W912P822B0029 Bid Abstract.pdf
PDF 503 KB Posted
- Solicitation number
- W912P822B0029
About this file
This abstract of offers summarizes bids received in response to Solicitation Number W912P822B0029 issued by the United States Army Corps of Engineers New Orleans District. The solicitation seeks bids for a sand placement contract to construct 5950 linear feet of sand fill to an elevation of +3.0 in a marsh area, including clearing, grubbing, and stump removal. The base contract work consists of 3075 linear feet, with optional work 1 adding 1540 linear feet and optional work 2 adding 1335 linear feet if exercised. Nine contractors submitted bids ranging from $1,688,690 to $3,324,866 for the base work plus both options. Required bid security was $3,000,000 and amendments were acknowledged by all bidders. The small business set-aside solicitation had a response due date of March 29, 2022 and was issued to provide access to West Shore Lake Pontchartrain via Highway 61.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
West Shore Lake Pontchartrain, LA Hurricane and Storm Dramage Risk Reduction Project, WSLP-SP1, Site Preparation Contract 1, St. Charles Parish and John the Baptiste Parish, LA
Solicitation Number: W912P822B0029
2. DATE ISSUED 3. DATE OPENED PAGE
10-Feb-22 1 0F __ PAGES
DATE SIGNED
7A. ITEM 7C. EST. D. UNIT E. UNIT F. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 Mobilization & Demobilization 1 JOB $367,000.00 $367,000.00 $411,000.00 $411,000.00 $275,000.00 $275,000.00 $182,732.45 $182,732.45 $349,900.00 $349,900.00 $30,878.00 $30,878.00 $47,500.00 $47,500.00 $260,000.00 $260,000.00 $535,000.00 $535,000.00 $175,000.00 $175,000.00 $475,000.00 $475,000.00
Traffic Control and Coordination -
CANCELLED 1 $196,732.45 $196,732.45 $15,782.00 $15,782.00
0003 Truck Wash-Down Racks 1 JOB $114,000.00 $114,000.00 $90,000.00 $90,000.00 $10,000.00 $10,000.00 $187,732.45 $187,732.45 $21,600.00 $21,600.00 $38,000.00 $38,000.00 $26,350.00 $26,350.00 $22,500.00 $22,500.00 $25,000.00 $25,000.00 $15,000.00 $15,000.00 $35,000.00 $35,000.00
0004 Clearing and Grubbing 1 $789,000.00 $789,000.00 $800,000.00 $800,000.00 $1,205,000.00 $1,205,000.00 $197,732.45 $197,732.45 $499,800.00 $499,800.00 $58,000.00 $58,000.00 $1,689,000.00 $1,689,000.00 $615,000.00 $615,000.00 $725,000.00 $725,000.00 $270,000.00 $270,000.00 $190,000.00 $190,000.00
0005 Sand Fill
0005AA First 38,980 Ton 38,980 TON $23.00 $896,540.00 $7.50 $292,350.00 $11.30 $440,474.00 $9.43 $367,581.40 $26.40 $1,029,072.00 $24.15 $941,367.00 $10.50 $409,290.00 $12.70 $495,046.00 $14.25 $555,465.00 $11.00 $428,780.00 $10.00 $389,800.00
0005AA All Over 38,980 Ton 25,990 TON $21.00 $545,790.00 $7.50 $194,925.00 $11.30 $293,687.00 $11.65 $302,783.50 $9.00 $233,910.00 $22.66 $588,933.40 $10.50 $272,895.00 $12.70 $330,073.00 $14.10 $366,459.00 $9.00 $233,910.00 $10.00 $259,900.00
0006 Maintenance Surfacing 750 TON $75.00 $56,250.00 $50.00 $37,500.00 $48.00 $36,000.00 $305.31 $228,982.50 $93.00 $69,750.00 $22.66 $16,995.00 $55.00 $41,250.00 $75.00 $56,250.00 $55.00 $41,250.00 $88.00 $66,000.00 $65.00 $48,750.00
$2,768,580.00 $1,825,775.00 $2,260,161.00 $1,664,277.20 $2,204,032.00 $1,689,955.40 $2,486,285.00 $1,778,869.00 $2,248,174.00 $1,188,690.00 $1,398,450.00
