W912P820B0019 - WSLP STOCKPILE 1
Solicitation number
W912P820B0019
Issued by

About this file

This solicitation requests proposals for a federal construction contract to excavate, process, and stockpile clay material from the Bonnet Carre Spillway and haul it to a stockpile site within six miles. Work includes clearing, grubbing, and reconstructing an asphalt ramp. The magnitude of the acquisition is between $25 million and $100 million. Offerors must submit a bid bond and payment and performance bonds if awarded. The Department of the Army Corps of Engineers Engineering District New Orleans is the contracting agency. The bid opening was scheduled for September 7, 2020 according to the document, though an amendment may have changed this date. The contractor will be responsible for compliance with environmental regulations and permits as described.

View the file

Other files

File Type Posted
W912P820B0019 Abstract signed.pdf PDF
W912P820B0019-0012.pdf PDF
W912P820B0019-0010.pdf PDF
W912P820B0019-0008.pdf PDF
W912P820B0019-0007.pdf PDF
W912P820B0019-0005 .pdf PDF
W912P820B0019-0004.pdf PDF
W912P820C0019-P00003.pdf PDF
W912P820B0019-0002.pdf PDF
20B0019-0001.pdf PDF
A21_20B0019_Solicitation rev.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912P820B0019

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this modification is to provide answ ers to contractors questions and provide the revised section as attached. Please see attached continuation pages.

1. CONTRACT ID CODE PAGE OF PAGES

1 20

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Sep-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P820B0019

X 9B. DATED (SEE ITEM 11)

14-Nov-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Sep-2020

CODE

USACE, CONTRACTING DIVISION

ATTN: HPO CT - ROOM 184

7400 LEAKE AVE.

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

CONTINUATION PAGE FOR AMD 0009

SECTION 01 57 23.00 12

Delete this section in its entirety and substitute the attached revised Section 01 57 23.00 12 therefore.

