W912P823B0024- Specs-WSLP 101a.pdf

PDF 4 MB Posted

Attached to
West Shore Lake Pontchartrain, WSLP-101a Levee, St. John the Baptist Parish & St. Charles Parish, Louisiana
Solicitation number
W912P823B0024
Issued by

About this file

This document provides details for a federal contract solicitation for construction work on a levee project. The solicitation, number W912P823B0024, will result in an award of a firm fixed price contract valued between $25-100 million to construct a levee in St. John the Baptist Parish and St. Charles Parish, Louisiana near Laplace. The work includes clearing, grubbing, excavating drainage channels, constructing an embankment, installing drains and geotextiles, placing stone, and establishing turf. The response deadline is March 7, 2023. Interested vendors should monitor the System for Award Management website for the solicitation package and any amendments. The Corps of Engineers District in New Orleans is the contracting agency. Calvin Fogle and Margaret Maine are the contract specialists that can be contacted for any questions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01100-a ED 19-020

Section Table of Contents

SECTION 01100 - GENERAL PROVISIONS

1. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER 1

2. DAMAGE TO WORK 2

3. SAFETY PROVISIONS 2

4. INSPECTOR'S FIELD OFFICE 6

5. PROJECT SIGN 7

6. RIGHTS-OF-WAY 8

7. CERTIFICATES OF COMPLIANCE 9

8. ENVIRONMENTAL LITIGATION 9

9. UTILITIES AND IMPROVEMENTS 10

10. STONE SOURCES 12

11. CLAY SOURCES 13

12. FORMAT OF SURVEYS 14

13. BENCHMARK VERIFICATION SURVEYS 15

14. BASELINE RE-ESTABLISHMENT 16

15. ACCESS ROAD “J” MAINTENANCE 17

16. SPECIAL SURVEYING REQUIREMENTS 18

17. GEOTECHNICAL INSTRUMENTATION 18

18. WEIGHT LIMIT RESTRICTIONS OVER PIPELINE CROSSINGS 19

19. COMMERCIAL WARRANTY 19

20. ACCESS PLAN AND STAGING PLAN 19

21. SERVICE TO BE FURNISHED TO THE GOVERNMENT 19

22. ORDER OF WORK 20

23. PERMISSIBLE HOURS OF WORK 21

24. VIDEO AND PHOTOGRAPHIC DOCUMENTATION 22

25. AVAILABILITY AND USE OF UTILITY SERVICES 22

26. COORDINATION WITH LOCAL INTERESTS 22

27. SECURITY REQUIREMENTS 23

28. EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE 24

29. JOINT RISK MANAGEMENT 25

01100-1 ED 19-020

SECTION 01100 - GENERAL PROVISIONS

1. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

(a) This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the Contract Clause in Section 00700, entitled DEFAULT (FIXED PRICE CONSTRUCTION) (FAR 52.249-10).

In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

(b) The following schedule of monthly anticipated adverse weather delays is based upon data collected by the Louisiana Office of State Climatology for temperature, precipitation and wet ground conditions or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor’s progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities. The adverse weather days apply to rain, fog, high winds, high/low tides, hail, lightning, and high/low temperatures as indicated on the Weather Data Sheet and will be used by the Government to record weather during construction.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS

BASED ON (5) DAY WORK WEEK

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

(c) Upon receipt of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

(d) The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month) and shall be calculated chronologically from the first to the last

01100-2 ED 19-020

day of each month and shall be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clause in Section 00700, entitled DEFAULT (FIXED PRICE CONSTRUCTION) (FAR 52.249-10).

2. DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause in Section 00700, entitled PERMITS AND RESPONSIBILITIES (FAR 52.236-7). However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit price or job prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there is no contract unit or job prices applicable to any part of such work, an equitable adjustment shall be made pursuant to the Contract Clause in Section 00700, entitled CHANGES (FAR 52.243-4). Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

3. SAFETY PROVISIONS

The safety provisions as specified herein refer to the November 2014 edition of EM 385-1-1. The current document can be found at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM _385-1-1.pdf

(a) Mishap Reporting and Recordkeeping. Refer to EM 385- 1-1, Section 01.D.

Reports shall be submitted on ENG Form 3394. Accidents shall be investigated and reports completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or his/her representative within one working day after the accident occurs. All data reported must be complete, timely and accurate. A follow-up report shall be submitted when the estimated lost time days differs from the actual lost time days.

(b) Accident Prevention Plan (APP). (See the Contract Clause in Section 00700, entitled ACCIDENT PREVENTION (FAR 52.236-13).) Within 15 days after receipt of Notice of Award of the contract, and at least 7 days prior to the pre-work conference, four copies of the Accident Prevention Plan shall be submitted to the Contracting Officer for review and acceptance. The plan shall be prepared in the following format:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

01100-3 ED 19-020

(1) Executed CESO Form A-02), Accident Prevention Plan Checklist (the “fillable form” can be obtained from:

http://www.usace.army.mil/Portals/2/docs/Safety/EM%20385-1- 1,%202014%20Sections/Checklists/CESO%20Checklist%20A- 02%20Accident%20Prevention%20Plan.pdf)

(2) Activity Hazard Analysis (AHA) Form, Figure 1-2 in Section 1 “Program Management” of EM 385-1-1 (attached at the end of this section). The Contractor shall address each of the elements/sub-elements in the outline contained in Appendix A of EM 385-1-1 in the order that they are provided in the manual. If an item is not applicable because of the nature of the work to be performed, the Contractor shall state this exception and provide a justification.