0007 Sand Fill - OW1 0007A A First 19,520 Ton 19,520 TON $24.00 $468,480.00 $7.50 $146,400.00 $11.30 $220,576.00 $6.23 $121,609.60 $26.40 $515,328.00 $22.98 $448,569.60 $10.50 $204,960.00 $13.00 $253,760.00 $17.30 $337,696.00 $8.00 $156,160.00 $9.25 $180,560.00 0007A B All Over 19,460 Ton 13,020 TON $24.00 $312,480.00 $7.50 $97,650.00 $11.30 $147,126.00 $6.85 $89,187.00 $9.00 $117,180.00 $22.66 $295,033.20 $10.50 $136,710.00 $13.00 $169,260.00 $15.20 $197,904.00 $7.50 $97,650.00 $9.25 $120,435.00
$780,960.00 $244,050.00 $367,702.00 $210,796.60 $632,508.00 $743,602.80 $341,670.00 $423,020.00 $535,600.00 $253,810.00 $300,995.00
0008 Sand Fill - OW1
0008AA First 19,520 Ton 19,460 TON $24.00 $467,040.00 7.50 $145,950.00 $11.30 $219,898.00 6.23 $121,235.80 $26.40 $513,744.00 23.64 $460,034.40 $10.50 $204,330.00 13.25 $257,845.00 17.40 $338,604.00 $8.00 $155,680.00 9.25 $180,005.00
0008AB All Over 19,460 Ton 12,980 TON $24.00 $311,520.00 7.50 $97,350.00 $11.30 $146,674.00 6.85 $88,913.00 $9.00 $116,820.00 23.64 $306,847.20 $10.50 $136,290.00 13.25 $171,985.00 15.60 $202,488.00 $7.50 $97,350.00 9.25 $120,065.00
$778,560.00 $243,300.00 $366,572.00 $210,148.80 $630,564.00 $766,881.60 $340,620.00 $429,830.00 $541,092.00 $253,030.00 $300,070.00
$4,328,100.00 $2,313,125.00 $2,994,435.00 $2,085,222.60 $3,467,104.00 $3,200,439.80 $3,168,575.00 $2,631,719.00 $3,324,866.00 $1,695,530.00 $1,999,515.00
B. BID SECURITY (Type and amount) $3,000,000
C. AMENDMENTS ACKNOWLEDGED Yes
NO. 10
A. OFFEROR SNA Contracting, LLC
B. BID SECURITY (Type and amount) $3,000,000.00
C. AMENDMENTS ACKNOWLEDGED Yes
B. BID SECURITY (Type and amount) $3,000,000.00
C. AMENDMENTS ACKNOWLEDGED Yes
NO. 8
A. OFFEROR Onshore Materials, LLC
B. BID SECURITY (Type and amount) $3,000,000.00
C. AMENDMENTS ACKNOWLEDGED Yes
Total Option Work 1 (OW1)
Total Option Work 2 (OW2)
TOTAL BASE WORK + OW1 + OW2:
OPTION WORK 1 (OW1)
OPTION WORK 2 (OW2)
Total Base Work
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY (Type and amount) $3,000,000.00
C. REASONABLE CONTRACT
West Shore Lake Pontchartrain, LA Hurricane and Storm Dramage Risk Reduction Project, WSLP-SP1, Site Preparation Contract 1, St. Charles Parish and John the Baptiste Parish, LA
(Including Profit)
C. AMENDMENTS ACKNOWLEDGED - Yes
6. NUMBER OF AMENDMENTS ISSUED: 8
A. HIRED LABOR A. OFFEROR B&K Construction Co., LLC
NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) Prescribed by GSA - FAR (48 CFR) 53.236-1
ABSTRACT OF OFFERS - CONSTRUCTION Solicitation Number: W912P822B0029
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
SIGNATURE
4. ISSUING OFFICE
US ARMY ENGINEER DISTRICT, MVN (NOD)
7400 Leake Avenue
Contract Specialist
Veronica Garner-Flint Contracting Officer
BASE WORK
7B. DESCRIPTION OF OFFERED ITEM
(Check A, B or C and complete D, E, and F)
New Orleans, LA 70118-3651
Small Business Set Aside
5. PROJECT TITLE
B. BID SECURITY (Type and amount) 20%
C. AMENDMENTS ACKNOWLEDGED - YesC. AMENDMENTS ACKNOWLEDGED -Yes
A. OFFEROR Cycle Construction
C. AMENDMENTS ACKNOWLEDGED Yes
B. BID SECURITY (Type and amount) $3,000,000.00
A. OFFEROR J. Star Enterprises, Inc.
8. GOVERNMENT ESTIMATE
Cori Caimi
NO. 1 NO. 2
B. BID SECURITY (Type and amount) $3,000,000.00 B. BID SECURITY (Type and amount) $3,000,000.00
C. AMENDMENTS ACKNOWLEDGED Yes
NO. 6
B. BID SECURITY (Type and amount) 20%
C. AMENDMENTS ACKNOWLEDGED Yes
NO. 5
A. OFFEROR Justin J. Reeves, LLC
9. OFFERS
A. OFFEROR Lemoine-Frazier JV, LLCA. OFFEROR Forrester & Associates, LLC
NO. 3
29-Mar-22
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
NO. 4 NO. 7
A. OFFEROR MTC Construction, LLC
NO. 9
A. OFFEROR Phylway Construction, LLC
29 March 2022
| 2022-03-29T14:53:35-0500 | |
| GARNER- FLINT.VERONICA.FAYE.1230833504 |