contractor can perform the sampling work as scheduled in autonomy and with the use of its own tools;
- Il responsabile del campionamento dovra’ evitare l’esecuzione di attivita’ che possano comportare rischi per le aree di lavoro al di fuori dell’area delimitata di propria competenza The Responsible of the sampling must avoid performing any activity which may be of risk for the work areas outside of the delimited area for which he/she is responsible.
c) Terminato l’intervento di campionamento, il Responsabile del campionamento provvedera’ a rimuovere le segnaletica usata per la delimitazione della zona / Once the sampling has been completed the Responsible of the sampling proceed to remove the signs to delimit the work area.
d) Terminati il campionamento, la ditta’ dovra’ provvedere a mettere in sicurezza le proprie attrezzature, a rimuovere tutti i residui delle lavorazioni eseguite, provvedendo eventualmente a smaltirli direttamente o a posizionarli all’interno degli appositi contenitori / Once the sampling is completed, the Contractor is responsible for assuring that all his equipment is safely stowed out of harm way, he must remove all residue/rubbish created by his work, disposing of it himself or empting into the appropriate refuse containers.
ATTREZZATURE UTILIZZATE DALL’APPALTATORE / CONTRACTOR SPECIAL TOOLS
Scale, attrezzature varie / ladders, various tools Ogni altra attrezzatura idonea ad effettuare i cmpionamenti inerenti il servizio. / Any other equipment or tools adequate to perform the samplings under the service.
L’utilizzo delle attrezzature da parte dell’appaltatore non comporta rischi al di fuori dell’area perimetrata. Non sono previste ulteriori misure di prevenzione e protezione oltre alla perimetrazione delle aree. / Use of equipment by the Contractor do not pose any risks outside of the cordoned area. No other preventive or protective measures apart from cordoning off the work area are prospected.
RISCHI DI INTERFERENZA DELL’ATTIVITÀ OGGETTO DELL’APPALTO, SVOLTA ALL’INTERNO DELLE AREE DI LAVORO, DERIVANTI DA
UTENSILI/ATTREZZATURE/SOSTANZE/MEZZI UTILIZZATI / SUMMARY OF RISKS DUE TO USE OF TOOLS / EQUIPMENT / CHEMICALS /
VEHICLES
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy
N. DESCRIZIONE / HAZARD DESCRIPTION RISCHIO / RISK
MISURE DI PREVENZIONE-PROTEZIONE /
PREVENTIVE-PROTECTIVE MEASURES
MOVIMENTAZIONE MANUALE DEI CARICHI /
MANUAL HANDLING OF HEAVY LOADS
Assenti / Not applicable La movimentazione manuale dei carichi non comporta interferenza
Non necessarie / Not applicable
AGENTI FISICI: Rischi utilizzo utensili/attrezzature RUMOROSI PHYSICAL AGENTS: use of tools / equipment’s producing high noise
Assenti / Not applicable Assenti / Not applicable
AGENTI FISICI: Rischi utilizzo utensili/attrezzature VIBRANTI PHYSICAL AGENTS: use of vibrating tools / equipment
Assenti / Not applicable Assenti / Not applicable
AGENTI FISICI: Rischio di utilizzo attrezzature che emettono CAMPI ELETTROMAGNETICI
PERICOLOSI
PHYSICAL AGENTS: use of tools / equipment emitting dangerous electromagnetic fields
Assenti / Not applicable Non necessarie / Not applicable
AGENTI FISICI: Rischio di utilizzo attrezzature che emettono RADIAZIONI OTTICHE
PERICOLOSE
PHYSICAL AGENTS: use of tools / equipment emitting dangerous radiation / optic fields
Assenti / Not applicable Non necessarie / Not applicable
SOSTANZE PERICOLOSE: Rischi utilizzo sostanze/preparati chimici pericolosi CHEMICALS: use of hazardous chemicals
Assenti / Not applicable Non necessarie / Not applicable
SOSTANZE PERICOLOSE: Rischi utilizzo sostanze/preparati chimici cancerogeni/mutageni CHEMICALS: use of cancerous / mutagen chemicals
Assenti / Not applicable Non necessarie / Not applicable
AMIANTO: Rischi utilizzo sostanze contenenti amianto ASBESTOS: use of asbestos containing material
Presente / Present Indossare appropriati dispositivi di sicurezza/wear appropriated safety protection
AGENTI BIOLOGICI: Rischi di utilizzo agenti biologici pericolosi BIOLOGICAL AGENTS: use of hazardous biological agents
Assenti / Not applicable Non necessarie / Not applicable