(3) A copy of company policy statement regarding accident prevention.

(4) When marine plant and equipment are in use under a contract, the method of fuel oil transfer shall be included on MVN Form 385-10 (Latest Edition), Fuel Oil Transfer (attached at the end of this section), (Refer to

33 CFR 156).

(5) EM-385-1-1 01.A.14, subparagraph (a), requires a hazard analysis for all features of work. For this contract, these hazard analyses shall be submitted with the rest of the APP for review before work begins. Hazard analysis may be refined and resubmitted at a later date if the Contractor chooses.

The Contractor shall not commence physical work at the site until the Contracting Officer, or his/her authorized representative has accepted the plan. The Contractor may submit its Accident Prevention Plan only for the first phase of construction provided that it is accompanied by an outline of the remaining phases of construction. All remaining phases shall be submitted and accepted prior to the beginning of work in each phase. Also refer to Section 1 of EM 385- 1-1.

(c) Comprehensive Hazard Communication Program. The Contractor shall develop, implement, and maintain at the workplace a written, Comprehensive Hazard Communication Program (see Section 06.B.01 of EM 385-1-1) that includes identification of potential hazards as prescribed in 29 CFR Part

1910.1200 and/or 1926.59, effects of exposure and control measures to be used for chemical products and physical agents that may be encountered during the performance of work on this contract, provisions for container labeling, Safety Data Sheets, and employee training program, and other criteria in accordance with 29 CFR Part 1910.1200 and/or 1926.59. Training shall include communication methods and systems to be used (i.e., voice, hand signals, radios or other means), and training in the use and understanding of safety data sheets http://www.usace.army.mil/Portals/2/docs/Safety/EM%20385-1-1,%202014%20Sections/Checklists/CESO%20Checklist%20A-02%20Accident%20Prevention%20Plan.pdf http://www.usace.army.mil/Portals/2/docs/Safety/EM%20385-1-1,%202014%20Sections/Checklists/CESO%20Checklist%20A-02%20Accident%20Prevention%20Plan.pdf http://www.usace.army.mil/Portals/2/docs/Safety/EM%20385-1-1,%202014%20Sections/Checklists/CESO%20Checklist%20A-02%20Accident%20Prevention%20Plan.pdf

01100-4 ED 19-020

and chemical product hazard warning labels. Prior to bringing hazardous substances, as defined in 29 CFR 1910.1200 and/or 1926.59, onto the job site, a copy of the Hazard Communication Program and the Safety Data Sheets of each substance shall be submitted to the Contracting Officer and made available to the Contractor's employees as part of its Accident Prevention Plan. A site map shall be attached to the inventory showing where the inventoried hazardous substances are stored. The inventory list and site map shall be updated monthly to assure accuracy.

(d) Daily Inspections. The Contractor shall perform daily safety inspections and record them on the forms approved by the Contracting Officer. Reports of daily inspections shall be maintained at the jobsite in accordance with Section 01 45

04.00 10, "CONTRACTOR QUALITY CONTROL". The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:

(1) Phase(s) of construction underway during the inspection.

(2) Locations of areas where inspections were made.

(3) Results of inspections, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

(e) Safety Sign. The Contractor shall furnish, erect, and maintain a safety sign at the site where indicated by the Contracting Officer. The sign shall conform to the requirements of this paragraph and the drawing included at the end of this section. The lettering shall be black, the safety circle and cross green, and the background white. When placed on a floating plant, the sign may be half size.

The sign shall be erected as soon as practicable, but not later than 15 calendar days after the date established for commencement of work. The data required shall be current. The sign coordinator is Timothy Lacoste, (504) 862-2663.

(f) Ground Fault Protection. Electrical equipment used on this contract shall be equipped with ground fault circuit interrupters in accordance with EM 385-1-1, Section 11.D.05.

(g) Hurricane Plan. The contractor shall prepare a detailed Hurricane Plan to protect personnel and equipment in the event of an impending storm. The plan shall include at least the following:

(1) Sealing Operation: The contractor shall submit with his Hurricane Plan a method for sealing any de-grassed area prior to evacuation from the construction site. Sealing must be performed with equipment exerting a ground force of not less than 6.0 psi. If a dozer is used to seal the embankment, it shall not weigh less than 20,000 lbs. Initial passes shall be

01100-5 ED 19-020

parallel to the levee centerline, and the final pass shall be perpendicular to the levee centerline. Sealing equipment shall remain on site at all times between 1 June and 30 November.

(2) The time when each phase will be put into effect. This time is the number of hours remaining for the storm to reach the work site if it continues at the predicted speed and direction.

(3) The estimated time necessary to implement emergency flood protection, secure the site, and evacuate all personnel.

The Hurricane Plan is required as an enclosure to the contractor's Accident Prevention Plan. It shall be submitted to the Contracting Officer, or his/her representative, for review and approval prior to the preconstruction conference.