Am_0009_WSLP Bonnet Carre Stockpile Contract 1 Ed 19-007

SECTION 01 57 23.00 12 Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

STORM WATER POLLUTION PREVENTION PLAN

PART 1 GENERAL

1.1 SCOPE

1.2 REFERENCES

1.3 MEASUREMENT AND PAYMENT

1.3.1 SWPPP

1.3.2 Silt Fence

1.3.3 Truck Wash Down Racks

1.4 DEFINITIONS

1.5 GENERAL

1.5.1 Environmental Assessment of Contract Deviations

1.5.2 Notice Of Intent

1.6 SUBMITTALS

1.7 RECORD RETENTION REQUIREMENTS

1.7.1 Documents

1.7.2 Plan Accessibility

1.7.3 Activity Records

1.7.4 LDEQ Correspondence

1.8 MAINTENANCE AND SURVEILLANCE FEES

1.9 EROSION AND SEDIMENT CONTROLS

1.9.1 Stabilization Controls

1.9.1.1 Unsuitable Conditions

1.9.1.2 No Activity for Less Than 21 Days

1.9.2 Structural Controls

1.9.2.1 Silt Fence Barrier

1.9.2.2 Truck Wash Down Racks

PART 2 PRODUCTS

2.1 COMPONENTS FOR SILT FENCE BARRIER

2.1.1 Silt Fence Geotextile

2.1.2 Wooden Posts and Steel T-Posts

2.1.3 Identification Storage and Handling

PART 3 EXECUTION

3.1 INSTALLATION OF SILT FENCE BARRIER

3.2 INSTALLATION OF TRUCK WASH DOWN RACKS

3.3 MAINTENANCE

3.3.1 Silt Fence Barrier Maintenance

3.4 INSPECTIONS

3.4.1 General

3.4.2 Inspections Details

3.4.3 Inspection Reports

3.5 NOTICE OF TERMINATION

3.6 ADDITIONAL INFORMATION

SECTION 01 57 23.00 12 Page 2

-- End of Section Table of Contents --

SECTION 01 57 23.00 12 Page 3

STORM WATER POLLUTION PREVENTION PLAN

PART 1 GENERAL

1.1 SCOPE

The work specified in this section consists of the Contractor implementing, and diligently pursuing all measures required in the Storm Water Pollution Prevention Plan (SWPPP)for the Government-furnished stockpile areas outside of the Bonnet Carre spillway. The SWPPP consists of this Section, Section 01 57 23.00 12, and any and all references and attachments including existing and future signed certification statements. The purpose of the SWPPP is to control soil erosion and the resulting sediment to the extent necessary to prevent sediment from leaving the contract rights-of-way, and prevent pollution of any water body caused by the runoff from the areas of construction activities under this contract, under the terms of PERMIT NO. LAR050000 (copy attached at the end of this section), and as specified herein and shown on the drawings. The requirements of these specifications are supplemental to and shall become part of the overall Environmental Protection Plan required by Section 01 57 20.00 12 ENVIRONMENTAL PROTECTION. The Contractor shall review the SWPPP to determine requirements for compliance. In addition, the Contractor shall ascertain that their subcontractors have reviewed the plan, and that they comply with its provisions. The Contractor shall ensure that all subcontractors sign, "Certification Statements #2 and #3" (blank forms attached at the end of this section).

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D 4491 (1999; R 2004e1) Water Permeability of Geotextiles by Permittivity

ASTM D 4632 (2008) Grab Breaking Load and Elongation of Geotextiles

ASTM D 4751 (2004) Determining Apparent Opening Size of a Geotextile

ASTM D 4833 (2000e1) Index Puncture Resistance of Geotextiles, Geomembranes, and Related Products

ASTM D 4873 (2002) Identification, Storage, and Handling of Geosynthetic Rolls and Samples

SECTION 01 57 23.00 12 Page 4

LOUISIANA DEPARTMENT OF ENVIRONMENTAL QUALITY (LDEQ)

PERMIT NO. LAR050000 (2016) Multi-Sector General Permit For Storm Water Discharges Associated With Industrial Activities

1.3 MEASUREMENT AND PAYMENT

1.3.1 SWPPP

No separate measurement and payment will be made for the implementation of the Storm Water Pollution Prevention Plan required by this section, except as specified in paragraphs "Silt Fence", and "Truck Wash-Down Racks".

Price and payment shall be distributed amongst the existing items.

1.3.2 Silt Fence

Measurement for silt fences satisfactorily placed will be made by the linear foot. Payment for silt fences as specified herein will be made at the contract unit price per linear foot for "Silt Fences". Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment, including geotextile, and performing all operations necessary for the placement and maintenance of silt fences throughout the contract period, including final dressing and cleanup of the disturbed areas.

1.3.3 Truck Wash Down Racks

Measurement and payment for truck wash down racks will be as specified in Section 01 57 23.01 12 TRUCK WASH DOWN RACKS.

1.4 DEFINITIONS

a. Construction Owner - The construction owner is the party that has operational control over plans and specifications including the ability to make changes to those items. The New Orleans District (Government) is the construction owner.

b. Construction Operators - The construction operators are the party having control over the plans and specifications and the party having day-to-day operational control over those activities at a project site which are necessary to ensure compliance with the SWPPP or other permit conditions. Both the Government and the Contractor are the construction operators.

c. Notice of Intent (NOI) - A document that is completed and submitted to the Louisiana Department of Environmental Quality as application for coverage to discharge under the PERMIT NO. LAR050000. (Copy provided at the end of this section.)

d. Notice of Termination (NOT) - A document that is completed and submitted to the Louisiana Department of Environmental Quality to terminate permission to discharge under the PERMIT NO. LAR050000. The NOT must be filed within 30 days after final stabilization of the construction site has been achieved or the Contractor is no longer the construction operator. (Copy provided at the end of this section.)

SECTION 01 57 23.00 12 Page 5

1.5 GENERAL

The Contractor shall implement the Storm Water Pollution Prevention Plan (SWPPP) specified in a manner which will meet the requirements of Section 01 57 20.00 12 ENVIRONMENTAL PROTECTION, and the requirements of the Louisiana Pollution Discharge Elimination System (LPDES) permit, LAR050000 effective May 9, 2016.

1.5.1 Environmental Assessment of Contract Deviations

The Contractor is advised that deviations from the SWPPP could result in the requirement for the Government to reanalyze the project from an environmental standpoint. Deviations from the SWPPP erosion control requirements as specified herein and as shown on the drawings which may have an environmental impact will require an extended review, processing, and approval time by the Government.