ATMOSFERE ESPLOSIVE: Rischi di sviluppo di atmosfere esplosive durante svolgimento attività EXPLOSIVE ATMOSPHERES: Development of explosive atmospheres during operations
Assenti / Not applicable Non necessarie / Not applicable
ATMOSFERE ESPLOSIVE: Rischio utilizzo di utensili, attrezzature, mezzi che possono innescare atmosfere esplosive EXPLOSIVE ATMOSPHERES: use of tools, equipment, vehicles that could ignite explosive atmospheres
Assenti / Not applicable Non necessarie / Not applicable
Rischi utilizzo sostanze infiammabili/facilmente combustibili Use of flammables / combustibles
Presente / Present Non necessarie / Not applicable
Rischi caduta materiale dall’alto Risk of falling objects
Non necessarie / Not applicable
Rischi utilizzo corrente elettrica Electrical equipments
Rischio utilizzo utensili/attrezzature che comportano la proiezione di schegge Use of tools / equipment that expose to flying particles
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy
N. DESCRIZIONE / HAZARD DESCRIPTION RISCHIO / RISK
MISURE DI PREVENZIONE-PROTEZIONE /
PREVENTIVE-PROTECTIVE MEASURES
MOVIMENTAZIONE MANUALE DEI CARICHI /
MANUAL HANDLING OF HEAVY LOADS
La movimentazione manuale dei carichi non comporta interferenza
Non necessarie / Not applicable
Rischio utilizzo/presenza di utensili/attrezzature che hanno parti mobili pericolose (urti, schiacciamenti, tagli, ecc.)
Use of tools/equipment with exposed moving parts
Rischio spostamento con automezzi Moving traffic
Presente / Present
Gli spostamenti all’interno della base devono essere preventivamente autorizzati dalla committente. Devono essere seguite scrupolosamente le regole di circolazione interna. In assenza di indicazioni particolari, procedere a passo d’uomo (5Km/ora). Vietato parcheggiare davanti a mezzi di salvataggio, soccorso, antincendio / All internal traffic needs to be previously authorized by the Commissioning Employer. All rules governing traffic will be observed. In the absense of signs, procede at walking pace (5 Km/h). Parking in front of emergency vehicles is prohibited
MISURE DI PREVENZIONE-PROTEZIONE AGGIUNTIVE / OTHER PREVENTIVE-PROTECTIVE MEASURES
1. Prima di accedere alle aree interessate dall’intervento, concordare con il COR dell’appalto le modalità di effettuazione delle attività e formalizzare le misure di prevenzione e protezione concordate / Before entering the premises subject to the contract work, coordination with Contract COR must be done in order to establish the procedures of performance activities and the agreed on preventive and protective measures
2. Esporre la tessera di riconoscimento corredata di fotografia contenente le generalità del lavoratore e l'indicazione del datore di lavoro per tutto il tempo di permanenza nell’azienda (ai sensi dell’art.26 c.8 del D.Lgs.81/08) / Wear a badge equipped with photograph, name and address of contractor during the entire permanence inside the premises (IAW art. 26 para 8 of Law 81/08)
3. In caso di evacuazione attenersi alle procedure vigenti / In case of evacuation of bldg follow emergency evacuation plan
4. Indossare i dispositivi di Protezione Individuale ove siano prescritti / Wear personal Protective Equipment as prescribed
5. Non ingombrare le vie di fuga con materiali e attrezzature / Do not block emergency exits with material and equipment
6. Non occultare i presidi e la segnaletica di sicurezza con materiali e attrezzature / Do not conceal first aid kits and warning signs with material and equipment
7. Non operare su macchine, impianti e attrezzature se non autorizzati / Do not operate machinery, equipment and tools if not authorized
8. Evitare l’uso di cuffie o auricolari per l’ascolto della musica durante l’attività perché potrebbero impedire la corretta percezione dei segnali acustici di allarme in caso di emergenza (allarme incendio, allarme evacuazione, cicalini dei mezzi
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy e delle macchine, ecc.) / Refrain from using headphones or earphones while working because they could prevent hearing emergency alarms (i.e. fire alarm, evacuation alarm, equipment and machinery buzzers, etc.)