No separate measurement or payment will be made for the Hurricane Plan.

Payment shall be distributed amongst the existing bid items. Payment for all work associated with the Hurricane Plan, and providing the equipment required for the duration specified, shall be distributed amongst the existing bid items.

(h) Cranes. The Contractor (including subcontractors) shall have cage boom guards, insulating links, or proximity warning devices on cranes that will be working adjacent to power lines. These devices shall not alter the requirements of any other regulation of this part - even if such device is required by law or other regulation. Insulating links shall be capable of withstanding a 1-minute dry low frequency dielectric test of 50,000 volts, alternating current (EM 385-1-1, Section 11.F.08). Calibration records or stamped date of required manufacturer inspection of proximity warning devices shall be kept on the crane. Additionally, prior to any work commencing an Activity Hazard Analysis (EM 385-1-1, Fig.1-2) identifying and satisfying EM 385-1-1, Section 11.A.02, 11.F.03, 11.F.04, 11.F.05, and Table 11-1 requirements shall be submitted and accepted by the Contracting Officer.

(i) Site Safety and Health Officer (SSHO). The Contractor shall have a qualified Site Safety and Health Officer (SSHO) on the construction site at all times that work is being performed to manage the Contractor’s Accident Prevention Plan.

The SSHO shall be a full-time responsibility and shall have no other duties (see EM 385-1-1, paragraph 01.A.17). The person(s), as a minimum, shall have completed the 30-hour OSHA Construction Industry Safety Class (may be web-based training if the student is able to directly ask questions of the instructor by chat / phone) or an equivalent course (see Appendix A, paragraph 3.d.(3)) applicable to the work to be performed, and given by a qualified instructor. Such training shall have been completed within the last three (3) years. SSHO’s shall maintain competency through taking 8 hours of documented formal, on-line, or self-study safety and health coursework every year. For projects with multiple shifts, an alternate SSHO shall be assigned to assure coverage of the project during all working hours. Alternate SSHO’s (as listed in the Contractor’s APP)

01100-6 ED 19-020

must meet the same requirements as the primary SSHO. Alternate SSHO’s may hold other positions when not functioning as an SSHO.

(j) Hazardous Energy Protection. The Contractor shall develop, implement and maintain at the workplace, a written Control of Hazardous Energy (Lockout/Tagout) System. Refer to Section 12 of EM 385-1-1.

4. INSPECTOR'S FIELD OFFICE

(a) The Contractor shall furnish, throughout the contract period, for the exclusive use of the Government employees, a temporary waterproof building, or trailer, to be utilized as a field office. It shall be conveniently located at the site of construction and shall be independent of any building, or trailer, used by the Contractor. Toilet facilities and potable water, including bottled water with water cooler, shall be provided within the Inspector's office. It shall be equipped with approved electrical wiring, private telephone service, a fax / copier / printer / scanner machine. It shall be equipped with 3 ceiling lamps, 3 double convenience outlets, and the required switches and fuses, to provide 110-volt power for lighting and operating a laptop computer and printer. It shall be equipped with an air conditioning unit to provide cooling in warm or hot weather, and a heater, properly installed and vented in accordance with the National Fire Protection Association Code, for heating in cold weather, as required. The Contractor shall make the necessary arrangements to obtain or to generate the power required to operate the air conditioning unit, lights, and laptop computer and printer, and the power or fuel required for the heater, and shall bear the cost thereof. A drafting table providing a working surface having dimensions of at least 4-feet by 6-feet (which may consist of a piece of plywood, at least 3/4-inch thick, hinged to a wall of the building with hinged legs) shall be installed in the building. The building shall have a built-in locker, extending from the floor to the ceiling, having dimensions of at least 2- feet by 5-feet, with a shelf 12-inch from the top, and one door equipped with two hinges, a hasp and a padlock. All exterior doors and window frames of the building shall be equipped with iron security guards. The door shall also be equipped with butt hinges and a cylinder lock. One draftsman's stool, two strong chairs and two desks shall be provided.

The building or trailer shall conform to the following minimum requirements:

Ceiling height, not less than 6-feet 9-inches Floor space, no less than 240 square feet

Windows, not less than 4

Doors, outside 2

Rooms 3

01100-7 ED 19-020

Screens over windows; walls and ceilings shall be insulated; and interior walls finished.

(b) The building, or trailer, shall be removed by the Contractor after completion of all work under this contract and before final acceptance thereof. No separate payment will be made for furnishing, maintaining, providing the prescribed utilities, and removing the inspector's field office. The cost of the same shall be distributed throughout the existing bid items. In the event the Contractor fails to furnish the required facilities, the Government may elect to procure the required facilities and deduct all costs from amounts due or to become due under this contract.

(c) The Contractor shall provide daily janitorial services for this and other buildings at the site throughout the life of the contract. The cost of this service shall be distributed throughout the existing bid items and there shall be no separate payment. The Contractor shall provide an airboat with operator to safely transport personnel through the swamp should an injury occur and also to transport Government personnel to perform inspections of work in progress.