1.5.2 Notice Of Intent

Upon preparation of a complete SWPPP, the NOI will be submitted by the Government to the LDEQ as application for the Government's coverage under the terms of PERMIT NO. LAR05000. A copy of the Government's NOI, will be provided to the Contractor at the Pre-construction Conference for the Contractor's use in preparing their NOI. If a specific LPDES permit applicable to this construction item has been received from the LDEQ in response to the NOI, a copy of the specific LPDES permit will also be provided to the Contractor. The Contractor shall make any necessary modification to this SWPPP; attach the Construction Owner / Operator certification statement provided at the end of this section to the SWPPP;

and certify by signing the statement as the construction operator. The Contractor shall then submit an NOI to the LDEQ as application for his/her coverage under the terms of PERMIT NO. LAR05000, prior to initiating any construction activities. Certified mail is recommended for Contractor's proof of submittal. A copy of the Contractor's NOI submittal shall be provided to the Contracting Officer's representative at the time of submittal. LDEQ will provide a specific LPDES permit to the Contractor in response to that NOI submittal. The NOI's of both the Contractor and the Government, as well as the specific permits in response to the NOI, shall be posted at the job site by the Contractor. (Forms are attached at the end of this Section.)

1.6 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Stormwater Pollution Prevention Plan (SWPPP); G

A copy of the SWPPP shall be forwarded to Contracting Officer's representative for review and approval prior to Contractor mobilization to the project site.

SD-04 Samples

SECTION 01 57 23.00 12 Page 6

Silt Fence Geotextile; G, EDC

A sample, approximately 2 feet by 4 feet, of each geotextile that the Contractor plans to use shall accompany the certificate required below.

SD-07 Certificates

Silt Fence Geotextile; G, EDC

A mill certificate or affidavit shall be provided attesting that the geotextile meets the chemical, physical, and manufacturing requirements stated in this specification. The mill certificate or affidavit shall specify the actual Minimum Average Roll Values and shall identify the geotextile supplied by roll identification numbers. The Contractor shall submit a mill certificate or affidavit signed by a legally authorized official from the company manufacturing the geotextile.

Geotextile shall not be delivered to the site until the geotextile is approved by the Contracting Office.

1.7 RECORD RETENTION REQUIREMENTS

1.7.1 Documents

The Contractor shall retain copies of the SWPPP and all reports required by the general permit, and all records of data used to complete the NOI, for a period of at least three years from the date that the construction site is finally stabilized. Records of the NOI as well as any data used to complete it, the SWPPP, and any reports required by PERMIT NO. LAR050000 shall be retained by the permittee for at least three years from the date that the site is finally stabilized.

1.7.2 Plan Accessibility

A copy of the SWPPP and a copies of all permits received, shall be retained at the construction site (or other local location accessible to the State Administration Authority and the public) from the date of construction initiation to the date of final stabilization. The Contractor shall have a copy of the plan available at a central location on-site for the use of all operators and those identified as having responsibilities under the plan whenever they are on the construction site. A notice shall be posted near the main entrance to the construction site with the following information:

(1) the LPDES permit number for the project or a copy of the NOI if a permit has not yet been assigned; (2) the name and telephone number of a local contact person; (3) a brief description of the project; and (4) the location of the SWPPP if the site is inactive or does not have an on-site location to store the plan.

1.7.3 Activity Records

The dates of the following activities shall be recorded:

(1) Major grading activities occurred.

(2) Construction activities temporarily or permanently ceased.

SECTION 01 57 23.00 12 Page 7

(3) Stabilization measures were initiated.

1.7.4 LDEQ Correspondence

Any written correspondence with the LDEQ concerning the NOI, NOT, SWPPP, or discharges from any facility covered under PERMIT NO. LAR05000, shall be identified by permit number, if one has been assigned, and sent to the address below:

Louisiana Department of Environmental Quality Office of Environmental Services P.O. Box 4313 Baton Rouge, LA 70821-4313 Attn: Permits Division

1.8 MAINTENANCE AND SURVEILLANCE FEES

In accordance with the Contract Clause in Section 00700 entitled, "Permits And Responsibilities (FAR 52.236-7)," the Contractor shall, without additional expense to the Government, be responsible for paying any state required annual maintenance and surveillance fee for work associated with coverage under PERMIT NO. LAR05000.