9. Le attivita’ di campionamento di terreni o in copertura dovranno essere svolte perimetrando e isolando preventivamente la zona oggetto dell’intervento di manutenzione/riparazione copertura / The sampling activities of soil or on the roof will be performed after having previously cordoned off the area object of the roofs maintenance/repair intervention;
10. Il responsabile di area dovra’ evitare l’esecuzione di attivita’ particolari che possano determinare rischi all’interno della zona di lavoro delimitata / The person responsible for the area will prevent any particular activity that can put at risk anyone present in the delimited work area;
11. Il responsabile della ditta incaricata dovra’ evitare l’esecuzione di attivita’ che possano comportare rischi per le aree di lavoro al di fuori dell’area delimitata di propria competenza / The Contractor responsible must avoid performing any activity which may be of risk for the work areas outside of the delimited area for which he/she is responsible.
MISURE DI PREVENZIONE E PROTEZIONE ADOTTATE
Per rischi interferenti, in generale, si intendono:
rischi derivanti da sovrapposizioni di più attività svolte ad opera di appaltatori diversi;
rischi immessi nel luogo di lavoro del committente dalle lavorazioni dell’appaltatore;
rischi esistenti nel luogo di lavoro del committente, ove è previsto che debba operare l’appaltatore, ulteriori rispetto a quelli specifici dell’attività propria dell’appaltatore;
rischi derivanti da modalità di esecuzione particolari (che comportano rischi ulteriori rispetto a quelli specifici dell’attività appaltata), richieste esplicitamente dal committente.
Nelle misure di prevenzione e protezione adottate non sono riportate le misure per eliminare i rischi derivanti dall’attività delle singole imprese appaltatrici o dei singoli lavoratori autonomi, ma solo i rischi derivanti dalle interferenze presenti nell’effettuazione della prestazione.
L’impresa aggiudicataria, all’atto della comunicazione del rischi specifici connessi alla propria attività, può presentare proposte di integrazione, ove ritenga di poter meglio garantire la sicurezza del lavoro, sulla base della propria esperienza.
COSTI DELLA SICUREZZA
Sono quantificabili come costi della sicurezza tutte quelle misure preventive e protettive necessarie per l’eliminazione o la riduzione dei rischi interferenti individuate, così come indicativamente riportato di seguito:
gli apprestamenti previsti nel DUVRI (come ponteggi, trabattelli, etc.);
le misure preventive e protettive e dei dispositivi di protezione individuale eventualmente previsti nel DUVRI per lavorazioni interferenti;
gli eventuali impianti di terra e di protezione contro le scariche atmosferiche, degli impianti antincendio, degli impianti di evacuazione fumi previsti nel DUVRI;
i mezzi e servizi di protezione collettiva previsti nel DUVRI (come segnaletica di sicurezza, avvisatori acustici, etc.);
le procedure contenute nel DUVRI e previste per specifici motivi di sicurezza;
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy gli eventuali interventi finalizzati alla sicurezza e richiesti per lo sfasamento spaziale o temporale delle lavorazioni interferenti previsti nel DUVRI;
le misure di coordinamento previste nel DUVRI relative all'uso comune di apprestamenti, attrezzature, infrastrutture, mezzi e servizi di protezione collettiva.
La stima, analitica per voci singole, a corpo o a misura (quindi NON A PERCENTUALE), viene riferita ad elenchi prezzi standard o specializzati, oppure basata su prezziari o listini ufficiali vigenti nell'area interessata, o sull'elenco prezzi delle misure di sicurezza del committente; nel caso in cui un elenco prezzi non sia applicabile o non disponibile, si farà riferimento ad analisi costi complete e desunte da indagini di mercato.
