This is a solicitation for a sand placement contract on the West Shore of Lake Pontchartrain in Louisiana. The United States Army Corps of Engineers, New Orleans District is seeking bids for clearing, grubbing, stump removal and placement of approximately 5950 linear feet of sand fill to an elevation of +3.0 feet. The base contract work consists of 3075 linear feet with optional additions of 1540 linear feet and 1335 linear feet. Access to the project site will utilize the West Shore Lake Pontchartrain Access Road "J". The pre-bid meeting was held on February 9th, 2022 and all questions are due by February 23rd, 2022. Bids for the work are due by March 29th, 2022. The contract is valued between $1,000,000 and $5,000,000.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
West Shore Lake Pontchartrain, LA Hurricane and Storm Damage Risk Reduction Project, WSLP-SP1, Site Preparation Contract 1, St. Charles Parish and John the Baptist Parish, LA (ED-22-013) has been amended to:
1. Extend the offer due date to 29 March 2022 at 11:00am
2. Provide Conference Line Information
3. Respond to Questions
4. Update Plans and Specif ications
1. CONTRACT ID CODE PAGE OF PAGES
1 15
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Mar-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P822B0029
X 9B. DATED (SEE ITEM 11)
08-Feb-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Mar-2022
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P822B0029
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0006
INSTRUCTIONS TO BIDDERS
INSTRUCTION TO BIDDERS
Due to the response for COVID-19, most federal employees have been mandated to telework, and currently only authorized personnel are allowed access to the District buildings throughout USACE. As a result, we have implemented the below procedures for all current and future bid openings, until such restrictions have been lifted and normal access has resumed at the MVN HQ Building.
Electronic Submission of Bids:
MVN will utilize email for receipt of electronic bids under IFB Solicitations. In order to submit an electronic bid please follow these steps:
Send an email containing your name, email address and proposal to BOTH the following Contracting Officer and Contract Specialist associated with the IFB:
Contracting Officer – Ms. Veronica Garner-Flint email: Veronica.Garner- Flint@usace.army.mil Contract Specialist – Ms. Cori Caimi, email: Cori.A.Caimi@usace.army.mil
Once the Contracting Officer or Contract Specialist receives your Proposal, you will then receive a confirmation email stating your Proposal was received.
The Bid Opening is currently scheduled for Tuesday, March 29, 2022 at 11:30 AM CST.
The Contracting Officer and Contract Specialist will begin downloading bids at 11:00 AM CST, which is the bid receipt cutoff time. All bids received after 11:00 AM CST on Tuesday, March 29, 2022 will be considered late.
Audio Teleconference Bid Opening Information:
Bid Opening will be held on Tuesday, March 29, 2022 at 11:30 AM CST. Please use the following call-in information to attend the meeting:
Toll-Free: 844-291-5489 Access Code: 6859482
Following the conclusion of the bid opening, the Bid Abstract will be uploaded to SAM website under this solicitation, within 24 hours.
Question 1:
In Amendment No. 3, Section 31 11 00.00 12 “Clearing and Grubbing”, paragraph 3.4.1 revisions have caused confusion amongst potential clearing contractors. Is it the intent of the Government to have the Contractor place all grubbed material (stumps) and existing fallen trees which lie within the 100’ clearing limits, outside the sand base and have all vegetation which exist within the 100’ clearing limits disposed of offsite or burned?
Response 1:
Yes, that is the intent.
Question 2:
In regards to the clearing and grubbing of the future levee area:
Specification section 31 11 00.00 12 paragraph 3.2.5.1 first sentence states “The entire area within the construction limits shall be cleared.” Is it the intent to clear from Right of Way to Right of Way or just in the limits of sand placement as shown on Drawing C-004 Detail H1?
Response 2:
The intent is to clear just in the limits of sand placement as shown on Drawing C-004 Detail H1.
Question 3:
Section 31 24 00.00 12 Paragraph 3.2 Sand Fill Construction states the sand fill shall be place in a bullnose configuration to minimize the amount of soft material trapped underneath the sand fill and to minimize the mud wave forming ahead of the sand fill. If a significant mud wave forms even though placement is following the bullnose construction procedure such that continued placement of sand would trap soft material trapped underneath the sand fill or overtake the sand fill, will the contractor be required to remove the mud wave forming ahead of the placement or will this be compensable by change order?