1.9 EROSION AND SEDIMENT CONTROLS

The controls and measures required for controlling sediment during construction are described below.

1.9.1 Stabilization Controls

The stabilization practices to be implemented shall include any temporary measure to restrict erosion from the construction site. On the daily CQC Report, the Contractor shall record the dates when the major grading activities occur, (e.g., clearing and grubbing, excavation, stockpiling, and grading); when construction activities temporarily or permanently cease on a portion of the site; and when stabilization practices are initiated.

Except as provided in paragraphs "Unsuitable Conditions" and "No Activity for Less Than 21 Days," stabilization practices shall be initiated as soon as practicable, but no more than 14 days, in any portion of the site where construction activities have temporarily or permanently ceased.

1.9.1.1 Unsuitable Conditions

Where the initiation of stabilization measures by the fourteenth day after construction activity temporarily or permanently ceases is precluded by unsuitable conditions caused by the weather, stabilization practices shall be initiated as soon as practicable after conditions become suitable.

1.9.1.2 No Activity for Less Than 21 Days

Where construction activity will resume on a portion of the site within 21 days from when activities ceased (e.g., the total time period that construction activity is temporarily ceased is less than 21 days), then stabilization practices do not have to be initiated on that portion of the site by the fourteenth day after construction activity temporarily ceased.

Stabilization practices shall be initiated on that portion of the site by the fourteenth day in the case where construction activities will not resume within 21 days after construction activities have ceased.

SECTION 01 57 23.00 12 Page 8

1.9.2 Structural Controls

Structural practices shall be implemented to divert flows from exposed soils, temporarily store flows, or otherwise limit runoff and the discharge of pollutants from exposed areas of the site. Structural practices shall be implemented in a timely manner during the construction process to minimize erosion and sediment runoff. Location and details of installation and construction are shown on the drawings. The structural practices shall include either of the following devices.

1.9.2.1 Silt Fence Barrier

The Contractor shall provide silt fences as a temporary structural practice to minimize erosion and sediment runoff around the perimeter of the stockpile areas. Silt fences shall be properly installed, as shown on the contract drawings, to effectively retain sediment immediately after completing each phase of work where erosion would occur in the form of sheet and rill erosion (e.g. clearing and grubbing, excavation, embankment, and grading). Silt fences shall be installed in the locations indicated on the drawings. (Final removal of silt fence barriers shall be upon approval by the Contracting Officer.)

1.9.2.2 Truck Wash Down Racks

See Section 01 57 23.01 12 TRUCK WASH DOWN RACKS.

PART 2 PRODUCTS

2.1 COMPONENTS FOR SILT FENCE BARRIER

2.1.1 Silt Fence Geotextile

The geotextile shall consist of polymeric filaments which are formed into a stable network such that filaments retain their relative positions. The filament shall consist of a long-chain synthetic polymer composed of at least 85 percent by weight of ester, propylene, or amide, and shall contain stabilizers and/or inhibitors added to the base plastic to make the filaments resistant to deterioration due to ultraviolet and heat exposure.

Geotextile shall contain ultraviolet ray inhibitors and stabilizers to provide a minimum of six months of expected usable construction life at a temperature range of 0 to 120 degrees F. The silt fence geotextile shall meet the following requirements:

GEOTEXTILE FOR SILT FENCE

PROPERTY TEST PROCEDURE VALUE

Grab Breaking Load, pounds ASTM D 4632 220 minimum Grab Elongation at Ultimate, percent ASTM D 4632 20 maximum Puncture Strength, pounds ASTM D 4833 130 minimum AOS, U.S. Standard Sieve No. ASTM D 4751 30 - 70 Permittivity, per second ASTM D 4491 0.25 minimum

2.1.2 Wooden Posts and Steel T-Posts

The Contractor may use either rounded wooden posts or steel T-posts for silt fence construction. Wooden posts utilized for silt fence construction, shall conform to the contract drawings and shall be either

SECTION 01 57 23.00 12 Page 9 oak or pine wood. Steel T-posts utilized for silt fence construction, shall have a minimum weight of 1.33 pounds per linear foot and a minimum length of 7 feet.

2.1.3 Identification Storage and Handling

Geotextile shall be identified, stored and handled in accordance with

ASTM D 4873.