(d) The Contractor shall provide the inspector’s field office with a hard line broadband high speed internet service and associated equipment for the exclusive use of the Government. If this service is not practical at the jobsite, the Contractor may instead provide the inspector’s field office with a cellular wireless Broadband / WiFi 802.11n capable router that accepts cellular data signals through Express Card / Air Card or USB modems. This service must be capable of providing adequate connection to allow the inspectors to import/export files through RMS. The Contractor must field verify that the service provider chosen has adequate continuous coverage at the construction site. This service shall provide a minimum download speed of 20 Mbps and a minimum upload speed of 5 Mbps. The Contractor shall be responsible for the installation, the maintenance of, and the monthly service fees necessary to provide continuous high speed internet service for the duration of the contract.

(e) The Government and Contractor’s field offices shall be placed within the location and limits of the Government environmentally cleared right of way (ROW) or Limits of Construction (LOC).

5. PROJECT SIGN

Prior to commencement of work, the Contractor shall construct a project sign at the site of the work at a location directed by the Contracting Officer. The sign, which will identify the work with the Corps of Engineers shall be 4 feet by 6 feet in size and shall conform to the requirements of the PROJECT SIGN drawing and installation instructions attached at the end of this section. The lettering for the 2 feet by 4 feet section of the sign with the Corps logo and Army Star shall be white; all other lettering shall be black. Lettering for the project name shall be Helvetica Bold, all other

01100-8 ED 19-020

lettering shall be Helvetica Regular. The sign coordinator is Timothy Lacoste, (504) 862-2663. No separate payment will be made for construction and erection of the project sign and all costs in connection therewith will be considered an incidental obligation of the Contractor. Upon completion of the work, the sign shall become the property of the Contractor and shall be removed from the job site.

6. RIGHTS-OF-WAY

a. The rights of entry required for the work to be constructed under this contract, within the rights-of-way limits indicated on the drawings, have been obtained by the Government and are provided without cost to the Contractor. The Contractor shall make its own investigations to determine the conditions, restrictions, and difficulties that may be encountered in the transportation of equipment and material to and from the work site. The proposed work, including rights-of-way, as defined by these specifications and as shown on the drawings, is in compliance with all applicable Federal and state environmental laws and regulations. Upon completion of the Contractor’s work, rights-of-way furnished by the Government shall be returned to its original condition prior to construction unless otherwise noted.

b. If the Contractor proposes a deviation from the Government furnished rights-of-way for his convenience, the Contractor shall notify the Contracting Officer or its representative in writing. Contractor shall not provide any permanent rights-of-way for the project. The Contractor is cautioned that any deviation to the Government furnished rights-of-way is subject to all applicable Federal and state environmental laws and regulations. Compliance with these environmental laws and regulations may require additional National Environmental Policy Act (NEPA) documents, cultural resources surveys, coordination with the Louisiana State Historical Preservation Officer, water quality certification, modification of the Federal consistency determination, etc. The Government is ultimately responsible for environmental compliance; therefore, the Government will determine the additional environmental coordination and documentation necessary for a proposed deviation to the Government furnished rights-of-way.

For any environmental investigations the Government is to perform on areas outside of Government furnished rights-of-way, the Contractor shall provide sufficient rights of entry to the Government. The Contracting Officer will advise the Contractor of the additional environmental coordination and documentation that must be completed. The Government shall be responsible for any additional environmental compliance; however, the Contractor may conduct specific tasks identified by the Government. The Government will offer advice and assistance to the Contractor in conducting these tasks. Depending on the environmental impact of the proposed deviation, obtaining the coordination and documentation may not be approved or could take as much as 180 days for approval by the Government. The Government must review, approve and ensure distribution of all environmental compliance documentation and ensure all comments on the same have been resolved before any utilization of any areas outside of the

01100-9 ED 19-020

Government furnished rights-of-way. The Contractor shall reimburse the Government for actual expenses incurred for assistance in completing or attempting to complete additional environmental coordination and documentation, which expenses will not exceed one hundred thousand ($100,000.00.) dollars. There is no guarantee that environmental compliance will be obtained; therefore, the Contractor shall assume all risks and liabilities associated with pursuing a deviation. Any delays resulting from the deviation and/or the environmental coordination and documentation shall not be made the basis of any Contractor claim for increase in the contract cost and/or increase in contract time. Deviations will be at Contractor’s sole risk and liability, including, but not limited to, such liabilities associated with items such as hazardous substances regulated under the Comprehensive Environmental Response, Compensation, and Liability Act (42 U.S.C. 9601 et. seq.), and at no cost to the Government. Government assistance in obtaining additional environmental clearances does not relieve the Contractor of responsibility for complying with other Federal, state or local licenses and permits.

c. The Contractor shall stake out and flag the project right-of-way limits at 500’ intervals as well as at directional changes. The Contractor is responsible for maintaining the project right-of-way limits.

7. CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in three (3) copies. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet specified requirements.

8. ENVIRONMENTAL LITIGATION

(a) The term "environmental litigation," as used herein, means a lawsuit alleging that the work has an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

(b) If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined above, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If the order is not due in any part to acts or omissions of

01100-10 ED 19-020

the Contractor (or a Subcontractor at any tier) other than as required by this contract, such suspension, delay, or interruption shall be as if ordered by the Contracting Officer under the Contract Clause in Section 00700, entitled SUSPENSION OF WORK (FAR 52.242-14). The period of such suspension, delay or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof.