GESTIONE DELLE EMERGENZE / EMERGENCY MANAGEMENT
In caso di emergenza e/o infortunio dovranno essere adottate le procedure specificate nel “Piano di pronto intervento per l’evacuazione delle persone infortunate per la comunita’ USAG Vicenza DMC di Livorno” allegato al contratto di appalto. / In case of emergency and/or injury, follow the procedures contained in the Emergency plan for the evacuation of injured people for USAG Vicenza DMC areas.
TIPO EMERGENZA
EMERGENCY TYPE
DESCRIZIONE
DESCRIPTION
RIFERIMENTI
REFERENCES
Sicurezza Security
La gestione della sicurezza è assicurata dal servizio interno di polizia militare.
Security services are the responsibility of the internal military police.
Servizi Interni/ Internal Services
MILITARY POLICE DSN 633-7575
Commercial 050-54-7575
CARABINIERI DSN633-8701/8711
Commercial 050-54-8701/8711 Servizi esterni / External Services
CARABINIERI tel. 112
Incendio- Esplosione
Fire-Explosion
La gestione delle emergenze legate agli incendi/esplosioni è affidato agli addetti alla lotta antincendio designati dall’appaltatore ai quali saranno affiancati gli addetti alla lotta antincendio presenti nei repati e al dipartimento interno per la lotta antincendio.
Fire/explosion emergency management is the responsibility of the contractor’s qualified fire wardens, supported by the building fire wardens present in the area
Servizi Interni/ Internal Services Addetti di reparto / BFW:
FIRE DEPARTEMENT DSN 117
Commercial 050-54-7117
Servizi esterni / External Services Vigili del Fuoco tel. 115
Infortunio – malore Accident – Illness
La gestione delle emergenze legate ad infortunio/malore è affidato agli addetti designati dall’appaltatore ai quali potranno essere affiancati gli addetti presenti nei repati.
Medical emergency management is the responsibility of the contractor’s first aid qualified employees, supported by the area firs aid qualified employees
Servizi Interni/ Internal Services Addetti al primo soccorso / First-Aiders Servizi esterni / External Services
Pronto Soccorto (esterno) First Aid (external)
Tel. Fisso/From fixed telephone: 118Tel Cellulare /From Cell Phone: 800011800
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy
Others general dispositions to eliminate interference / Disposizioni generali aggiuntive per l’eliminazione delle interferenze.
Utilizzare solo le area autorizzate Non accedere in altri locali o edifici
Non presentarsi sul luogo di lavoro sotto l’influenza di alcool, medicinali o sostanze psicotrope
Non manomettere e/o escludere protezioni, dispositivi di sicurezza o sistemi di segnalazione e controllo.
Non oltrepassare o disattivare le protezioni.
Non usare fiamme libere in azienda se non ESPRESSAMENTE AUTORIZZATI (tramite form MD 00 0277 “Richiesta permesso di lavoro”)
È vietato fumare in locali chiusi e all’esterno a 15 metri dalle porte.
È vietato introdurre bevande alcoliche all’interno dell’azienda
È vietato arrampicarsi su scaffali, ripiani, macchinari e comunque su qualsiasi altra postazione sopraelevata; obbligatorio l’impiego di scale e/o trabattelli conformi alla normativa vigente, di proprietà.
È vietato toccare gli apparati elettrici alle persone non autorizzate e qualificate.
È obbligatorio:
farsi riconoscere all’ingresso presso il gate;
ricevere autorizzazione per l’ingresso di auto – furgoni – mezzi ed esporre il pass sul mezzo;
camminare percorrendo solo le aree pedonali segnalate;
rispettare la segnaletica orizzontale e verticale (percorsi pedonali e carrabili, aree di stoccaggio merci, vie di evacuazione, cartelli di divieto, d’obbligo, di segnalazione e di avvertimento, altro);
astenersi dall’utilizzare, manutenere, verificare, oliare, registrare, ingrassare, macchine e/o impianti di Ns. proprietà;
utilizzare esclusivamente Vs. macchine o attrezzature, previa Ns. autorizzazione scritta, conformi ai requisiti antinfortunistici;
rispettare le procedure di sicurezza aziendali;
mantenere ordinate e pulite le zone di passaggio, deposito e lavoro riprestinando le condizioni presenti prima dell’esecuzione degli interventi;
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy provvedere in proprio al trasporto e smaltimento dei rifiuti decadenti dallo svolgimento del/i Vs. incarico/i, salvo Ns.