PART 3 EXECUTION

3.1 INSTALLATION OF SILT FENCE BARRIER

The silt fence shall be located and installed as indicated on the contract drawings. Geotextile shall be from a continuous roll cut to the length of the barrier to avoid the use of joints. When joints are unavoidable, geotextile shall be spliced together at a support post, with a minimum 6-inch overlap, and securely sealed. A trench shall be excavated approximately 4 inches wide and 6 inches deep on the upslope side of the location of the silt fence. The 4-inch by 6-inch trench shall be backfilled and the soil compacted over the geotextile. The geotextile shall be attached to the land side of the post with wire or other method recommended by the manufacturer and such that a 6-inch length of geotextile is left unattached at the bottom of the post, the unattached geotextile embedded in the trench and the trench backfilled. It is the responsibility of the Contractor to maintain the integrity of the silt fence. The Contractor shall immediately correct any deficiencies. The silt fence shall be promptly repaired or replaced should it become damaged or otherwise ineffective. The silt fence is to remain in place upon completion of the project, or as directed by the Contracting Officer. Its maintenance shall be continual for that period of time for which excavated materials are placed in the area of the silt fence.

3.2 INSTALLATION OF TRUCK WASH DOWN RACKS

Operation of truck wash down racks shall not include use of detergents.

Sediments resulting from operation of truck wash down racks shall not be permitted to pollute any receiving waters. Sediments shall be utilized in the job or disposed of as construction debris. Sediment retention measures shall be utilized as described in Section 01 57 23.01 12 TRUCK WASH DOWN

RACKS.

3.3 MAINTENANCE

The Contractor shall maintain the temporary and permanent vegetation, erosion and sediment control measures, and other protective measures in good and effective operating condition by performing routine inspections to determine condition and effectiveness, by restoration of destroyed vegetative cover, and by repair of erosion and sediment control measures and other protective measures. The following procedures shall be followed to maintain the protective measures.

3.3.1 Silt Fence Barrier Maintenance

Silt fences shall be inspected in accordance with paragraph "INSPECTIONS."

Any required repairs shall be made promptly. Close attention shall be paid to the repair of damaged silt fence resulting from end runs and undercutting. Should the geotextile on a silt fence decompose or become ineffective, and the barrier is still necessary, the geotextile shall be

SECTION 01 57 23.00 12 Page 10 replaced promptly. Sediment deposits shall be removed when deposits reach one-third of the height of the barrier. Sediments shall be utilized in the job or disposed of as construction debris. When a silt fence is no longer required, it shall be left in place.

3.4 INSPECTIONS

3.4.1 General

The Contractor shall inspect disturbed areas of the construction site, areas used for storage of materials that are exposed to precipitation that have not been finally stabilized, stabilization practices, structural practices, other controls, and area where vehicles exit the site at least once every fourteen (14) calendar days, before anticipated storm events (or series of storm events such as intermittent showers over one or more days) expected to cause a significant amount of runoff, and within 24 hours of the end of any storm that produces 0.5 inches or more rainfall at the site. Where sites have been finally stabilized, such inspection shall be conducted at least once every two weeks.

3.4.2 Inspections Details

Disturbed areas and areas used for material storage that are exposed to precipitation shall be inspected for evidence of, or the potential for, pollutants entering the drainage system. Erosion and sediment control measures identified in the SWPPP shall be observed to ensure that they are operating correctly. Discharge locations or points shall be inspected to ascertain whether erosion control measures are effective in preventing significant impacts to receiving waters. Locations where vehicles exit the site shall be inspected for evidence of offsite sediment tracking.

3.4.3 Inspection Reports

For each inspection conducted, the Contractor shall prepare a report summarizing the scope of the inspection, name(s) and qualifications of personnel making the inspection, the date(s) of the inspection, major observations relating to the implementation of the SWPPP, maintenance performed, and actions taken. The report shall be furnished to the Contracting Officer within 24 hours of the inspection as a part of the Contractor's daily CQC REPORT. A copy of the inspection report shall be maintained on the job site. Sample inspection reports (Exhibit D-2, Exhibit D-3, Exhibit D-4, and Table D-5) are included at the end of this section.