9. UTILITIES AND IMPROVEMENTS

(a) No utilities within the limits of work have been identified. Access Road “J” located outside of the limits of work, contains multiple pipeline crossings with weight limit restrictions. See paragraph WEIGHT LIMIT RESTRICTIONS OVER PIPELINE CROSSINGS. Additional utilities lie outside the limit of work at approximately B/L Sta. 979+00. All utilities shown are not to be disturbed. Any unidentified pipes or structures which may be found within the limits of the work during construction shall not be disturbed nor shall construction or excavation be performed at these locations unless and until approved by the Contracting Officer. The Contractor shall contact Louisiana One Call at 1-800-272-3020 to verify utility lines crossing levee, prior to start of mobilization. Utility points of contact are provided below.

ST. JOHN the BAPTIST PARISH Reed Alexander Asst. Director of Utilities 1811 W. Airline Hwy LaPlace, LA 70068 985-651-6800 (office) r.alexander@stjohn-la.gov

SHELL PIPELINE COMPANY

Damian Cambre 15601 Airline Hwy Norco, LA 70079 225-380-9089 (mobile) 504-465-6878 (office) Damian.Cambre@shell.com

Shane Degruise 15601 Airline Hwy Norco, LA 70079 346-773-5782 (mobile) Shane.Degruise@shell.com mailto:r.alexander@stjohn-la.gov mailto:Damian.Cambre@shell.com mailto:Shane.Degruise@shell.com

01100-11 ED 19-020

ENERGY TRANSFER PARTNERS, L.L.C.

Celeste Waterwall Senior Manager of Encroachments 1300 Main St Houston, TX 77002 713-989-7000 (office) Celeste.Waterwall@EnergyTransfer.com

ENTERPRISE PRODUCTS COMPANY

Cameron Lair Land-Encroachments 1100 Louisiana Street Houston, TX 77002 713-381-3128 (mobile) 713-381-6500 (office) clair@eprod.com

ENTERGY LOUISIANA, LLC

James Cotton ELL South Region Distribution Field Engineer 4317 W Airline Hwy Reserve, LA 70084 985-479-2000 (office) 601-300-1136 (mobile) jcotton1@entergy.com

PRAXAIR, LINDE

John Mack 175 E Park Dr Tonawanda, NY 14150 716-879-7560 (office) 716-465-1908 (work) John_Mack@praxair.com

ENLINK LIG, LLC

Chris Greneaux Right-of-Way Department 2300 South College Road Lafayette, LA 70508 337-354-1700 (office) chris.greneaux@enlink.com

BUCKEYE

Daniel Mangum 4200 Westheimer Rd Ste 975 Houston, TX 77027 mailto:Celeste.Waterwall@EnergyTransfer.com mailto:clair@eprod.com mailto:jcotton1@entergy.com mailto:John_Mack@praxair.com mailto:chris.greneaux@enlink.com

01100-12 ED 19-020

832-325-1626 (office) 832-541-3946 (mobile) DMangum@buckeye.com

PHILLIPS 66

Lamar Felder 2331 Citywest Blvd Houston, TX 77042 832-765-4015 (office) 713-517-0516 (mobile) Lamar.Felder@p66.com

AIR LIQUIDE LARGE INDUSTRIES U.S. LP

William Wood 3011 Pasadena Freeway, Ste 190 Pasadena, Texas 77503 713-740-8707 (office) 601-818-5420 (mobile) william.wood@airliquide.com

10. STONE SOURCES

(a) On the basis of information and data available to the Contracting Officer, stone meeting the quality requirements of these specifications has been produced from the listed stone sources attached at the end of this section.

(b) Stone may be furnished from any of the listed STONE SOURCES (attached at the end of this section), or at the option of the Contractor may be furnished from any other source designated by the Contractor and accepted by the Contracting Officer, subject to the conditions hereinafter stated.

(c) The Contractor shall determine that the stone source or combination of sources selected is capable of supplying the quantities and gradation needed and at the rate needed to maintain the scheduled progress of the work.

(d) After the award of the contract, the Contractor shall designate in writing only one source or one combination of sources from which he/she proposes to furnish stone. If the Contractor proposes to furnish stone from a source not listed in STONE SOURCES (attached at the end of this section), he/she may designate only a single additional source for stone. Samples for acceptance testing shall be provided as required by Section 35 31 19.04 12. If a source for stone so designated by the Contractor is not accepted for use by the Contracting Officer, the Contractor may not propose other sources but shall furnish the stone from a source listed in STONE SOURCES (attached at the end of this section) at no additional cost to the Government.

mailto:DMangum@buckeye.com mailto:Lamar.Felder@p66.com mailto:william.wood@airliquide.com

01100-13 ED 19-020

(e) The listings of the names of the stone suppliers does not constitute an endorsement of such companies. Acceptance of a source of stone is not to be construed as acceptance of all material from the source. The right is reserved to reject materials from certain localized areas, zones, strata, or channels, when such materials are unsuitable for stone as determined by the Contracting Officer.