Response 3:
If a mud wave forms during sand fill placement which the COR deems to be removed, the contractor shall remove such material and place it outside the sand fill section at no additional cost to the Government.
Question 4:
Section 31 11 00.00 12 allows grubbed material to be placed outside of the footprint of the sand placement; however, above surface vegetation such as grass, bushes, weeds and down timber snags shall be removed from the project or burned. Considering most of the clearing is a substantial quantity of marsh grasses and occasional downed timber snags it is very costly to remove and dispose of the vegetation as classified by the specifications. Burning in the marsh areas with no easy access for fire control is risky, and to burn marsh grasses with attached wet roots is near impossible to burn productively. Would the government consider allowing for cutting of the marsh grass and chipping of the down timber snags and allowing cut grass and chips to displace with the muck wave.
Response 4:
No.
Question 5:
Section 01 57 20.00 paragraph 3.3 states significant work restrictions when colonial nesting wading birds or bald eagle nests are found in the vicinity of the work. In the event work restrictions are placed due to the discovery of nests with given distance and work restrictions will a change order be issued to compensate the contractor for standby and work restrictions?
Response 5:
Yes.
Question 6:
If submerged trees that are clearly from the original logging and clearing of the alignment are found disposed of below the mud surface will their relocation be compensated under change order as this would require additional effort in grubbing.
Response 6:
No.
Question 7:
Section 31 11 00.00 12 paragraph 3.3 Grubbing refers to Section 31 24 00.00 12 Sand Fill paragraph 2.1 Materials regarding what is to be removed. We just want to confirm the intent is to removed concentrated masses of unsuitable sticks, branches and roots AND the stumps.
Response 7:
Yes, that is the intent.
Question 8:
Will contractor be required to provide scales for sand measurement and payment.
Response 8:
Yes.
Question 9:
52.236-4 (c) requires the contractor to provide transportation such as an airboat or marsh buggy to Government personnel for the purpose of inspecting the work in process and documenting the progress of work for approving request for payments. Will contractor need to provide this for times the contractor will not be present, or will the government only require this piece of equipment when the contractor is present and working?
Response 9:
Required only when the Contractor is present.
Question 10:
Given the recent nature of fuel escalations can the government allow fuel escalation payments with basing fuel on a specific stated price in the bid.
Response 10:
No.
Question 11:
Section 01100 – 16 states permissible hours of work between 7am and 7pm, would the government consider adjusting the permissible work hours to daylight hours?
Response 11:
No.
Question 12:
Please provide details of the settlement plate required by the contract. A simple plate seems likely to displace with the mud wave.
Response 12:
Settlement Plate Details to be added to plans.
Question 13:
Section 32 15 00.00 12 Paragraph 1.6.2.2 states testing of surfacing material shall be performed at a minimum frequency of one set of tests per day surfacing material is placed. Given this is placed as needed for maintenance of access road J, would the government consider just one initial test of the material instead of testing every day material is placed?
Response 13:
Initial test will be required. Specifications to be changed.
Question 14:
Section 01100 paragraph 9 (d) was amended stating only one vehicle or equipment at a time will be allowed to cross over the entire width of the pipeline crossing. Please confirm the pipeline crossings allow only one truck to cross at a time over the length of the crossings and if that is what the supervision required at the pipeline crossings will be responsible for assuring beyond the axle and total weight limitations.
Response 14:
Contract only allows single vehicle traffic over all pipelines.
Question 15:
Section 01 55 26.00 12 Traffic Control and Coordination Paragraph 3.3.2 requires a traffic engineer or traffic control supervisor to inspect the project at 30-day intervals with a report issued with each inspection. Considering the minimal amount of traffic control required on the access road can the government waive this requirement.
Response 15:
Traffic Control and Coordination to be removed from solicitation.
Question 16:
Since the job is bid by the ton, what is the purpose for the settlement plates? Can they be eliminated?
Response 16:
1st part: Purpose is to determine for Government purposes the final sand thickness. 2nd part: No.
Question 17:
Since the job is bid by the ton, can the requirement for original and final cross sections be eliminated? Or does the USACE intend to verify and adjust the final delivered quantities based on the final volume measure?
Response 17:
1st part: No. 2nd part: No, quantity is measured by the ton.
Question 18:
In the question listed as number 13 in Amendment 0001 (number 6 in Amendment 0003), it is phrased “Government furnished sand” in asking the question. With that option to use sand from the USACE stockpile, does the contractor have to furnish the scales to provide sand by the ton?