3.5 NOTICE OF TERMINATION

Upon stabilization and elimination of all storm water discharges authorized by PERMIT NO. LAR05000, or where the operator of all storm water discharges at a facility changes, a Notice of Termination (NOT) shall be certified and submitted by the Contractor to the Permits Division at the LDEQ. A copy of the NOT form is provided at the end of this section. Certified mail is recommended for proof of the NOT submittal. The NOT shall be submitted within 30 days of final stabilization of the construction site or when the Contractor is no longer the construction operator.

3.6 ADDITIONAL INFORMATION

(a) Job description. This contract consists of excavating and borrow

SECTION 01 57 23.00 12 Page 11 material within the Bonnet Carre spillway and hauling to a stockpile site located within St John the Baptist Parish, LA on prior used agricultural lands adjacent to Hwy 61.

(b) Activity sequence. Clearing, grubbing of stockpile sites, placement of silt fence at stockpile sites, excavation from the borrow sites and stockpiling at the stockpile site.

(c) Disturbed area. Multiple borrow sites will be excavated and one sites will be cleared and used for stockpile for a total of approximatley 105 acres combined.

(d) Runoff coefficient. The runoff coeffecient will not be changed substantially over existing coeeficient at the stockpile areas. There will be no change to runoff coefficient within the Bonnet Carre Spillway.

(e) Location. The location of excavation is within the Bonnet Carre Spillway. The locations of stockpiling are as shown in the contract drawings.

(f) Associated discharges. There are no expected discharges.

(g) Name of receiving waters / wetlands / special aquatic sites.

Excavation work takes place within the Bonnet Carre Spillway.

Stockpiling work takes place within agriculutural land.

(h) Permit requirements. Permit requirements are described in the copy of Permit No. LAR050000 attached at the end of this section.

(i) Endangered or Threatened Species Concerns. Construction activities are not likely to adversely affect threatened and endangered species. There is no critical habitat for any threatened or endangered species found in proximity to the construction activity. Colonial nesting wading birds (including but not limited to herons, egrets and ibis) and bald eagles may be found in proximity to construction activity and should be avoided to reduce the risk of injuring birds.

The nesting activity period generally extends from February 15 through September 15 for wading bird and September to May for bald eagles.

Presence of nesting wading birds or nesting bald eagles must be immediately reported to Patrick Smith at (504) 862-1583. Coordination by New Orleans District personnel with the U.S Fish and Wildlife Service may result in work related restrictions depending on the species of birds found nesting and its proximity to the work site.

(j) Borrow Pits are in southern part of Bonnet Carre Spillway. The Kugler cemetery (16SC51) is east of Stockpile Contract 1 (Easting 748094, Northing 3322021). The Kenner Cemetery (16SC50) is near the east boundary of the Spillway property (Easting 746683 northing 3321781). Both sites were listed on the National Register of Historic Places as the Kenner and Kugler Cemeteries Archaeological District in 1987. The boundaries for both cemeteries have been marked with stakes. Several cultural resources investigations have been conducted throughout the Spillway and no additional historic properties are deemed eligible for the National Register of Historic Places.

Access Road to the Hwy 61 stockpile area crosses the Mississippi River Sugar Belt Railroad south of Stockpile 1. Stockpile 1 has been modified to avoid the MRSBRR. In a 6 January 2020 letter regarding the WSLP, the State Historic Preservation Office determined that the MRSBRR

SECTION 01 57 23.00 12 Page 12 is eligible for the National Register of Historic Places. However, construction of Road J will have no adverse effect on the MRSBRR.

CERTIFICATION STATEMENT #1

SECTION 01 57 23.00 12 Page 13

Any person, including the construction owner/operator, signing documents (the SWPPP, modifications to the SWPPP, or other reports) under Part VI.G.

of PERMIT NO. LAR050000 shall make the following certification.

(Contract Title) (Permit Number)

(Document being Certified, such as SWPPP)

I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage this system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I also certify that a storm water pollution prevention plan, including both construction and post construction controls, has been prepared for the site in accordance with the permit and that such plan complies with approved State, Tribal and/or local sediment and erosion plans or permits and/or storm water management plans or permits. I am aware that signature and submittal of the Notice of Intent is deemed to constitute my determination of eligibility under one or more of the requirements of Permit Part I.A.3.e(1), related to the Endangered Species Act requirements. To the best of my knowledge, I further certify that such discharges and discharge related activities will not have an effect on properties listed or eligible for listing on the National Register of Historic Places under the National Historic Preservation Act, or are otherwise eligible for coverage under Part I.A.3.f of the permit. I am also aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.