diversa disposizione da comunicarvi per iscritto;
segnalare a Ns. addetto qualsiasi situazione ritenuta a rischio, oltre che di altre condizioni di pericolo di cui si è a conoscenza;
prendersi cura della propria sicurezza e della propria salute e di quella delle altre persone presenti, conformemente alla propria formazione ed alle istruzioni e ai mezzi forniti dal datore di lavoro.;
l’utilizzo degli idonei DPI forniti.
Rispettare tutte le procedure di sicurezza indicate dall’Ufficio Sicurezza della Committente.
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy
RISCHI INTRODOTTI DALL’APPALTATORE (DA COMPILARE UNA VOLTA SELEZIONATO L’APALTATORE):
N. DESCRIZIONE / HAZARD DESCRIPTION MISURE DI PREVENZIONE-PROTEZIONE ADOTTATE / PREVENTIVE-PROTECTIVE MEASURES
Carico e smaltimento materiali contenenti amianto / Loading and disposal of materials containing asbestos
Vedere documento “Modalita d;esecuzione rimozione amianto” preparato dall”impresa Ecoflash / See the document “Execution procedure for asbestos removal” prepared by the
Firm Ecoflash
DARBY MILITARY COMMUNITY
Campionamenti ed analisi di laboratorio, Acqua potabile, acque di scarico e rifiuti e materiali scnosciuti Laboratory Sampling and Analysis, Potable Water, Waste Water and Unknown Waste and Materials
Edifici interessati USAG ITALY, DMC – Vari edificie e aree
Datore di lavoro richiedente COMANDO USAG Italy
CONSIDERAZIONI CONCLUSIVE / CONCLUSIONS:
Il Committente dichiara di aver fornito all’Appaltatore / The Commissioning Employer provided the Contractor with:
le informazioni tecniche relative allo stato dei luoghi sede dell’attività e dettagliate informazioni sui rischi specifici esistenti nell’ambiente dove dovrà operare e sulle misure di sicurezza e emergenza adottate; / all the technical info regarding the status of the work places and detailed information on the specific risks in the locations where the Contractor is going to work and the safety and emergency measures adopted;
le informazioni per evitare inutili rischi e per lavorare in sicurezza in relazione alla contemporanea presenza sul luogo di lavoro o nelle immediate vicinanze di altre imprese appaltatrici e sui rischi specifici relativi. / all the information to avoid unnecessary risks and to work in safety, in relation to the contemporary presence on the work-place, or in the immediate vicinities, of other contractors and relative specific risks.
Con la firma riportata in calce la ditta appaltatrice attesta / With the following signature the contractor states:
di aver preso atto delle dettagliate informazioni ricevute sui rischi specifici esistenti nell’ambiente in cui è chiamata ad operare e sulle misure di prevenzione e di emergenza adottate in relazione all’attività del committente; / understood the detailed information received regarding the specific risks in the workplace where is going to perform the activity and regarding the prevention measures and corrective actions adopted in relation to the Contractor’s activity.
dell’avvenuta cooperazione in merito all’attuazione delle misure di prevenzione e protezione dai rischi sul lavoro e incidenti sull’attività lavorativa oggetto dell’appalto; / will cooperate for the implementation of the prevention and protection measusres regarding the on the job risks and injuries on the work activity subject of the contract.
dell’avvenuto scambio reciproco di informazioni, attraverso i documenti di cui si allega copia, al fine di eliminare i rischi dovuti alle eventuali interferenze tra i lavori svolti dalle parti; / the mutual exchange of information, through the attached documents, to avoid the risks/hazards due to potential interferences between works performed by the involved contractors and committing part.
che rimane a carico della ditta appaltatrice la valutazione e l’adozione di idonee misure di prevenzione e protezione inerenti i rischi della propria attività. / the contractor has the responsability for the evaluation and implemenatation of the required prevention and protection measusres for the own activity.