What scale certification is acceptable? Plans seem to indicate use of the stockpile, as dust control is only from the sand stockpile to the levee, not from Airline Highway?
Response 18:
1st part: Yes. 2nd part: State scale certification. 3rd part: Intent is to use Government furnished sand stockpile.
Question 19:
With the scheduling of the scale certification by the local authority being beyond the control of the contractor, and with the very tight schedule for completion, will the USACE consider allowing time for any delay to the scale certification?
Response 19:
No.
Question 20:
If State scale certification is acceptable there will be scale/scanner cert fees, but will a Weighmaster License and Weighmaster be required for the scale usage?
Response 20:
No.
Question 21:
With the extreme volatility in the energy market would the USACE consider adding a fuel escalation clause to the contract for the sand deliveries and the tree disposal?
Response 21:
No.
Question 22:
There is an exclusion of off-road trucks, but with the need to keep the dump trucks from getting stuck traversing the sand, the sand must be kept wet (or add truck mats) for the possible 6000 feet of sand haul road: would the USACE allow use of an off-road water truck?
Response 22:
Yes, an off-road water truck is allowed along the levee alignment where sand is being placed. Off-road trucks are not allowed on the access road or in the stockpile area.
Question 23:
Note 2 on the Existing Condition Typical Section of sheet C-004 states “Contractor will encounter standing water along Project. Depth will vary.” Will time still be allowed for Lake Pontchartrain high tide during wind events?
Response 23:
Time extensions in accordance with the Default clause will be issued if high tides prevent sand placement.
Question 24:
Will crane mats be an acceptable alternate to the airboat or marsh buggy for USACE access required per 52.236-4(c)?
Response 24:
No.
Question 25:
Will any sand loss due to tides be considered the contractor’s responsibility?
Response 25:
No, refer to Damage to Permanent Work clause.
Question 26:
The USACE has made SWPPP measure costs incidental to other work, but have not provided any proposed plan or erosion control measures: is silt fence to be required anywhere? Note 2 on the Existing Condition Typical Section of sheet C-004 states “Contractor will encounter standing water along Project. Depth will vary.” What erosion control measures are required in the water?
Are turbidity curtains required anywhere?
Response 26:
1st part: No. 2nd part: None. 3rd part: No.
Question 27:
Section 01 57 23.00 12, part 1.8.1 states that “At the Contractor's option, the structural practices shall include either of the following devices.”, but none are listed: please advise what Structural Controls for erosion control are expected?
Response 27:
Refer to paragraph 1.8.1.1.
Question 28:
Per the answer to questions the contractor is required to clear from station 945 to 973+75 in the base bid: what erosion control measures are required for skidding trees in standing water for removal and disposal?
Response 28:
None required.
Question 29:
Is this Solicitation subject to the Executive Order 14026 minimum wage of $15 per hour?
Response 29:
Executive Order 14026 applies:
1. To solicitations issued on or after January 30, 2022, and their resulting contracts.
2. To new contracts awarded without a prior solicitation (e.g., a purchase order under part 13), on or after January 30, 2022.
3. To new contracts with a prior solicitation awarded on or after March 31, 2022.
4. To existing contracts, including procurements for recreational services, when extending, renewing, or exercising an option on the existing contract on or after the effective date of the rule. Contracting officers shall incorporate the amended clause in this rule at 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026, in the existing contracts through bilateral modifications.
In such a circumstance, if the contracting officer is unable to incorporate the clause in an existing contract through bilateral modification, then the contracting officer shall decline to extend, renew, or exercise the option on the existing contract.
5. In accordance with FAR 1.108(d), contracting officers are strongly encouraged to include the amended clause in other contracts awarded before March 31, 2022, with appropriate consideration.
Question 30:
Is this Solicitation subject to the Executive Order 13706 accrued paid time off of 1 hour per each thirty hours worked?
Response 30:
Executive Order 13706 applies to new contracts and replacements for expiring contracts with the Federal Government that result from solicitations issued on or after January 1, 2017 (or that are awarded outside the solicitation process on or after January 1, 2017) Under the Final Rule, Executive Order 13706 applies to four major categories of contractual agreements:
1. procurement contracts for construction covered by the Davis-Bacon Act (DBA);
2. service contracts covered by the McNamara-O’Hara Service Contract Act (SCA);
3. concessions contracts, including any concessions contracts excluded from the SCA by the Department of Labor’s regulations at 29 CFR 4.133(b); and
4. contracts in connection with Federal property or lands and related to offering services for Federal employees, their dependents, or the general public.