Signature

Printed Name

Title

Company

Date

Telephone

CERTIFICATION STATEMENT #2

SECTION 01 57 23.00 12 Page 14

Any Contractor or subcontractor implementing any part of this plan must prepare and sign a copy of the following certification.

(Contract Title) (Permit Number)

I certify, under penalty of law, that I understand the terms and conditions of the Louisiana Pollutant Discharge Elimination System (LPDES) general permit that authorizes storm water discharges associated with construction activity from the construction site identified as part of this certification.

Firm Name:

Address:

Telephone No:

Signature: Title:

Date:

Any Contractor or subcontractor that does not meet the definition of "operator" that will conduct activities that may impact the effectiveness of the SWPPP control measures must prepare and sign the following certification.

(Contract Title) (Permit

Number)

I certify, under penalty of law, that I will coordinate, through the contractor, owner, or directly, with the Contractor (s) identified in the pollution prevention plan having responsibility for implementing storm water control measures to minimize any impact my actions may have on the effectiveness of these storm water control measures.

Firm Name:

Address:

Telephone No:

Signature: Title:

Date:

-- End of Section --

RESPONSES TO QUESTIONS - 0009

* Within the east side of Borrow Pits 1 and 2, west of the existing access road, there is a large drainage area (with water at the same elevation as the Barbars Canal to the east of the access road). What measures would be allowed to separate the drainage area from the Barbars Canal during high tide to mitigate the repeated flooding of Borrow Pits 1 and 2?

Government Response: Diking around the perimeter of the pits.

* There is a canal/drainage ditch within and along the west side of Borrow Pits 1 and 3 that also rises with the tides. What measures, if any, are not allowed in that area to prevent flooding during high tide?

Government Response: The contractor is responsible for water management within the borrow pits. Operations shall not impact adjacent contractors and shall not alter the drainage within the Spillway.

* Is the ditch around the Option Work stockpile part of the Base Bid or the Option Work?

Government Response: Optional Work 1.

* The access road width to the Stockpile shown on the new typical section (B3 on C-04) shows 24 feet wide with shoulders without the need for grading but the existing road is less than 24 feet in many places: is the necessary grading of the road, shoulders, and ditches to be incidental to what other items of work?

Government Response: Grading of all areas to receive surfacing is included in CLIN Item 0010, “Surfacing – OW2”, as stipulated in specification section 32 15 00.00 12.

* In Amendment 005, at Paragraph 52.236-4 PHYSICAL DATA, subparagraph (c), third sentence, it says: Only right turns into and out of the stockpile access road to and from Hwy 61 are allowed for all vehicles. Is it the intention that traffic returning to the Spillway must turn right (or west) into LaPlace to find a place to turn around?

Government Response: Yes.

* If traffic may go east on Airline, there is a partial curb island and no center turn lane on Airline Highway for trucks exiting the stockpile road turning left onto Highway 61. Is it acceptable to install lane drops and flagmen in each direction on Highway 61 to facilitate trucks entering the highway?

Government Response: No left turns will be allowed. Left turns are in violation of the approved project access permit from LaDOTD.

* Alternatively, in order to get trucks onto Airline/Hwy 61 from the stockpile access road would the installation of temporary signals be allowed?

Government Response: No.

* Will light plants and security guards be allowed at the stockpile site at night?

Government Response: Yes, provided any plan for lighting is submitted to the COR for approval.

The following have been modified:

RESPONSES TO QUESTIONS

Q.9-1: Since there was no hour established with the bid date, it is apparent that posting the bid date for Labor Day is only a placeholder. Could you please give the tentative expected date and time?

A.9-1: See response in Description of Amendment.

Q.9-2: Is the solicitation still to read “Work will be performed within the Bonnet Carre Spillway with an option … outside the Bonnet Carre Spillway …? The new Bidding Schedule indicates all of the stockpiling will be outside the spillway.

A.9-2: Solicitation description needs to be updated from "The work consists of excavating, processing and stockpiling of clay material. Work will be performed within the Bonnet Carre Spillway with an option to stockpile clay materials outside of the Bonnet Carre Spillway, but within 12 miles" to "The work consists of excavating, processing and stockpiling of clay material within the Bonnet Carre Spillway and hauling/stockpiling at a site outside the Bonnet Carre Spillway."