Materials produced from a listed or unlisted source shall meet all requirements of Section 35 31 19.04 12.

11. CLAY SOURCES

(a) Embankment materials may be obtained from the Government furnished embankment stockpile as shown on the drawings.

(b) On the basis of information and data available to the Contracting Officer, the commercial borrow sources designated below have been studied by the Government for environmental concerns and soil suitability. The designated sites, below, may be capable of producing the quality of clay material meeting the requirements set forth in Section 31 24 00.00 12 EMBANKMENT, paragraph entitled “MATERIALS”, including salinity requirements set forth in Section 31 23

00.00 12 EXCAVATION, paragraph entitled “Borrow Area Agronomy Report”, and are subject to the subparagraphs (b) through (e) below. However, some documentation relating to the below sites may need to be updated prior to their use. The Contractor shall verify that environmental clearances for the below sites have not expired. The Contractor shall, within 90 days of notice to proceed, inform the Contracting Officer of the intention to not use the Government furnished borrow pit(s) shown on the drawings.

Source Name Point of Contact Contact Information Location

Edgard Construction John Ohle, III President, CEO

(224) 260-1709 jbo@edgardconstructionmateria ls.com

1973 Hwy 3127, Edgard, Louisiana 70049

St. James Construction Materials (Big Shake)

John Ohle, III President, CEO

(224) 260-1709 ibo@river-parishes.com

4011 Highway 3125.

Paulina, LA 70763

Myrtle Grove Khai Nguyen khai.nguyen@myrtlegroveborro w.com

(504) 615-1077

1051-A W. Ravenna Rd, Belle Chasse, LA 70037

Providence Eng. & Environmental Group, LLC / Hurricane Work, LLC

Claud Klein

Tim Kimmel

Cklein01@bellsouth.net

(504) 338-3670 timkimmel@bellsouth.net

(225) 766-7400

POC Location: 114 Schleif Dr, Belle Chasse, LA 70037 Business Location: 39050 Hwy 942, Darrow LA

Pearlington Clay, LLC Johnny E Dollar, Managing Member johnny.dollar@thedollarlawfirm.

com

(318) 366-8218

Whites Rd and Lower Bay Rd, Pearlington, MS 39573

(c) Clay may be furnished the embankment stockpile area provided, from any of the above listed sources, or at the option of the Contractor may be furnished from any other source designated by the Contractor and accepted by the Contracting Officer. Clay furnished from a source designated by the Contractor not included

01100-14 ED 19-020

in the above listed sources are subject to the conditions in Section 31 23 00.00 12 EXCAVATION, paragraph entitled CONTRACTOR-FURNISHED BORROW

AREAS.

(d) The Government is not responsible for any agreements or breach of agreements nor the resulting impacts of any breach of agreements between the Contractor and the listed owners and/or agents and or any other persons.

(e) Contact the Point of Contact for the above sources for information regarding the location of the sites and geotechnical boring logs of the material.

(f) Usage of any of the above listed clay sources shall neither relieve the Contractor from its obligation to furnish satisfactory material to the project nor commit the Government to the acceptance of the character, quantity or availability of material from these sources. Verification of the material should be performed by the Contractor to assure that the material meets the contract specifications for embankment construction material.

12. FORMAT OF SURVEYS

a. The Contractor shall submit compliance surveys upon completion of certain construction activities. The survey shall be collected in accordance with the “USACE New Orleans District Minimum Survey Standards” and delivered in USACE EM Format as described in “Engineering Manual File Format Specifications”. Links to these documents are shown below:

http://www.mvn.usace.army.mil/Missions/Engineering/SurveySection/SurveyingG uidelines.aspx http://www.mvn.usace.army.mil/portals/56/docs/engineering/Geospatial/EM_For mat15.pdf

b. Each surveyed point should be listed on a separate line as a comma-delimited list of the following:

(1) Point ID, northing, easting, elevation, code

(2) Surveyed points that are part of a profile shall be grouped under the appropriate #P01 record for that profile.

(3) Surveyed points that are part of a cross-section shall be grouped under the appropriate #X01 record for that cross-section.

(4) All other points shall be grouped under the appropriate #M01 record.

c. Each Project Control Point (PCP) shall be included as #V/#T records with the surveyed elevation #V/T06, and vertical datum and epoch information. Absolute http://www.mvn.usace.army.mil/Missions/Engineering/SurveySection/SurveyingGuidelines.aspx http://www.mvn.usace.army.mil/Missions/Engineering/SurveySection/SurveyingGuidelines.aspx http://www.mvn.usace.army.mil/portals/56/docs/engineering/Geospatial/EM_Format15.pdf http://www.mvn.usace.army.mil/portals/56/docs/engineering/Geospatial/EM_Format15.pdf

01100-15 ED 19-020

vertical and horizontal accuracies shall be shown in the #H03 and #H17 records.