Furthermore, any subcontract of a covered contract that (like the upper-tier contract) falls into one of these four categories is subject to the paid sick leave requirements.
Procurement Contracts for Construction Under the Final Rule, any contract covered by the DBA and its implementing regulations is subject to the Executive Order’s requirements. The Executive Order does not apply, however, to contracts that are subject only to the Davis-Bacon Related Acts, i.e., Acts under which Federal agencies provide financial and other assistance to construction projects through grants, loans, guarantees, insurance and other methods, but do not directly procure construction services.
Service Contracts Under the Final Rule, both procurement and non-procurement contracts that are subject to the SCA and its implementing regulations are subject to the Executive Order’s requirements.
Question 31:
Would the USACE provide the estimated quantity for the items they have bid on a JOB basis?
Response 31:
JOB quantities as requested:
Clearing and Grubbing: Approx 16 acres Settlement plates 21
Question 32:
Since all sand loads must cross the gas main corridor, are all loads limited to 72,000 pounds total weight (per Amendment 0003, Section 01100)?
Response 32:
Yes.
Question 33:
Does the one vehicle at a time limit apply to the entire approximate 400 foot width of the gas main corridor (per Amendment 0003, Section 01100)?
Response 33:
Limit applies only to crossing of pipelines.
Question 34:
Does one man have to be staffed at the gas main corridor at all times to limit vehicle usage (per Amendment 0003, Section 01100) for the entire 400 foot width?
Response 34:
Yes.
Question 35:
Section 01 57 23.00 12, Part 3.5(a) provides “placement of geotextile” as an item of work: where is it used, and will a pay item be added?
Response 35:
No geotextile is required by this contract. Section will be revised.
Question 36:
SECTION 31 24 00.00 12, Part 3.3.1.4 provides for a speed limit of 15 mph “within the construction easement area”: does this apply to the Access Road also?
Response 36:
Yes.
SPECIFICATIONS:
SECTION 00010
Page 00010-3 thru 6. Delete the Bidding Schedule in its entirety and substitute the attached revised Bidding Schedule, page 00010-3 thru 6.
SECTION 01 55 26.00 12
Delete “Section 01 55 26.00 12” in its entirety.
SECTION 01 57 23.00 12
Page 6, paragraph 3.5 (a) Delete subparagraph “(a) Job description…”in its entirety and substitute the revised subparagraph (a) as follows:
“(a) Job description. The work consists of clearing, grubbing, sand placement, and other incidental work.”
Page 6, paragraph 3.5 (b) Delete subparagraph “(b) Activity sequence…”in its entirety and substitute the revised subparagraph (b) as follows:
“(b) Activity sequence. Contractor shall clear and grub areas to receive sand fill and proceed to place sand fill to the lines and grades as shown on the drawings.”
SECTION 32 15 00.00 12
Page 3, paragraph 1.6.2.2 Testing. Delete the 1st sentence “Testing of surfacing materials…” in its entirety and substitute the revised sentence as follows:
“One initial set of testing of surfacing materials shall be performed.”
DRAWINGS:
SHEET IDENTIFICATION. Delete drawings G-03 and C-005 in their entirety and substitute the attached revised drawings SHEET ID No. G-03 and C-005.
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 22-Mar-2022 11:00 AM to 29-Mar-2022 11:00 AM.
CLIN 0002
The CLIN description has changed from Traffic Control and Coordination to Traffic Control & Coor - CLIN Cancelled.
The CLIN extended description has changed from:
To:
CLIN Cancelled * DO NOT BID The pricing detail quantity has decreased by 1.00 from 1.00 to 0.00.