Q.9-3: With the Separator Geotextile and Surfacing listed as Optional Work, please confirm; is the Base Work to be quoted without surfacing for the Hwy 61 Stockpile Access? If so, is cement stabilization required to meet EM 385- 1-1 04B-13 through 15?

A.9-3: Base Work is to be quoted without Option Work Items as per Bid Schedule, Cement stabilization not required.

Q.9-4: Please confirm what minimum quantity of turnouts is required on the haul roads?

A.9-4: Number of turnouts from haul roads within the Spillway shall be determined by Contractor to accommodate his/her means and methods of hauling in the Spillway. One turnout is shown for accessing the stockpile site from the access road off of Hwy 61. How many maximum speed limit signs? Speed limit signs shall be spaced as per any/all applicable guidelines for such. Barring any such guidance, as a minimum 2 per direction of travel shall be placed along the access road leading to the stockpile

Q.9-5: Please confirm that the reduced 24 foot haul road width for two-way traffic is acceptable?

A.9-5: Yes.

Q.9-6: Part of new Paragraph 52.236-4, subparagraph (c) requires: “All vehicles shall come to a full stop at all intersections.” Will stop signs be required?

A.9-6: No

Q.9-7: Where access to Borrow Pit 3 crosses the Stockpile Contract 2 haul road, will the Contract 1 on-road dump truck traffic be required to yield to the off-road equipment?

A9-7: Yes

Q.9-8: What minimum measures are required at the gas main crossings? Are existing crossings considered to already be sufficient?

A.9-8: No additional measures are required.

Q.9-9: Does the new Section 31 05 19.04 12 Separator Geotextile completely delete the old one?

A.9-9: Yes.

Q.9-10: Are any additional culverts needed in the approximate 8400 feet of new access road to the stockpile site?

A.9-10: No.

Q.9-11: With the number of recent openings and durations of the Spillway, does the USACE have a current survey/estimate of sand overburden for the Borrow Pits?

A.9-11: Amendment P00003 issued on December 11, 2019 indicated updated elevations at boring locations to provide such an estimate. More recent surveys are not available.

Q.9-12: Will we be loading and unloading the materials from Government property?

A.9-12: The stockpile contract will require the contractor to develop a borrow pit in the Bonnet Carre Spillway, which is Government owned property and stockpile the borrow at a stockpile site that was acquired by the non-Federal Sponsor. The stockpile site is not owned by the Government but we have been granted permission to use the property as a stockpile site.

Q.9-13: Section 01 57 23.01 12, Para 1.1 states that a wash down rack must be installed "at the borrow site." Para

3.1 states that the wash down rack shall be located at a "point of egress from the construction site onto Hwy 61."

Drawing C-03 note 1 states that the washdown rack shall be located at the stockpile exit. Please clarify. Does this mean at the exit from the Bonnet Carre spillway onto US-61, at the Stockpile exit onto US-61, or both?

A.9-13: Both.

Q.9-14: Also will that wash down rack(s) constructed as a part of this contract be shared with other contractors hauling sand or clay out of the spillway or into the stockpile location during the life of this contract?

A.9-14: No

Q.9-15: If so, who is responsible for maintenance and/or repair?

A.9-15: Contractor shall be responsible for wash racks constructed under the contract.

Q.9-16: Will the access road at the stockpile location as a part of this contract be shared with other contractors hauling sand or clay into the location during the life of this contract?

A.9-16: Yes

Q.9-17: If so, which contractor will be responsible for maintenance?

A.9-17: Any Contractor utilizing the road is jointly responsible for maintenance.

Q.9-18: Will the asphalt access ramp that is required for this project be shared with other contractors hauling sand or clay out of the spillway during the life of this contract?

A.9-18: Yes.

Q.9-19: If so, which contractor will be responsible for maintenance and repairs that may occur?

A.9-19: The contractor for this contract.

Q.9-20: Are there specifications for the Silt Fence?

A.9-20: The specs for the silt fence were not in the amendment 00005. The specifications for such will be added.

Q.9-21: Is the bid opening still happening on Labor Day, September 7, 2020?

A.9-21: The bid opening date has changed. Please see Description of Amendment.

(End of Summary of Changes)