In corso d’opera, se dovessero venirsi a modificare le condizioni sopra esposte, sarà cura del committente promuovere una nuova iniziativa di coordinamento e cooperazione al fine dell’eliminazione dei rischi che tale nuova situazione potrebbe comportare. / During the contract activity, in case the conditions above axplained change, the Contractor has the responsability to implement action for the coordination and cooperation in order to eliminate the risks rised from the new condition.
Data / Date: __________
FIRME / SIGNATURES:
Per la Commitenza (POC) / For the Commissioning Employer
Per l’Appaltatore / For the Contractor
| undefined: | |
| 1: | |
| 2: | |
| undefined_4: | |
| 1_2: | |
| 2_2: | |
| INDIRIZZO ADDRESS 1: | |
| INDIRIZZO ADDRESS 2: | |
| undefined_8: | |
| DATORE DI LAVORO EMPLOYER: | |
| undefined_10: | |
| undefined_12: | |
| Date: | |
| 2019-08-27T14:39:43+0200 | |
| CHELOSSI.CHIARA.1462956963 |
| COMANDO USAG ItalyNumero di contratto: |
| COMANDO USAG ItalyAppaltatore: |
| Ragione sociale: |
| Legale rappresentante: |
| Sede legale: |
| Sede operativa: |
| TelefonoFax: |
| eMail: |
| Codice fiscale: |
| Partita iva: |
| Iscrizione alla CCIAA: |
| Posizione assicurativa INAIL: |
| Posizione INPS: |
| CCNL applicato: |
| Responsabile del Servizio di Prevenzione e Protezione RSPP: |
| Rappresentante dei Lavoratori per la Sicurezza RLS: |
| Medico Competente: |
| Responsabile Prevenzione Incendi: |
| Responsabile Pronto Soccorso: |
| Referente della ditta appaltatrice per il coordinamento e la sicurezza: |
| COMANDO USAG ItalyNumero di contratto_2: |
| COMANDO USAG ItalyAppaltatore_2: |
| COMANDO USAG ItalyNumero di contratto_3: |
| COMANDO USAG ItalyAppaltatore_3: |
| COMANDO USAG ItalyNumero di contratto_4: |
| COMANDO USAG ItalyAppaltatore_4: |
| COMANDO USAG ItalyNumero di contratto_5: |
| COMANDO USAG ItalyAppaltatore_5: |
| COMANDO USAG ItalyNumero di contratto_6: |
| COMANDO USAG ItalyAppaltatore_6: |
| COMANDO USAG ItalyNumero di contratto_7: |
| COMANDO USAG ItalyAppaltatore_7: |
| Appaltatore: |
| COMANDO USAG ItalyNumero di contratto_8: |
| COMANDO USAG ItalyAppaltatore_8: |
| Addetti di reparto BFW 1: |
| Addetti di reparto BFW 2: |
| FIRE DEPARTEMENT DSN 117: |
| Servizi esterni External Services: |
| Appaltatore_2: |
| COMANDO USAG ItalyNumero di contratto_9: |
| COMANDO USAG ItalyAppaltatore_9: |
| COMANDO USAG ItalyNumero di contratto_10: |
| COMANDO USAG ItalyAppaltatore_10: |
| NRow1: |
| NRow2: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow1: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow1: |
| NRow3: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow2: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow2: |
| NRow4: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow3: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow3: |
| NRow5: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow4: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow4: |
| NRow6: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow5: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow5: |
| NRow7: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow6: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow6: |
| NRow8: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow7: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow7: |
| NRow9: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow8: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow8: |
| NRow10: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow9: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow9: |
| NRow11: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow10: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow10: |
| NRow12: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow11: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow11: |
| NRow13: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow12: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow12: |
| NRow14: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow13: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow13: |
| NRow15: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow14: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow14: |
| NRow16: |
| Carico e smaltimento materiali contenenti amianto Loading and disposal of materials containing asbestosRow15: |
| Vedere documento Modalita desecuzione rimozione amianto preparato dallimpresa Ecoflash See the document Execution procedure for asbestos removal prepared by the Firm EcoflashRow15: |
| Appaltatore_3: |