The USACE Survey Drivers shall be used to check for proper formatting.

http://www.mvn.usace.army.mil/Missions/Engineering/GeospatialSection/USACE SurveyDrivers.aspx

d. A survey report shall be submitted which includes a brief synopsis of the survey methodology (traverse run, level loops, GPS). Copies of all supporting field books shall be signed and sealed by a Licensed Surveyor registered in the state in which the work is being performed. If static GPS is collected, minimally and fully constrained GPS adjustment reports must be submitted as well as any other notes, reports, raw data, and supporting documentation.

e. All surveys shall adhere to the requirements of the “USACE New Orleans District Minimum Survey Standards” and be performed by a licensed surveyor registered in the state in which the work is being performed. The point of contact for survey information is Dwayne Blanchard @ 504.862.1589.

13. BENCHMARK VERIFICATION SURVEYS

a. Project Control Points. For purposes of vertical control, Project Control Points may be referred to as Project Benchmarks. Project Control Points located at the project site may be used as Local Project Control Points and referred to as Site Benchmarks. To ensure local / internal consistency, the Contractor shall verify all Project Benchmarks and Site Benchmarks using differential leveling following Section J of the “USACE New Orleans District Minimum Survey Standards”. All benchmarks serve as vertical control for the entire project. The benchmark verification survey shall constrain to the Primary Benchmark as shown on the drawings. The differential levels must be to Second Order Class II closure standards, as defined in Appendix 4 of the Minimum Survey Standards, and as follows: closure error (in feet) must be less than or equal to 0.035 x √(distance in miles). Significant closure error (any random error whose magnitude would affect the final elevation of benchmarks when significant digits are considered) shall be distributed through all benchmarks (Project Benchmarks and Site Benchmarks) according to their relative distance along the loop. Verification of all benchmarks shall be performed within 14 days of receipt of the Notice to Proceed and at least every 6 months using differential leveling.

b. Site Benchmarks. At all established hurricane protection, flood control, shore protection, and navigation projects, three permanent site benchmarks (new or existing) shall be identified/established at the immediate work site (situated as nearly as practicable at the middle and at each end of the project) and referenced to the applicable required epoch of NAVD88. Site Benchmarks are Local Project Control Points provided on the drawings or monuments set by the Contractor according to EM 1110-1-1002, Survey Markers and Monumentation.

Site Benchmarks set by the Contractor are limited to types A, B, C, F, or G as http://www.mvn.usace.army.mil/Missions/Engineering/GeospatialSection/USACESurveyDrivers.aspx http://www.mvn.usace.army.mil/Missions/Engineering/GeospatialSection/USACESurveyDrivers.aspx

01100-16 ED 19-020

described in Chapter 3 of EM 1110-1-1002 and the type and location must be approved in advance by the District Datum Coordinator (DDC). Vertical positioning for all construction activities shall be constrained to a Project or Site Benchmark. To obtain pre-approval for a proposed Site Benchmark, the Contractor shall submit the following to the Contracting Officer’s representative (COR): the approximate proposed x, y position; the type of monument; and 5 photos of the proposed location: 1 of the proposed site, and 4 photos taken from the proposed site facing in 4 cardinal directions.

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals /EM_1110-1-1002.pdf

c. Survey Report. The benchmark verification survey data shall be submitted in a Survey Report signed and sealed by a Licensed Surveyor registered in the state in which the work is being performed. The survey report shall be updated and submitted with each benchmark verification survey. The survey report shall include a table of all Project and Site Benchmark measurements and all previous benchmark verification measurements for comparison purposes. The report shall include a graphic that shows the approximate positions of all control points, the route of the differential level loop, and the approximate distances between control points. The report shall include clear, legible field notes that show the daily “Two-Peg Test”, all measurements and calculations, and the closure error for each closed loop. Any raw data such as digital level pre or post-processing reports should be included. Each level loop shall be reviewed and initialed in the field book by a person independent of the field crew performing the level loop.

Only the field notes for the current benchmark verification survey should be included in each report.

d. Submittals. Survey Reports of the benchmark verifications shall be submitted to the Contracting Officer’s Representative (COR) in electronic format via RMS- CM within 7 days of the completion of the benchmark verification. If the file is too large to submit via RMS-CM, contact the COR for alternate methods. The COR shall be notified immediately if any errors or inconsistencies in the benchmark verifications are found. The Survey Report of the first benchmark verification survey must be received within 14 days of receipt of the Notice to Proceed or as required by the COR.

14. BASELINE RE-ESTABLISHMENT

a. Project Baseline Re-establishment. To ensure consistency with the information shown on the drawings, prior to any construction layout activities the Contractor shall reestablish the project baseline using procedures to assure a survey accuracy of +/- 0.10 feet. The surveys shall be constrained to the Project Control Points shown on the drawings and collected in accordance with the “USACE New Orleans District Minimum Survey Standards”. Each baseline point http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_1110-1-1002.pdf

01100-17 ED 19-020

of intersection (PI) shall be marked on the ground with a temporary marker as defined by EM 1110-1-1002:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals /EM_1110-1-1002.pdf

b. Floodwall Alignment Layout. Upon completion of the project baseline re-establishment, the Contractor shall establish the floodwall alignment. Each wall-line point of intersection (PI) must be marked on the ground with a temporary marker as defined by EM 1110-1-1002. The surveys shall be collected in accordance with the “USACE New Orleans District Minimum Survey Standards”.

