This document contains an amendment to a federal solicitation and answers to pre-proposal questions. The purpose of the amendment is to post the last question from 19 August 2019 and revise the contract specification based on the answers provided. The solicitation is for replacing two excitation systems at the Clarence Cannon Power Plant on Mark Twain Lake in Monroe City, Missouri. The contractor will remove asbestos-containing excitation cubicles and field wiring, properly abate the asbestos, and repair the floor. The contractor must also provide a new digital exciter and power potential transformer for each hydroelectric generating unit, connect new non-segregated bus, replace generator brush and holders, and refurbish collector rings. The main control board must be modified to interface with the new digital excitation systems. The solicitation number is W912P919R0044 and is a best value tradeoff request for proposal issued by the U.S. Army Corps of Engineers St. Louis District. The contract duration is 18 months and the project value is between $1-5 million. The response due date is contained in the solicitation package available on FedBizOpps.
Amendment 0006 to Solicitation W912P919R0044.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_Excitation_Specs.pdf | ||
| A22_W912P919R0044_Amend_5.pdf | ||
| Unit_2_Test_Report.pdf | ||
| Unit_1_Test_Report.pdf | ||
| A22_W912P919R0044_Amend_4.pdf | ||
| Asbestos_Testing_Report_391609384_001.pdf | ||
| Pre-Bid_Sign-In.pdf | ||
| A22_W912P919R0044_Amend_3.pdf | ||
| 20190812_CT_Cabinet_Photos.zip | ZIP file | |
| A22_W912P919R0044_Amend_2.pdf | ||
| A22_W912P919R0044_Amend_1.pdf | ||
| A02_CC_Excitation_Plans.pdf | ||
| A02_CC_Excitation_Ref_Drawings.pdf | ||
| A22_Sol_W912P919R0044_Clarence_Cannon_Dam_Excitation_Replacement_System.pdf | ||
| A02_CC_Excitation_Spec.pdf | ||
| A12_Synopsis_19R044.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81C8X91150348
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to post the last question from 19 August 2019. There are no other changes.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Sep-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P919R0044
X 9B. DATED (SEE ITEM 11)
25-Jul-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Sep-2019
CODE
CONTRACTING DIVISION
US ARMY ENGR DIST ST LOUIS
1222 SPRUCE STREET, RM 4.207
ST LOUIS MO 63103-2833
W912P9 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P919R0044
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
QUESTION & ANSWER NO. 5
Clarence Cannon Power Plant Excitation System Replacement
Pre-proposal Questions 19 Aug 2019
Answers to these questions have resulted in a revised contract specification.
1. Subcontracting Plan Large business, If a Commercial Plan is accepted will only SSR Reporting be necessary or will this contract require ISR Reporting?
This contract will require both the SSR Reporting and the ISR Reporting.
End of Questions and Answer
(End of Summary of Changes)