The following have been added by full text:
AMENDMENT 0006
SECTION 00010 – BIDDING SCHEDULE
West Shore Lake Pontchartrain, Hurricane and Storm Damage Risk Reduction Project, WSLP-SP1 Site Preparation Contract 1, St. John the Baptist and St. Charles Parishes, LA
Item DESCRIPTION Estimated Quantity
Unit Unit Price Estimated Amount
BASE WORK
0001 Mobilization and Demobilization 1 JOB
*0002 Traffic Control and Coordination -
CANCELLED
DO NOT BID
0003 Truck Wash-Down Rack 1 JOB
0004 Clearing and Grubbing 1 JOB
0005 Sand Fill
0005AA First 38,980 Ton 38,980 TON
0005AB All Over 38,980 Ton 25,990 TON
0006 Maintenance Surfacing 750 TON
TOTAL BASE WORK: $
OPTIONAL WORK 1 (OW1)
0007 Sand Fill - OW1
0007AA First 19,520 Ton 19,520 TON
0007AB All Over 19,520 Ton 13,020 TON
TOTAL OW1: $
OPTIONAL WORK 2 (OW2)
0008 Sand Fill – OW2
0008AA First 19,460 Ton 19,460 TON
0008AB All Over 19,460 Ton 12,980 TON
TOTAL OW2: $
TOTAL BASE WORK + OW1 + OW2 $
* Denoted change from previous Bidding Schedule.
**The unit "JOB" as used in this Bidding Schedule is synonymous with the term "Lump Sum" used elsewhere within these plans and specifications.
Award will be made as a whole to one bidder.
NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE
UNIT PRICE AND THE EXTENDED TOTAL OR ESTIMATED AMOUNT FOR ANY
ITEM, ITS BID SHALL BE DECLARED NON-RESPONSIVE AND THEREFORE
INELIGIBLE FOR AWARD.
NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or sub line items are materially unbalanced (See FAR 14.404-2, Rejection of Individual Bids).
NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.
NOTE 4: RAPID VENDOR PAYMENT: Web based instructions for the submission of invoices;
http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx
NOTE 5: OPTIONAL WORK ITEMS. The Government may require the delivery of the numbered line item(s), identified in the schedule as OPTIONAL WORK Items, in the quantities and prices stated in the schedule. The Contracting Officer may exercise the OPTIONAL WORK Items by written notice to the Contractor. Bidders shall bid on all items including optional items (see “Evaluation of Options” FAR 52.217-5). Failure to bid on all items will result in a non-responsive bid.
NOTE 6: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement. Evaluation of options will not obligate the Government to exercise the option(s). ** If an option is to be exercised at the time of contract award FAR17.208 shall be used in place of FAR 52.217-5
NOTE 7: TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF OPTIONAL
WORK.
(a) If OW1 is exercised under the terms of the contract, the time required for completion of the contract will be 40 calendar days in addition to the original contract duration of 145 calendar days established for the BASE WORK items specified in the Contract Clause entitled “COMMENCEMENT, PROSECUTION, AND COMPLETION
OF WORK (FAR 52-211-10 – APR 1984)”.
(b) If OW2 is exercised under the terms of the contract, the time required for completion of the contract will be 35 calendar days in addition to the original contract duration of 145 calendar days established for the BASE WORK items specified in the Contract Clause entitled “COMMENCEMENT, PROSECUTION, AND COMPLETION
OF WORK (FAR 52-211-10 – APR 1984)”.
EVALUATION OF SUBLINE ITEMS (Dec 2019 - AFARS 5152.211-9000).
Item Nos. 0004, 0006, and 0007 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its subline items.
(End of Clause)
VARIATIONS IN ESTIMATED QUANTITIES - SUBLINE ITEMS (Dec 2019 -
AFARS 5152.211-9001).
This variation in estimated quantities clause is applicable only to item Nos.
0004, 0006, and 0007.
(a) Variation from the estimated quantity in the actual work performed under any second or subsequent subline item or elimination of all work under such a second or subsequent subline item will not be the basis for an adjustment in contract unit price.
(b) Where the actual quantity of work performed for item Nos. 0004, 0006, and 0007 is less than 85% of the quantity of the first subline item listed under such item, the contractor will be paid at the contract unit price for that subline item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause at Federal Acquisition Regulation (FAR) 52.211-18, VARIATION IN ESTIMATED
QUANTITY.
(c) If the actual quantity of work performed under item Nos. 0004, 0006, and 0007 exceeds 115% or is less than 85% of the total estimated quantity of the subline item under that item and/or if the quantity of the work performed under the second subline item or any subsequent subline item under item Nos.
NONE exceeds 115% or is less than 85% of the estimated quantity of any such subline item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, VARIATION
IN ESTIMATED QUANTITY.
(End of Clause)
(End of Summary of Changes)