c. Survey Report. The baseline re-establishment survey data shall be submitted in a Survey Report signed and sealed by a Licensed Surveyor registered in the state in which the work is being performed. The survey report shall include the X and Y location of all set PIs and the constraining Project Control Points. The survey report shall include a table of all Project Control Points, Local Project Control Points, and temporary PI markers that were set. The report shall include a graphic that shows the approximate positions of all control points, the baseline, and the baseline PIs. The report shall include clear, legible field notes that show the control ties, and all measurements and calculations. Any raw data such as GPS reports or pre/post-processing traverse reports should be included.

d. Submittals. Survey Reports of the baseline re-establishment shall be submitted to the Contracting Officer’s Representative (COR) in electronic format via RMS-CM within 7 days of the completion of the baseline re-establishment. If the file is too large to submit via RMS-CM, contact the COR for alternate methods. The COR shall be notified immediately if any errors or inconsistencies in the baseline re-establishment are found. Field records of the baseline re-establishment must be received within 14 days of receipt of the Notice to Proceed.

15. ACCESS ROAD “J” MAINTENANCE

The maintenance of access roads shall include grading, replacing road surfacing, watering, dust control, removal of mud, spillage, and disposal of debris. Access Road "J" is a shared use roadway which will be utilized by other Contractors, landowners, and farmers during the construction duration. Each Contractor is responsible for their own maintenance. Grading the entire road shall be conducted every other day until substantial completion of this contract. Grading shall be done regardless of whether the Contractor is hauling or not. Adding of surfacing to the access road shall be as directed by the COR. The Contractor shall remove any spillage, debris and any mud tracking on the shared access road and US Hwy 61 regardless of source of debris.

Watering and dust control shall be conducted on a continuous and daily basis.

Maintenance of “Access Road “J” shall be in accordance with applicable requirements of Section 32 15 00.00 12 - SURFACING (GRANULAR).

01100-18 ED 19-020

16. SPECIAL SURVEYING REQUIREMENTS

(1) After completion of the levee sand base to the lines and grades shown on the drawings, the Contractor shall perform cross section surveys across the entire levee footprint prior to placing levee embankment, utilizing an independent licensed surveying firm. These surveys will be used in computing the quantities of embankment material for payment (see Section 31 24 00.00 12 EMBANKMENT for additional information). The surveyor shall be licensed in the State of Louisiana and shall not be an employee of the prime or sub-contractor.

All surveys and quantity computations submitted for payment shall be stamped by the independent licensed surveyor. The Contractor shall submit the original cross sections and the Government will perform the theoretical computations for computing the quantities for payment.

(2) All survey data shall be recorded in accordance with the paragraph FORMAT OF SURVEYS. The Contractor shall furnish the additional required data described below to the Government as an electronic text file via RMS and by email to mvn-cd-q-testresults@usace.army.mil. If the files are too large for transmission, contact the COR for alternate transmission methods. The information received should be free of errors and in the following format:

(a) The X - coordinate in feet (Easting),

(b) the Y - coordinate in feet (Northing), and

(c) mandatory remarks such as the station number (i.e. 1+00), CL (for centerline), ES (for end of station), EJ (for end of file), and direction of survey (either “L” for + or “R” for -, followed by Station No., i.e. L 30+00) as described in the attachments RECORDING SURVEYS FOR CROSS SECTIONS and the SURVEY DATA SAMPLE at the end of this section.

17. GEOTECHNICAL INSTRUMENTATION

Instrumentation will be installed by a third-party contractor. The approximate location of the instruments will be as shown on the drawings. The Contractor shall provide a ten-day advanced notice to the Contracting Officer indicating that the site is ready for the installation of the instrumentation. The Contractor shall coordinate with the third-party contractor for any work performed across the corridor between the instruments and the adjacent data logger. The Contractor shall provide access at all times to the third-party contractor to the instrumentation locations as well as access for the performance of borings and cone penetration tests. As soon as the Contractor establishes the width of the sand base at the locations of the geotechnical instrumentation, the Contractor shall install an access platform constructed of clay embankment material 15-feet wide to elevation 2.5 from the sand base out to 43-feet beyond the toe of the levee berm. The Contractor shall provide to the Government cross sections of the levee embankment adjacent to the geotechnical instrumentation twice a week during levee construction and once a month during the levee hold mailto:mvn-cd-q-testresults@usace.army.mil

01100-19 ED 19-020

periods. Payment for these surveys shall be included in the contract prices for the items to which the work is incidental thereto.

18. WEIGHT LIMIT RESTRICTIONS OVER PIPELINE CROSSINGS

The provided access roads and equipment traversing pipelines within the rights of way are restricted to the following individual vehicle load limits:

a. 24,000 pounds single axle weight

b. 48,000 pounds for each tandem axle group

c. 60,000 pounds for each tridum axle group

d. 54,000 pounds for each trunion axle group (16 wheels)

e. 650 pounds per inch width of tire

f. 180,000 pounds gross vehicle weight, not to exceed any axle or wheel limit listed in a. through e. above.

The Contractor shall ensure that only a single lane of traffic is utilized when crossing specialty equipment requiring a permit, including any custom axle…